Effective: September 10, 2012
Latest Legislation: House Bill 487 - 129th General Assembly
For the construction of those projects, improvements, and public buildings over which the Ohio facilities construction commission has general supervision pursuant to section 123.21 of the Revised Code, the estimates referred to in section 153.13 of the Revised Code shall be filed with the executive director by the owner referred to in section 153.01 or 153.12 of the Revised Code. Upon completion of a project referred to in section 153.13 of the Revised Code or any divisible part thereof, the maintenance and repair of such project or divisible part shall be assumed by the owner referred to in section 153.01 or 153.12 of the Revised Code.
In addition to all other payments on account of work performed, there shall be allowed by the owner referred to in section 153.01 or 153.12 of the Revised Code and paid to the contractor a sum at the rate of ninety-two per cent of the invoice costs, not to exceed the bid price in a unit price contract, of material delivered on the site of the work, or a railroad station, siding, or other point in the vicinity of the work, or other approved storage site, provided such materials have been inspected and found to meet the specifications. The balance of such invoiced value shall be paid when such material is incorporated into and becomes a part of such building, construction, addition, improvement, alteration, or installation. When an estimate is allowed on account of material delivered on the site of the work or in the vicinity thereof or under the possession and control of the contractor but not yet incorporated therein, such material shall become the property of the owner under the contract, but if such material is stolen, destroyed, or damaged by casualty before being used, the contractor shall be required to replace it at the contractor's own expense.
When the rate of work and amounts involved are so large that it is considered advisable by the owner or contractor, estimates and payments shall be made twice each month.
Payment on approved estimates filed with the owner or its representative shall be made within thirty days. Upon the failure of the owner or its representative to make such payments within thirty days, or upon an unauthorized withholding of retainage, there shall be allowed to the contractor, in addition to any other remedies allowed by law, interest on such moneys not paid within thirty days. Interest on the unauthorized withholding of retainage shall be in addition to any interest earned in the escrow account set forth in section 153.13 of the Revised Code. The rate of such interest shall be the average of the prime rate established at the commercial banks in the city of over one hundred thousand population that is nearest the construction project. Nothing in this section shall be construed as a limitation upon the authority of the director of transportation granted in Chapter 5525. of the Revised Code.
Structure Ohio Revised Code
Chapter 153 | Public Improvements
Section 153.011 | Using Domestic Steel Products in State Supported Projects.
Section 153.012 | Preference to Contractors Having Principal Place of Business in Ohio.
Section 153.02 | Debarment of Contractor From Contract Awards.
Section 153.03 | Contracts to Require Drug-Free Workplace Program.
Section 153.031 | Rc 153.03 Requirements Limited to State Improvements.
Section 153.04 | Forms for Providing Bidding Information - Life-Cycle Costs.
Section 153.05 | Actions to Enforce Bond.
Section 153.06 | Form of Bids.
Section 153.07 | Publishing Notice of Bids.
Section 153.08 | Opening Bids and Awarding Contract.
Section 153.09 | New Proposals When Necessary - Change in Work or Materials.
Section 153.10 | No Change in Plans Without Approval of Owner.
Section 153.11 | Change of Plans Becomes Part of Original Contract.
Section 153.12 | Awarding and Executing Contract.
Section 153.13 | Estimates of Labor and Materials - Funds in Escrow Account.
Section 153.15 | Assessment of Asbestos Hazard.
Section 153.17 | Requisition Upon Contractor for Additional Specific Force or Materials.
Section 153.18 | Certification of Additional Force or Materials.
Section 153.19 | Contract Shall Contain Provision as to Time of Completion.
Section 153.20 | Duty of Attorney General.
Section 153.21 | Building Commission.
Section 153.22 | Compensation of Commissioners.
Section 153.23 | Expenses of Building Commission.
Section 153.24 | Oath and Bond.
Section 153.27 | Architects - Superintendents - Employees.
Section 153.28 | Plans, Drawings, and Cost Estimates Filed With County Auditor.
Section 153.29 | Proceedings of Building Commission.
Section 153.30 | Record of Proceedings.
Section 153.31 | Plans and Estimates for Construction - Construction Project Manager or Consultants.
Section 153.311 | Construction of Public Building in Stages.
Section 153.32 | Contracts for Erection and Repair of Superstructures.
Section 153.33 | Bids on Other Plans May Be Considered.
Section 153.34 | Contents of Advertisement.
Section 153.35 | Plans Shall Be Kept on File in County Auditor's Office.
Section 153.36 | Approval of Plans for Courthouse or Jail.
Section 153.37 | Approval of Plans for County Home.
Section 153.38 | Approval of Plans for Bridge.
Section 153.39 | Approval of Plans for Children's Home.
Section 153.44 | Contracts Submitted to Prosecuting Attorney.
Section 153.45 | Commissioners May Annul Old and Make New Contracts.
Section 153.49 | Duty of County Treasurer.
Section 153.50 | Separate Bids for Work and Materials.
Section 153.502 | Construction Management or Design-Build Contracts; Prequalification of Bidders.
Section 153.503 | Adoption of Rules.
Section 153.51 | Separate Contracts - Single, Aggregate Contract.
Section 153.52 | Awarding of Contracts to Separate Bidders.
Section 153.53 | Adjusting Threshold in Section 153.01 for Inflation.
Section 153.54 | Bid Guaranty to Be Filed With Bid.
Section 153.56 | Creditor Shall Furnish Statement of Amount Due - Service of Notice of Furnishing.
Section 153.57 | Form of Bond.
Section 153.571 | Form of Bond.
Section 153.581 | Contracts for Construction Definitions.
Section 153.591 | Hiring Hall Contract or Agreement.
Section 153.61 | Agreement for Joint Construction and Management.
Section 153.62 | Issuing Change Order for Additional Work.
Section 153.63 | Agreement for Escrow Account for Contractor.
Section 153.65 | Professional Design Services Definitions.
Section 153.66 | Submitting Statement of Qualifications.
Section 153.67 | Announcing Contracts Available for Professional Design or Design-Build Services.
Section 153.68 | Instituting Prequalification Requirements.
Section 153.69 | Evaluating and Selecting Firms.
Section 153.691 | No Fee Estimate on Contract for Professional Design Services.
Section 153.692 | Obtaining Services of Criteria Architect or Engineer.
Section 153.693 | Evaluation of Design-Build Firms.
Section 153.694 | Conflicts of Interest.
Section 153.70 | Requiring Professional Liability Insurance.
Section 153.71 | Administrative Rules.
Section 153.72 | Authority of Design-Build Firm.
Section 153.73 | Construction of Statutes.
Section 153.80 | Reducing Bond.
Section 153.81 | Indemnity Provisions in Public Works Design Contracts.
Section 153.83 | Hearings Related to Contractor Labor Agreements.