Ohio Revised Code
Chapter 153 | Public Improvements
Section 153.571 | Form of Bond.

Effective: May 9, 2000
Latest Legislation: House Bill 495 - 123rd General Assembly
The bond provided for in division (B) of section 153.54 of the Revised Code shall be in substantially the following form, and recovery of any claimant thereunder shall be subject to sections 153.01 to 153.60 of the Revised Code, to the same extent as if the provisions of such sections were fully incorporated in the bond form:
"KNOW ALL PERSONS BY THESE PRESENTS, that we, the undersigned _________________ as principal and _____________ as sureties, are hereby held and firmly bound unto ______________ as obligee in the penal sum of the dollar amount of the bid submitted by the principal to the obligee on ______________ to undertake the project known as ________________ The penal sum referred to herein shall be the dollar amount of the principal's bid to the obligee, incorporating any additive or deductive alternate bids made by the principal on the date referred to above to the obligee, which are accepted by the obligee. In no case shall the penal sum exceed the amount of ____________ dollars. (If the foregoing blank is not filled in, the penal sum will be the full amount of the principal's bid, including alternates. Alternatively, if the blank is filled in, the amount stated must not be less than the full amount of the bid including alternates, in dollars and cents. A percentage is not acceptable.) For the payment of the penal sum well and truly to be made, we hereby jointly and severally bind ourselves, our heirs, executors, administrators, successors, and assigns.
Signed this _______________ day of _____________, ____ THE CONDITION OF THE ABOVE OBLIGATION IS SUCH, that whereas the above named principal has submitted a bid for __________________
Now, therefore, if the obligee accepts the bid of the principal and the principal fails to enter into a proper contract in accordance with the bid, plans, details, specifications, and bills of material; and in the event the principal pays to the obligee the difference not to exceed ten per cent of the penalty hereof between the amount specified in the bid and such larger amount for which the obligee may in good faith contract with the next lowest bidder to perform the work covered by the bid; or in the event the obligee does not award the contract to the next lowest bidder and resubmits the project for bidding, the principal pays to the obligee the difference not to exceed ten per cent of the penalty hereof between the amount specified in the bid, or the costs, in connection with the resubmission, of printing new contract documents, required advertising, and printing and mailing notices to prospective bidders, whichever is less, then this obligation shall be null and void, otherwise to remain in full force and effect; if the obligee accepts the bid of the principal and the principal within ten days after the awarding of the contract enters into a proper contract in accordance with the bid, plans, details, specifications, and bills of material, which said contract is made a part of this bond the same as though set forth herein;
Now also, if the said ________________ shall well and faithfully do and perform the things agreed by ______________ to be done and performed according to the terms of said contract; and shall pay all lawful claims of subcontractors, materials suppliers, and laborers, for labor performed and materials furnished in the carrying forward, performing, or completing of said contract; we agreeing and assenting that this undertaking shall be for the benefit of any materials supplier or laborer having a just claim, as well as for the obligee herein; then this obligation shall be void; otherwise the same shall remain in full force and effect; it being expressly understood and agreed that the liability of the surety for any and all claims hereunder shall in no event exceed the penal amount of this obligation as herein stated.
The said surety hereby stipulates and agrees that no modifications, omissions, or additions, in or to the terms of the said contract or in or to the plans or specifications therefor shall in any wise affect the obligations of said surety on its bond."

Structure Ohio Revised Code

Ohio Revised Code

Title 1 | State Government

Chapter 153 | Public Improvements

Section 153.01 | Architect Must Submit Accurate Plans, Estimates, Bills of Materials, and Details to Scale.

Section 153.011 | Using Domestic Steel Products in State Supported Projects.

Section 153.012 | Preference to Contractors Having Principal Place of Business in Ohio.

Section 153.013 | Capitol Square Review and Advisory Board - Indefinite Delivery Indefinite Quantity Contract.

Section 153.02 | Debarment of Contractor From Contract Awards.

Section 153.03 | Contracts to Require Drug-Free Workplace Program.

Section 153.031 | Rc 153.03 Requirements Limited to State Improvements.

Section 153.04 | Forms for Providing Bidding Information - Life-Cycle Costs.

Section 153.05 | Actions to Enforce Bond.

Section 153.06 | Form of Bids.

Section 153.07 | Publishing Notice of Bids.

Section 153.08 | Opening Bids and Awarding Contract.

Section 153.09 | New Proposals When Necessary - Change in Work or Materials.

Section 153.10 | No Change in Plans Without Approval of Owner.

Section 153.11 | Change of Plans Becomes Part of Original Contract.

