Section 5-18B-19 - Amendment or change order to existing contract.

5-18B-19. Amendment or change order to existing contract.
Any amendment or change order to an existing contract for construction, reconstruction, or remodeling of a public improvement does not need to be bid if:
(1)The contract contains unit prices for the same type or class of work;
(2)The change or extra work is necessitated by circumstances related to soils, utilities, or unknown conditions directly affecting the performance of the work that were not reasonably foreseeable at the time the underlying contract was let and the change or extra work is necessary to the completion of the public improvement; or
(3)The sum of the proposed amendment or change order plus the sum of all other prior unbid amendments or change orders, exclusive of change orders issued under subdivisions (1) and (2) of this section, does not exceed the following:
(a)For contracts not more than five hundred thousand dollars, the greater of twenty-five thousand dollars or fifteen percent of the base contract;
(b)For contracts exceeding five hundred thousand dollars but not more than two million five hundred thousand dollars, the greater of seventy-five thousand dollars or ten percent of the base contract; and
(c)For contracts exceeding two million five hundred thousand dollars, the greater of two hundred fifty thousand dollars or five percent of the base contract.

Source: SL 2010, ch 31, ยง58.

Structure South Dakota Codified Laws

South Dakota Codified Laws

Title 5 - Public Property, Purchases and Contracts

Chapter 18B - Procurement Of Public Improvements

Section 5-18B-1 - Plans and specifications--Advertisement--Availability.

Section 5-18B-2 - Certified check or cashier's check for percentage of bid or bid bond required.

Section 5-18B-3 - Check or bid bond requirement--Waiver.

Section 5-18B-4 - Surety bond or insurance contract required in bid, in contract, or by law.

Section 5-18B-5 - Negotiations if lowest responsive and responsible bid exceeds final estimated project cost.

Section 5-18B-6 - Certification regarding labor provided by nonresident subcontractors.

Section 5-18B-7 - Contractor's use tax liability.

Section 5-18B-8 - Forfeited funds accrue to funds provided for construction.

Section 5-18B-9 - Time limits--Return of checks--Return or destruction of bid bonds.

Section 5-18B-10 - Plans and specifications prepared by architect or engineer.

Section 5-18B-11 - Progress payments--Retention of funds from final payment--Interest.

Section 5-18B-12 - Bond or deposit of securities in lieu of retention of sums due for work performed.

Section 5-18B-13 - Occupancy before completion and acceptance.

Section 5-18B-14 - Project superintendent--Installment payments--Final payment.

Section 5-18B-15 - Architect or engineer may not be contractor or construction manager on project exceeding one hundred thousand dollars--Exemption.

Section 5-18B-16 - Unemployment compensation.

Section 5-18B-17 - Contractor's excise tax license.

Section 5-18B-18 - Contributions and interest due the Department of Labor and Regulation.

Section 5-18B-19 - Amendment or change order to existing contract.

Section 5-18B-20 - Design-build contracts.

Section 5-18B-21 - Design-builder to be authorized.

Section 5-18B-22 - Subletting of design services.

Section 5-18B-23 - Subletting construction or other services.

Section 5-18B-24 - Contracts with unlicensed or unqualified design-builder permitted if services sublet to licensed or qualified person.

Section 5-18B-25 - Request for proposals to contain performance criteria--Qualifications of developer.

Section 5-18B-26 - Performance criteria developer and design builder to perform separate roles.

Section 5-18B-27 - Performance criteria developer to be purchasing agency employee or engaged in accordance with statutorial procedures--Delegation.

Section 5-18B-28 - Development of performance criteria.

Section 5-18B-29 - Elements of design-build request for proposals--Time for mailing to pre-qualified design-builders.

Section 5-18B-30 - Design-build request not to be detailed--Drawings--Specifications--Standards.

Section 5-18B-31 - Pre-qualification of design-builders--Elements of request for qualifications.

Section 5-18B-32 - Deposit or bond submitted with proposal--Forfeiture.

Section 5-18B-33 - Proposals to be sealed--Contents.

Section 5-18B-34 - Confidentiality of proposals.

Section 5-18B-35 - Review and opinion of performance criteria developer--Submission to governing body.

Section 5-18B-36 - Acceptance of a proposal--Evaluation criteria scores.

Section 5-18B-37 - Rejection of design-build proposals--Solicitation of new proposals.

Section 5-18B-38 - Withdrawal of design-build proposal.

Section 5-18B-39 - Construction manager engagement.

Section 5-18B-40 - Services of construction manager.

Section 5-18B-41 - Manager-agent.

Section 5-18B-42 - Manager-at-risk.

Section 5-18B-43 - Criteria for construction manager engagement.

Section 5-18B-44 - Criteria for construction manager-at-risk engagement.

Section 5-18B-45 - Active involvement of licensed design professional required.

Section 5-18B-46 - Improvement projects that rely on federal funding from FAA.