South Dakota Codified Laws
Chapter 18B - Procurement Of Public Improvements
Section 5-18B-29 - Elements of design-build request for proposals--Time for mailing to pre-qualified design-builders.

5-18B-29. Elements of design-build request for proposals--Time for mailing to pre-qualified design-builders.
After a minimum of three design-builders have been pre- qualified in accordance with §5-18B-31, a design-build request for proposals shall be mailed to each pre-qualified design-builder. The minimum number of pre-qualified design-builders is not required for any improvement project that is complex in nature, requires close coordination of design and construction expertise, and does not require significant structural changes, additions, reconstruction, or new construction. The design-build request for proposals shall be prepared for each design-build contract containing the following elements:
(1)The identity of the purchasing agency which will award the design-build contract and the identity of the performance criteria developer;
(2)The procedures to be followed for submitting proposals, the criteria for evaluation of a proposal and its relative weight, and the procedures for making awards;
(3)The proposed terms and conditions for the design-build contract;
(4)The performance criteria, which shall include the following:
(a)The owners preliminary program of space needs and special requirements;
(b)Performance standards for materials and equipment; and
(c)Minimum system requirements and efficiencies;
(5)A description of the drawings, specifications, or other submittals to be submitted with the proposal, with guidance as to the form and level of completeness of the drawings, specifications, or submittals that is acceptable;
(6)A schedule for planned commencement and completion of the design-build contract;
(7)Budget limits for the design-build contract;
(8)Affirmative action, disadvantaged business, or set-aside goals or requirements for the design-build contract, if any;
(9)Requirements for performance and payment bonds, and insurance. These requirements shall meet the requirements of §5-21-1;
(10)The compensation, if any, to be given to design-builders submitting proposals who are not awarded the project;
(11)Whether project financing is in place;
(12)A schedule for payments to the design-builder;
(13)Site identification and geotechnical information if the site is owner-provided;
(14)Location of existing utilities and their capacity if the site is owner-provided; and
(15)Warranty and guarantee requirements.

Source: SL 2010, ch 31, §68.

Structure South Dakota Codified Laws

South Dakota Codified Laws

Title 5 - Public Property, Purchases and Contracts

Chapter 18B - Procurement Of Public Improvements

Section 5-18B-1 - Plans and specifications--Advertisement--Availability.

Section 5-18B-2 - Certified check or cashier's check for percentage of bid or bid bond required.

Section 5-18B-3 - Check or bid bond requirement--Waiver.

Section 5-18B-4 - Surety bond or insurance contract required in bid, in contract, or by law.

Section 5-18B-5 - Negotiations if lowest responsive and responsible bid exceeds final estimated project cost.

Section 5-18B-6 - Certification regarding labor provided by nonresident subcontractors.

Section 5-18B-7 - Contractor's use tax liability.

Section 5-18B-8 - Forfeited funds accrue to funds provided for construction.

Section 5-18B-9 - Time limits--Return of checks--Return or destruction of bid bonds.

Section 5-18B-10 - Plans and specifications prepared by architect or engineer.

Section 5-18B-11 - Progress payments--Retention of funds from final payment--Interest.

Section 5-18B-12 - Bond or deposit of securities in lieu of retention of sums due for work performed.

Section 5-18B-13 - Occupancy before completion and acceptance.

Section 5-18B-14 - Project superintendent--Installment payments--Final payment.

Section 5-18B-15 - Architect or engineer may not be contractor or construction manager on project exceeding one hundred thousand dollars--Exemption.

Section 5-18B-16 - Unemployment compensation.

Section 5-18B-17 - Contractor's excise tax license.

Section 5-18B-18 - Contributions and interest due the Department of Labor and Regulation.

Section 5-18B-19 - Amendment or change order to existing contract.

Section 5-18B-20 - Design-build contracts.

Section 5-18B-21 - Design-builder to be authorized.

Section 5-18B-22 - Subletting of design services.

Section 5-18B-23 - Subletting construction or other services.

Section 5-18B-24 - Contracts with unlicensed or unqualified design-builder permitted if services sublet to licensed or qualified person.

Section 5-18B-25 - Request for proposals to contain performance criteria--Qualifications of developer.

Section 5-18B-26 - Performance criteria developer and design builder to perform separate roles.

Section 5-18B-27 - Performance criteria developer to be purchasing agency employee or engaged in accordance with statutorial procedures--Delegation.

Section 5-18B-28 - Development of performance criteria.

Section 5-18B-29 - Elements of design-build request for proposals--Time for mailing to pre-qualified design-builders.

Section 5-18B-30 - Design-build request not to be detailed--Drawings--Specifications--Standards.

Section 5-18B-31 - Pre-qualification of design-builders--Elements of request for qualifications.

Section 5-18B-32 - Deposit or bond submitted with proposal--Forfeiture.

Section 5-18B-33 - Proposals to be sealed--Contents.

Section 5-18B-34 - Confidentiality of proposals.

Section 5-18B-35 - Review and opinion of performance criteria developer--Submission to governing body.

Section 5-18B-36 - Acceptance of a proposal--Evaluation criteria scores.

Section 5-18B-37 - Rejection of design-build proposals--Solicitation of new proposals.

Section 5-18B-38 - Withdrawal of design-build proposal.

Section 5-18B-39 - Construction manager engagement.

Section 5-18B-40 - Services of construction manager.

Section 5-18B-41 - Manager-agent.

Section 5-18B-42 - Manager-at-risk.

Section 5-18B-43 - Criteria for construction manager engagement.

Section 5-18B-44 - Criteria for construction manager-at-risk engagement.

Section 5-18B-45 - Active involvement of licensed design professional required.

Section 5-18B-46 - Improvement projects that rely on federal funding from FAA.