Section 153.12 | Awarding and Executing Contract.

Section 153.13 | Estimates of Labor and Materials - Funds in Escrow Account.

Section 153.14 | Estimates to Be Filed With Executive Director - Payment on Materials Delivered - Payment Procedure.

Section 153.15 | Assessment of Asbestos Hazard.

Section 153.16 | Policy and Procedure Guidelines for Contract Documents in Conjunction With Administration of Public Works Contracts.

Section 153.17 | Requisition Upon Contractor for Additional Specific Force or Materials.

Section 153.18 | Certification of Additional Force or Materials.

Section 153.19 | Contract Shall Contain Provision as to Time of Completion.

Section 153.20 | Duty of Attorney General.

Section 153.21 | Building Commission.

Section 153.22 | Compensation of Commissioners.

Section 153.23 | Expenses of Building Commission.

Section 153.24 | Oath and Bond.

Section 153.25 | Vacancies.

Section 153.26 | Contracts.

Section 153.27 | Architects - Superintendents - Employees.

Section 153.28 | Plans, Drawings, and Cost Estimates Filed With County Auditor.

Section 153.29 | Proceedings of Building Commission.

Section 153.30 | Record of Proceedings.

Section 153.31 | Plans and Estimates for Construction - Construction Project Manager or Consultants.

Section 153.311 | Construction of Public Building in Stages.

Section 153.32 | Contracts for Erection and Repair of Superstructures.

Section 153.33 | Bids on Other Plans May Be Considered.

Section 153.34 | Contents of Advertisement.

Section 153.35 | Plans Shall Be Kept on File in County Auditor's Office.

Section 153.36 | Approval of Plans for Courthouse or Jail.

Section 153.37 | Approval of Plans for County Home.

Section 153.38 | Approval of Plans for Bridge.

Section 153.39 | Approval of Plans for Children's Home.

Section 153.44 | Contracts Submitted to Prosecuting Attorney.

Section 153.45 | Commissioners May Annul Old and Make New Contracts.

Section 153.49 | Duty of County Treasurer.

Section 153.50 | Separate Bids for Work and Materials.

Section 153.501 | Subcontracts Awarded by Construction Manager at Risk, Design-Build Firm, or General Contracting Firm; Utilization of Design-Assist Firm; Self-Performed Portions of Work.

Section 153.502 | Construction Management or Design-Build Contracts; Prequalification of Bidders.

Section 153.503 | Adoption of Rules.

Section 153.51 | Separate Contracts - Single, Aggregate Contract.

Section 153.52 | Awarding of Contracts to Separate Bidders.

Section 153.53 | Adjusting Threshold in Section 153.01 for Inflation.

Section 153.54 | Bid Guaranty to Be Filed With Bid.

Section 153.55 | Dividing Project Into Parts to Avoid Threshold Prohibited; Costs Included in Threshold Amount.

Section 153.56 | Creditor Shall Furnish Statement of Amount Due - Service of Notice of Furnishing.

Section 153.57 | Form of Bond.

Section 153.571 | Form of Bond.

Section 153.58 | Prohibition.

Section 153.581 | Contracts for Construction Definitions.

Section 153.59 | Discrimination and Intimidation on Account of Race, Religion, Sex, Disability, National Origin or Ancestry.

Section 153.591 | Hiring Hall Contract or Agreement.

Section 153.60 | Forfeiture.

Section 153.61 | Agreement for Joint Construction and Management.

Section 153.62 | Issuing Change Order for Additional Work.

Section 153.63 | Agreement for Escrow Account for Contractor.

Section 153.64 | Protecting Underground Utility Facilities During Construction of Public Improvement.

Section 153.65 | Professional Design Services Definitions.

Section 153.66 | Submitting Statement of Qualifications.

Section 153.67 | Announcing Contracts Available for Professional Design or Design-Build Services.

Section 153.68 | Instituting Prequalification Requirements.

Section 153.69 | Evaluating and Selecting Firms.

Section 153.691 | No Fee Estimate on Contract for Professional Design Services.

Section 153.692 | Obtaining Services of Criteria Architect or Engineer.

Section 153.693 | Evaluation of Design-Build Firms.

Section 153.694 | Conflicts of Interest.

Section 153.70 | Requiring Professional Liability Insurance.

Section 153.71 | Administrative Rules.

Section 153.72 | Authority of Design-Build Firm.

Section 153.73 | Construction of Statutes.

Section 153.80 | Reducing Bond.

Section 153.81 | Indemnity Provisions in Public Works Design Contracts.

Section 153.83 | Hearings Related to Contractor Labor Agreements.

Section 153.99 | Penalty.