5-18B-11. Progress payments--Retention of funds from final payment--Interest.
The contract may permit progress payments, but an amount necessary to complete the improvement shall be retained from the final payment until the contract is executed in full and the public improvement completed to the satisfaction and acceptance of the purchasing agency. However, if the contractor has furnished the purchasing agency all required records and reports and a final inspection has been made, the purchasing agency shall pay to the contractor interest as set by the governing body at a rate of not less than the category E rate of interest as established by §54-3-16 on the amounts retained and on the final payment due the contractor beginning thirty days after the work under the contract has been completed, as evidenced either by the completion date established by the architect's or engineer's letter of acceptance or by the use and occupancy of the public improvement. The interest shall continue until the date when payment is tendered to the contractor unless delay in payment has been the result of federal participation in the contract in which event interest may not begin until thirty days after payment by the federal authority involved. If a portion of a progress payment is retained, other than the final payment, the purchasing agency shall pay to the contractor interest as set by the purchasing agency at a rate of not less than the category E rate of interest as established by §54-3-16 on the amount retained beginning thirty days after the contractor has furnished the purchasing agency with all required records and reports and a progress inspection.
Source: SL 2010, ch 31, §50.
Structure South Dakota Codified Laws
Title 5 - Public Property, Purchases and Contracts
Chapter 18B - Procurement Of Public Improvements
Section 5-18B-1 - Plans and specifications--Advertisement--Availability.
Section 5-18B-2 - Certified check or cashier's check for percentage of bid or bid bond required.
Section 5-18B-3 - Check or bid bond requirement--Waiver.
Section 5-18B-4 - Surety bond or insurance contract required in bid, in contract, or by law.
Section 5-18B-6 - Certification regarding labor provided by nonresident subcontractors.
Section 5-18B-7 - Contractor's use tax liability.
Section 5-18B-8 - Forfeited funds accrue to funds provided for construction.
Section 5-18B-9 - Time limits--Return of checks--Return or destruction of bid bonds.
Section 5-18B-10 - Plans and specifications prepared by architect or engineer.
Section 5-18B-11 - Progress payments--Retention of funds from final payment--Interest.
Section 5-18B-13 - Occupancy before completion and acceptance.
Section 5-18B-14 - Project superintendent--Installment payments--Final payment.
Section 5-18B-16 - Unemployment compensation.
Section 5-18B-17 - Contractor's excise tax license.
Section 5-18B-18 - Contributions and interest due the Department of Labor and Regulation.
Section 5-18B-19 - Amendment or change order to existing contract.
Section 5-18B-20 - Design-build contracts.
Section 5-18B-21 - Design-builder to be authorized.
Section 5-18B-22 - Subletting of design services.
Section 5-18B-23 - Subletting construction or other services.
Section 5-18B-26 - Performance criteria developer and design builder to perform separate roles.
Section 5-18B-28 - Development of performance criteria.
Section 5-18B-30 - Design-build request not to be detailed--Drawings--Specifications--Standards.
Section 5-18B-31 - Pre-qualification of design-builders--Elements of request for qualifications.
Section 5-18B-32 - Deposit or bond submitted with proposal--Forfeiture.
Section 5-18B-33 - Proposals to be sealed--Contents.
Section 5-18B-34 - Confidentiality of proposals.
Section 5-18B-36 - Acceptance of a proposal--Evaluation criteria scores.
Section 5-18B-37 - Rejection of design-build proposals--Solicitation of new proposals.
Section 5-18B-38 - Withdrawal of design-build proposal.
Section 5-18B-39 - Construction manager engagement.
Section 5-18B-40 - Services of construction manager.
Section 5-18B-41 - Manager-agent.
Section 5-18B-42 - Manager-at-risk.
Section 5-18B-43 - Criteria for construction manager engagement.
Section 5-18B-44 - Criteria for construction manager-at-risk engagement.
Section 5-18B-45 - Active involvement of licensed design professional required.
Section 5-18B-46 - Improvement projects that rely on federal funding from FAA.