Section 153.17 | Requisition Upon Contractor for Additional Specific Force or Materials.

Effective: September 10, 2012
Latest Legislation: House Bill 487 - 129th General Assembly
(A) When in the opinion of the owner referred to in section 153.01 of the Revised Code, the work under any contract made under any law of the state is neglected by the contractor or such work is not prosecuted with the diligence and force specified or intended in the contract, such owner may make requisition upon the contractor for such additional specific force or materials to be brought into the work under such contract or to remove improper materials from the grounds as in their judgment the contract and its faithful fulfillment requires.
Not less than five days' notice in writing of such action shall be served upon the contractor or the contractor's agent in charge of the work. If the contractor fails to comply with such requisition within fifteen days, such owner with the written consent of the Ohio facilities construction commission, may employ upon the work the additional force, or supply the special materials or such part of either as is considered proper, and may remove improper materials from the grounds.
(B) When the original contractor has defaulted on a contract and the surety has declined to take over the project, the owner may contract with one or more takeover contractors to complete work that was not finished because of the default of the original contractor. The owner may enter into a contract with a takeover contractor without competitive bidding or controlling board approval. Upon execution of a takeover contract, the owner shall notify the director of budget and management.
When the owner has taken over a project after a default has occurred, any moneys that the owner receives from the surety as a settlement for completion of the project shall be deposited in the original fund from which the capital appropriation for the project was made. The executive director, without controlling board approval, may authorize specified additional uses for the moneys related to completion of the project and may increase the appropriation authority in the appropriation line item used to fund the project by an amount equal to the moneys received from the surety.

Structure Ohio Revised Code

Ohio Revised Code

Title 1 | State Government

Chapter 153 | Public Improvements

Section 153.01 | Architect Must Submit Accurate Plans, Estimates, Bills of Materials, and Details to Scale.

Section 153.011 | Using Domestic Steel Products in State Supported Projects.

Section 153.012 | Preference to Contractors Having Principal Place of Business in Ohio.

Section 153.013 | Capitol Square Review and Advisory Board - Indefinite Delivery Indefinite Quantity Contract.

Section 153.02 | Debarment of Contractor From Contract Awards.

Section 153.03 | Contracts to Require Drug-Free Workplace Program.

Section 153.031 | Rc 153.03 Requirements Limited to State Improvements.

Section 153.04 | Forms for Providing Bidding Information - Life-Cycle Costs.

Section 153.05 | Actions to Enforce Bond.

Section 153.06 | Form of Bids.

Section 153.07 | Publishing Notice of Bids.

Section 153.08 | Opening Bids and Awarding Contract.

Section 153.09 | New Proposals When Necessary - Change in Work or Materials.

Section 153.10 | No Change in Plans Without Approval of Owner.

Section 153.11 | Change of Plans Becomes Part of Original Contract.

Section 153.12 | Awarding and Executing Contract.

Section 153.13 | Estimates of Labor and Materials - Funds in Escrow Account.

Section 153.14 | Estimates to Be Filed With Executive Director - Payment on Materials Delivered - Payment Procedure.

Section 153.15 | Assessment of Asbestos Hazard.

Section 153.16 | Policy and Procedure Guidelines for Contract Documents in Conjunction With Administration of Public Works Contracts.

Section 153.17 | Requisition Upon Contractor for Additional Specific Force or Materials.

Section 153.18 | Certification of Additional Force or Materials.

Section 153.19 | Contract Shall Contain Provision as to Time of Completion.

Section 153.20 | Duty of Attorney General.

Section 153.21 | Building Commission.

Section 153.22 | Compensation of Commissioners.

Section 153.23 | Expenses of Building Commission.

Section 153.24 | Oath and Bond.

Section 153.25 | Vacancies.

Section 153.26 | Contracts.

Section 153.27 | Architects - Superintendents - Employees.

Section 153.28 | Plans, Drawings, and Cost Estimates Filed With County Auditor.

Section 153.29 | Proceedings of Building Commission.

Section 153.30 | Record of Proceedings.

Section 153.31 | Plans and Estimates for Construction - Construction Project Manager or Consultants.

Section 153.311 | Construction of Public Building in Stages.

Section 153.32 | Contracts for Erection and Repair of Superstructures.

Section 153.33 | Bids on Other Plans May Be Considered.

Section 153.34 | Contents of Advertisement.

Section 153.35 | Plans Shall Be Kept on File in County Auditor's Office.

Section 153.36 | Approval of Plans for Courthouse or Jail.

Section 153.37 | Approval of Plans for County Home.

Section 153.38 | Approval of Plans for Bridge.

Section 153.39 | Approval of Plans for Children's Home.

Section 153.44 | Contracts Submitted to Prosecuting Attorney.

Section 153.45 | Commissioners May Annul Old and Make New Contracts.

Section 153.49 | Duty of County Treasurer.

Section 153.50 | Separate Bids for Work and Materials.

Section 153.501 | Subcontracts Awarded by Construction Manager at Risk, Design-Build Firm, or General Contracting Firm; Utilization of Design-Assist Firm; Self-Performed Portions of Work.

Section 153.502 | Construction Management or Design-Build Contracts; Prequalification of Bidders.

Section 153.503 | Adoption of Rules.

Section 153.51 | Separate Contracts - Single, Aggregate Contract.

Section 153.52 | Awarding of Contracts to Separate Bidders.

Section 153.53 | Adjusting Threshold in Section 153.01 for Inflation.

Section 153.54 | Bid Guaranty to Be Filed With Bid.

Section 153.55 | Dividing Project Into Parts to Avoid Threshold Prohibited; Costs Included in Threshold Amount.

Section 153.56 | Creditor Shall Furnish Statement of Amount Due - Service of Notice of Furnishing.

Section 153.57 | Form of Bond.

Section 153.571 | Form of Bond.

Section 153.58 | Prohibition.

Section 153.581 | Contracts for Construction Definitions.

Section 153.59 | Discrimination and Intimidation on Account of Race, Religion, Sex, Disability, National Origin or Ancestry.

Section 153.591 | Hiring Hall Contract or Agreement.

Section 153.60 | Forfeiture.

Section 153.61 | Agreement for Joint Construction and Management.

Section 153.62 | Issuing Change Order for Additional Work.

Section 153.63 | Agreement for Escrow Account for Contractor.

Section 153.64 | Protecting Underground Utility Facilities During Construction of Public Improvement.

Section 153.65 | Professional Design Services Definitions.

Section 153.66 | Submitting Statement of Qualifications.

Section 153.67 | Announcing Contracts Available for Professional Design or Design-Build Services.

Section 153.68 | Instituting Prequalification Requirements.

Section 153.69 | Evaluating and Selecting Firms.

Section 153.691 | No Fee Estimate on Contract for Professional Design Services.

Section 153.692 | Obtaining Services of Criteria Architect or Engineer.

Section 153.693 | Evaluation of Design-Build Firms.

Section 153.694 | Conflicts of Interest.

Section 153.70 | Requiring Professional Liability Insurance.

Section 153.71 | Administrative Rules.

Section 153.72 | Authority of Design-Build Firm.

Section 153.73 | Construction of Statutes.

Section 153.80 | Reducing Bond.

Section 153.81 | Indemnity Provisions in Public Works Design Contracts.

Section 153.83 | Hearings Related to Contractor Labor Agreements.

Section 153.99 | Penalty.