5-18B-31. Pre-qualification of design-builders--Elements of request for qualifications.
A purchasing agency shall pre-qualify design-builders for design-build contracts by advertising its request for qualifications in accordance with §5-18A-14. A request for qualifications shall contain the following elements:
(1)The identity of the purchasing agency;
(2)A description of the proposed public improvement;
(3)Budget limits for the proposed public improvement;
(4)The requirements the design-builder will be required to have; and
(5)The criteria and their relative weight for prequalification.

Source: SL 2010, ch 31, §70.

Structure South Dakota Codified Laws

South Dakota Codified Laws

Title 5 - Public Property, Purchases and Contracts

Chapter 18B - Procurement Of Public Improvements

Section 5-18B-1 - Plans and specifications--Advertisement--Availability.

Section 5-18B-2 - Certified check or cashier's check for percentage of bid or bid bond required.

Section 5-18B-3 - Check or bid bond requirement--Waiver.

Section 5-18B-4 - Surety bond or insurance contract required in bid, in contract, or by law.

Section 5-18B-5 - Negotiations if lowest responsive and responsible bid exceeds final estimated project cost.

Section 5-18B-6 - Certification regarding labor provided by nonresident subcontractors.

Section 5-18B-7 - Contractor's use tax liability.

Section 5-18B-8 - Forfeited funds accrue to funds provided for construction.

Section 5-18B-9 - Time limits--Return of checks--Return or destruction of bid bonds.

Section 5-18B-10 - Plans and specifications prepared by architect or engineer.

Section 5-18B-11 - Progress payments--Retention of funds from final payment--Interest.

Section 5-18B-12 - Bond or deposit of securities in lieu of retention of sums due for work performed.

Section 5-18B-13 - Occupancy before completion and acceptance.

Section 5-18B-14 - Project superintendent--Installment payments--Final payment.

Section 5-18B-15 - Architect or engineer may not be contractor or construction manager on project exceeding one hundred thousand dollars--Exemption.

Section 5-18B-16 - Unemployment compensation.

Section 5-18B-17 - Contractor's excise tax license.

Section 5-18B-18 - Contributions and interest due the Department of Labor and Regulation.

Section 5-18B-19 - Amendment or change order to existing contract.

Section 5-18B-20 - Design-build contracts.

Section 5-18B-21 - Design-builder to be authorized.

Section 5-18B-22 - Subletting of design services.

Section 5-18B-23 - Subletting construction or other services.

Section 5-18B-24 - Contracts with unlicensed or unqualified design-builder permitted if services sublet to licensed or qualified person.

Section 5-18B-25 - Request for proposals to contain performance criteria--Qualifications of developer.

Section 5-18B-26 - Performance criteria developer and design builder to perform separate roles.

Section 5-18B-27 - Performance criteria developer to be purchasing agency employee or engaged in accordance with statutorial procedures--Delegation.

Section 5-18B-28 - Development of performance criteria.

Section 5-18B-29 - Elements of design-build request for proposals--Time for mailing to pre-qualified design-builders.

Section 5-18B-30 - Design-build request not to be detailed--Drawings--Specifications--Standards.

Section 5-18B-31 - Pre-qualification of design-builders--Elements of request for qualifications.

Section 5-18B-32 - Deposit or bond submitted with proposal--Forfeiture.

Section 5-18B-33 - Proposals to be sealed--Contents.

Section 5-18B-34 - Confidentiality of proposals.

Section 5-18B-35 - Review and opinion of performance criteria developer--Submission to governing body.

Section 5-18B-36 - Acceptance of a proposal--Evaluation criteria scores.

Section 5-18B-37 - Rejection of design-build proposals--Solicitation of new proposals.

Section 5-18B-38 - Withdrawal of design-build proposal.

Section 5-18B-39 - Construction manager engagement.

Section 5-18B-40 - Services of construction manager.

Section 5-18B-41 - Manager-agent.

Section 5-18B-42 - Manager-at-risk.

Section 5-18B-43 - Criteria for construction manager engagement.

Section 5-18B-44 - Criteria for construction manager-at-risk engagement.

Section 5-18B-45 - Active involvement of licensed design professional required.

Section 5-18B-46 - Improvement projects that rely on federal funding from FAA.