Section 145. (a) For the purposes of this section, the following words shall, unless the context clearly requires otherwise, have the following meanings:--
"Customer'', a retail natural gas customer.
"Eligible infrastructure replacement'', a replacement or an improvement of existing infrastructure of a gas company that: (i) is made on or after January 1, 2015; (ii) is designed to improve public safety or infrastructure reliability; (iii) does not increase the revenue of a gas company by connecting an improvement for a principal purpose of serving new customers; (iv) reduces, or has the potential to reduce, lost and unaccounted for natural gas through a reduction in natural gas system leaks; and (v) is not included in the current rate base of the gas company as determined in the gas company's most recent rate proceeding.
"Plan'', a targeted infrastructure replacement program construction plan that a gas company files pursuant to subsection (b).
"Project'', an eligible infrastructure replacement project proposed by a gas company in a plan filed under this section.
[ Subsection (b) effective until June 24, 2021. For text effective June 24, 2021, see below.]
(b) A gas company may file with the department a plan to address aging or leaking natural gas infrastructure within the commonwealth in the interest of public safety and reducing lost and unaccounted for natural gas through a reduction in natural gas system leaks.
[ Subsection (b) as amended by 2021, 8, Sec. 87 effective June 24, 2021. For text effective until June 24, 2021, see above.]
(b) A gas company shall file with the department a plan to address aging or leaking natural gas infrastructure within the commonwealth and the leak rate on the gas company's natural gas infrastructure in the interest of public safety and reducing lost and unaccounted for natural gas through a reduction in natural gas system leaks. Each company's gas infrastructure plan shall include interim targets for the department's review. The department shall review these interim targets to ensure each gas company is meeting the appropriate pace to reduce the leak rate on and to replace the gas company's natural gas infrastructure in a safe and timely manner. The interim targets shall be for periods of not more than 6 years or at the conclusion of 2 complete 3-year walking survey cycles conducted by the gas company. The gas companies shall incorporate these interim targets into timelines for removing all leak-prone infrastructure filed pursuant to subsection (c) and may update them based on overall progress. The department may levy a penalty against any gas company that fails to meet its interim target in an amount up to and including the equivalent of 2.5 per cent of such gas company's transmission and distribution service revenues for the previous calendar year.
[ First paragraph of subsection (c) effective until June 24, 2021. For text effective June 24, 2021, see below.]
(c) Any plan filed with the department shall include, but not be limited to: (i) eligible infrastructure replacement of mains, services, meter sets and other ancillary facilities composed of non-cathodically protected steel, cast iron and wrought iron, prioritized to implement the federal gas distribution pipeline integrity management plan annually submitted to the department and consistent with subpart P of 49 C.F.R. part 192; (ii) an anticipated timeline for the completion of each project; (iii) the estimated cost of each project; (iv) rate change requests; (v) a description of customer costs and benefits under the plan; and (vi) any other information the department considers necessary to evaluate the plan.
[ First paragraph of subsection (c) as amended by 2021, 8, Sec. 88 effective June 24, 2021. For text effective until June 24, 2021, see above.]
(c) Any plan filed with the department shall include, but not be limited to: (i) eligible infrastructure replacement of mains, services, meter sets and other ancillary facilities composed of non-cathodically protected steel, cast iron and wrought iron, prioritized to implement the federal gas distribution pipeline integrity management plan annually submitted to the department and consistent with subpart P of 49 C.F.R. part 192; (ii) an anticipated timeline for the completion of each project; (iii) the estimated cost of each project; (iv) rate change requests; (v) a description of customer costs and benefits under the plan; (vi) the relocations, where practical, of a meter located inside of a structure to the outside of said structure for the purpose of improving public safety; and (vii) any other information the department considers necessary to evaluate the plan.
[ Second paragraph of subsection (c) effective until June 24, 2021. For text effective June 24, 2021, see below.]
