(A) The executive director of the Ohio facilities construction commission, may debar a contractor from contract awards for public improvements as referred to in section 153.01 of the Revised Code or for projects as defined in section 3318.01 of the Revised Code, upon proof that the contractor has done any of the following:
(1) Defaulted on a contract requiring the execution of a takeover agreement as set forth in division (B) of section 153.17 of the Revised Code;
(2) Knowingly failed during the course of a contract to maintain the coverage required by the bureau of workers' compensation;
(3) Knowingly failed during the course of a contract to maintain the contractor's drug-free workplace program as required by the contract;
(4) Knowingly failed during the course of a contract to maintain insurance required by the contract or otherwise by law, resulting in a substantial loss to the owner, as owner is referred to in section 153.01 of the Revised Code, or to the commission and school district board, as provided in division (F) of section 3318.08 of the Revised Code;
(5) Misrepresented the firm's qualifications in the selection process set forth in sections 153.65 to 153.71 or section 3318.10 of the Revised Code;
(6) Been convicted of a criminal offense related to the application for or performance of any public or private contract, including, but not limited to, embezzlement, theft, forgery, bribery, falsification or destruction of records, receiving stolen property, and any other offense that directly reflects on the contractor's business integrity;
(7) Been convicted of a criminal offense under state or federal antitrust laws;
(8) Deliberately or willfully submitted false or misleading information in connection with the application for or performance of a public contract;
(9) Been debarred from bidding on or participating in a contract with any state or federal agency.
(B) When the executive director debars a contractor that is a partnership, association, or corporation, the executive director also may debar any partner of the partnership or any officer or director of the association or corporation, as applicable.
(C) When the executive director reasonably believes that grounds for debarment exist, the executive director shall send the contractor a notice of proposed debarment indicating the grounds for the proposed debarment and the procedure for requesting a hearing on the proposed debarment. The hearing shall be conducted in accordance with Chapter 119. of the Revised Code. If the contractor does not respond with a request for a hearing in the manner specified in Chapter 119. of the Revised Code, the executive director shall issue the debarment decision without a hearing and shall notify the contractor of the decision by certified mail, return receipt requested.
(D) The executive director shall determine the length of the debarment period and may rescind the debarment at any time upon notification to the contractor. During the period of debarment, the contractor is not eligible to bid for or participate in any contract for a public improvement as referred to in section 153.01 of the Revised Code or for a project as defined in section 3318.01 of the Revised Code. After the debarment period expires, the contractor may be eligible to bid for and participate in such contracts if the vendor is not otherwise debarred.
(E) The executive director shall maintain a list of all contractors currently debarred under this section. Any governmental entity awarding a contract for construction of a public improvement or project may use a contractor's presence on the debarment list to determine whether a contractor is responsible or best under section 9.312 or any other section of the Revised Code in the award of a contract.
(F) As used in this section, "contractor" means a construction contracting business, a subcontractor of a construction contracting business, a supplier of materials, or a manufacturer of materials.

Structure Ohio Revised Code

Ohio Revised Code

Title 1 | State Government

Chapter 153 | Public Improvements

Section 153.01 | Architect Must Submit Accurate Plans, Estimates, Bills of Materials, and Details to Scale.

Section 153.011 | Using Domestic Steel Products in State Supported Projects.

Section 153.012 | Preference to Contractors Having Principal Place of Business in Ohio.

Section 153.013 | Capitol Square Review and Advisory Board - Indefinite Delivery Indefinite Quantity Contract.

Section 153.02 | Debarment of Contractor From Contract Awards.

Section 153.03 | Contracts to Require Drug-Free Workplace Program.

Section 153.031 | Rc 153.03 Requirements Limited to State Improvements.

Section 153.04 | Forms for Providing Bidding Information - Life-Cycle Costs.

Section 153.05 | Actions to Enforce Bond.

Section 153.06 | Form of Bids.

Section 153.07 | Publishing Notice of Bids.

Section 153.08 | Opening Bids and Awarding Contract.

Section 153.09 | New Proposals When Necessary - Change in Work or Materials.

Section 153.10 | No Change in Plans Without Approval of Owner.

Section 153.11 | Change of Plans Becomes Part of Original Contract.

Section 153.12 | Awarding and Executing Contract.

Section 153.13 | Estimates of Labor and Materials - Funds in Escrow Account.

Section 153.14 | Estimates to Be Filed With Executive Director - Payment on Materials Delivered - Payment Procedure.

