5-18B-14. Project superintendent--Installment payments--Final payment.
The purchasing agency may appoint a competent superintendent who may be the architect or engineer furnishing the plans and specifications for the public improvement. The superintendent shall report to the purchasing agency or board every thirty days as to the progress and character of the work done by the contractor. Upon the reports of the superintendent, the purchasing agency shall make payments promptly to the contractor during the process of construction to the extent provided by the contract based on the value of the work done and materials furnished. The payments shall be divided into such installments as the board and the contractor may agree upon at the time of entering into the contract, and which shall be included in and be a part of the terms of the contract. No payment, however, constitutes an acceptance, in whole or in part, by the purchasing agency prior to making of the final payment and acceptance in full completion of the contract. Final payment of any sums due to the contractor shall be made within thirty days after the completion and acceptance of the public improvement by the purchasing agency.
Source: SL 2010, ch 31, ยง53.
Structure South Dakota Codified Laws
Title 5 - Public Property, Purchases and Contracts
Chapter 18B - Procurement Of Public Improvements
Section 5-18B-1 - Plans and specifications--Advertisement--Availability.
Section 5-18B-2 - Certified check or cashier's check for percentage of bid or bid bond required.
Section 5-18B-3 - Check or bid bond requirement--Waiver.
Section 5-18B-4 - Surety bond or insurance contract required in bid, in contract, or by law.
Section 5-18B-6 - Certification regarding labor provided by nonresident subcontractors.
Section 5-18B-7 - Contractor's use tax liability.
Section 5-18B-8 - Forfeited funds accrue to funds provided for construction.
Section 5-18B-9 - Time limits--Return of checks--Return or destruction of bid bonds.
Section 5-18B-10 - Plans and specifications prepared by architect or engineer.
Section 5-18B-11 - Progress payments--Retention of funds from final payment--Interest.
Section 5-18B-13 - Occupancy before completion and acceptance.
Section 5-18B-14 - Project superintendent--Installment payments--Final payment.
Section 5-18B-16 - Unemployment compensation.
Section 5-18B-17 - Contractor's excise tax license.
Section 5-18B-18 - Contributions and interest due the Department of Labor and Regulation.
Section 5-18B-19 - Amendment or change order to existing contract.
Section 5-18B-20 - Design-build contracts.
Section 5-18B-21 - Design-builder to be authorized.
Section 5-18B-22 - Subletting of design services.
Section 5-18B-23 - Subletting construction or other services.
Section 5-18B-26 - Performance criteria developer and design builder to perform separate roles.
Section 5-18B-28 - Development of performance criteria.
Section 5-18B-30 - Design-build request not to be detailed--Drawings--Specifications--Standards.
Section 5-18B-31 - Pre-qualification of design-builders--Elements of request for qualifications.
Section 5-18B-32 - Deposit or bond submitted with proposal--Forfeiture.
Section 5-18B-33 - Proposals to be sealed--Contents.
Section 5-18B-34 - Confidentiality of proposals.
Section 5-18B-36 - Acceptance of a proposal--Evaluation criteria scores.
Section 5-18B-37 - Rejection of design-build proposals--Solicitation of new proposals.
Section 5-18B-38 - Withdrawal of design-build proposal.
Section 5-18B-39 - Construction manager engagement.
Section 5-18B-40 - Services of construction manager.
Section 5-18B-41 - Manager-agent.
Section 5-18B-42 - Manager-at-risk.
Section 5-18B-43 - Criteria for construction manager engagement.
Section 5-18B-44 - Criteria for construction manager-at-risk engagement.
Section 5-18B-45 - Active involvement of licensed design professional required.
Section 5-18B-46 - Improvement projects that rely on federal funding from FAA.