Section 153.15 | Assessment of Asbestos Hazard.

Section 153.16 | Policy and Procedure Guidelines for Contract Documents in Conjunction With Administration of Public Works Contracts.

Section 153.17 | Requisition Upon Contractor for Additional Specific Force or Materials.

Section 153.18 | Certification of Additional Force or Materials.

Section 153.19 | Contract Shall Contain Provision as to Time of Completion.

Section 153.20 | Duty of Attorney General.

Section 153.21 | Building Commission.

Section 153.22 | Compensation of Commissioners.

Section 153.23 | Expenses of Building Commission.

Section 153.24 | Oath and Bond.

Section 153.25 | Vacancies.

Section 153.26 | Contracts.

Section 153.27 | Architects - Superintendents - Employees.

Section 153.28 | Plans, Drawings, and Cost Estimates Filed With County Auditor.

Section 153.29 | Proceedings of Building Commission.

Section 153.30 | Record of Proceedings.

Section 153.31 | Plans and Estimates for Construction - Construction Project Manager or Consultants.

Section 153.311 | Construction of Public Building in Stages.

Section 153.32 | Contracts for Erection and Repair of Superstructures.

Section 153.33 | Bids on Other Plans May Be Considered.

Section 153.34 | Contents of Advertisement.

Section 153.35 | Plans Shall Be Kept on File in County Auditor's Office.

Section 153.36 | Approval of Plans for Courthouse or Jail.

Section 153.37 | Approval of Plans for County Home.

Section 153.38 | Approval of Plans for Bridge.

Section 153.39 | Approval of Plans for Children's Home.

Section 153.44 | Contracts Submitted to Prosecuting Attorney.

Section 153.45 | Commissioners May Annul Old and Make New Contracts.

Section 153.49 | Duty of County Treasurer.

Section 153.50 | Separate Bids for Work and Materials.

Section 153.501 | Subcontracts Awarded by Construction Manager at Risk, Design-Build Firm, or General Contracting Firm; Utilization of Design-Assist Firm; Self-Performed Portions of Work.

Section 153.502 | Construction Management or Design-Build Contracts; Prequalification of Bidders.

Section 153.503 | Adoption of Rules.

Section 153.51 | Separate Contracts - Single, Aggregate Contract.

Section 153.52 | Awarding of Contracts to Separate Bidders.

Section 153.53 | Adjusting Threshold in Section 153.01 for Inflation.

Section 153.54 | Bid Guaranty to Be Filed With Bid.

Section 153.55 | Dividing Project Into Parts to Avoid Threshold Prohibited; Costs Included in Threshold Amount.

Section 153.56 | Creditor Shall Furnish Statement of Amount Due - Service of Notice of Furnishing.

Section 153.57 | Form of Bond.

Section 153.571 | Form of Bond.

Section 153.58 | Prohibition.

Section 153.581 | Contracts for Construction Definitions.

Section 153.59 | Discrimination and Intimidation on Account of Race, Religion, Sex, Disability, National Origin or Ancestry.

Section 153.591 | Hiring Hall Contract or Agreement.

Section 153.60 | Forfeiture.

Section 153.61 | Agreement for Joint Construction and Management.

Section 153.62 | Issuing Change Order for Additional Work.

Section 153.63 | Agreement for Escrow Account for Contractor.

Section 153.64 | Protecting Underground Utility Facilities During Construction of Public Improvement.

Section 153.65 | Professional Design Services Definitions.

Section 153.66 | Submitting Statement of Qualifications.

Section 153.67 | Announcing Contracts Available for Professional Design or Design-Build Services.

Section 153.68 | Instituting Prequalification Requirements.

Section 153.69 | Evaluating and Selecting Firms.

Section 153.691 | No Fee Estimate on Contract for Professional Design Services.

Section 153.692 | Obtaining Services of Criteria Architect or Engineer.

Section 153.693 | Evaluation of Design-Build Firms.

Section 153.694 | Conflicts of Interest.

Section 153.70 | Requiring Professional Liability Insurance.

Section 153.71 | Administrative Rules.

Section 153.72 | Authority of Design-Build Firm.

Section 153.73 | Construction of Statutes.

Section 153.80 | Reducing Bond.

Section 153.81 | Indemnity Provisions in Public Works Design Contracts.

Section 153.83 | Hearings Related to Contractor Labor Agreements.

Section 153.99 | Penalty.