Upon filing an initial plan under this section, a gas company shall include a timeline for removing all leak-prone infrastructure on an accelerated basis specifying an annual replacement pace and program end date with a target end date of either (i) not more than 20 years, or (ii) a reasonable target end date considering the allowable recovery cap established pursuant to subsection (f). The department shall not approve a timeline as part of a plan unless the allowable recovery cap established pursuant to subsection (f) provides the gas company with a reasonable opportunity to recover the costs associated with removing all leak-prone infrastructure on the accelerated basis set forth under the timeline utilizing the cost recovery mechanism established pursuant to this section. After filing the initial plan, a gas company shall, at 5-year intervals, provide the department with a summary of its replacement progress to date, a summary of work to be completed during the next 5 years and any similar information the department may require. The department may require a gas company to file an updated long-term timeline as part of a plan if it alters the cap established pursuant to subsection (f).
[ Second paragraph of subsection (c) as amended by 2021, 8, Sec. 89 effective June 24, 2021. For text effective until June 24, 2021, see above.]
As part of each plan filed under this section, a gas company shall include a timeline for removing all leak-prone infrastructure on an accelerated basis specifying an annual replacement pace and program end date with a target end date of: (i) not more than 20 years from the filing of a gas company's initial plan; or (ii) a reasonable target end date considering the allowable recovery cap established pursuant to subsection (f). The department shall not approve a timeline as part of a plan unless the allowable recovery cap established pursuant to subsection (f) provides the gas company with a reasonable opportunity to recover the costs associated with removing all leak-prone infrastructure on the accelerated basis set forth under the timeline utilizing the cost recovery mechanism established pursuant to this section. After filing the initial plan, a gas company shall, at 5-year intervals, provide the department with a summary of its replacement progress to date, a summary of work to be completed during the next 5 years and any similar information the department may require. The department may require a gas company to file an updated long-term timeline as part of a plan if it alters the cap established pursuant to subsection (f).
(d) If a gas company files a plan on or before October 31 for the subsequent construction year, the department shall review the plan within 6 months. The plan shall be effective as of the date of filing, pending department review. The department may modify a plan prior to approval at the request of a gas company or make other modifications to a plan as a condition of approval. The department shall consider the costs and benefits of the plan including, but not limited to, impacts on ratepayers, reductions of lost and unaccounted for natural gas through a reduction in natural gas system leaks and improvements to public safety. The department shall give priority to plans narrowly tailored to addressing leak-prone infrastructure most immediately in need of replacement.
(e) If a plan is in compliance with this section and the department determines the plan to reasonably accelerate eligible infrastructure replacement and provide benefits, the department shall issue preliminary acceptance of the plan in whole or in part. A gas company shall then be permitted to begin recovery of the estimated costs of projects included in the plan beginning on May 1 of the year following the initial filing and collect any revenue requirement, including depreciation, property taxes and return associated with the plan.
(f) On or before May 1 of each year, a gas company shall file final project documentation for projects completed in the prior year to demonstrate substantial compliance with the plan approved pursuant to subsection (e) and that project costs were reasonably and prudently incurred. The department shall investigate project costs within 6 months of submission and shall approve and reconcile the authorized rate factor, if necessary, upon a determination that the costs were reasonable and prudent. Annual changes in the revenue requirement eligible for recovery shall not exceed (i) 1.5 per cent of the gas company's most recent calendar year total firm revenues, including gas revenues attributable to sales and transportation customers, or (ii) an amount determined by the department that is greater than 1.5 per cent of the gas company's most recent calendar year total firm revenues, including gas revenues attributable to sales and transportation customers. Any revenue requirement approved by the department in excess of such cap may be deferred for recovery in the following year.
(g) All rate change requests made to the department pursuant to an approved plan, shall be filed annually on a fully reconciling basis, subject to final determination by the department pursuant to subsection (f). The rate change included in a plan pursuant to section (c), reviewed pursuant to subsection (d) and taking effect each May 1 pursuant to subsection (e) shall be subject to investigation by the department pursuant to subsection (f) to determine whether the gas company has over collected or under collected its requested rate adjustment with such over collection or under collection reconciled annually. If the department determines that any of the costs were not reasonably or prudently incurred, the department shall disallow the costs and direct the gas company to refund the full value of the costs charged to customers with the appropriate carrying charges on the over-collected amounts. If the department determines that any of the costs were not in compliance with the approved plan, the department shall disallow the costs from the cost recovery mechanism established under this section and shall direct the gas company to refund the full value of the costs charged to customers with the appropriate carrying charges on the over collected amounts.
(h) The department may promulgate rules and regulations under this section. The department may discontinue the replacement program and require a gas company to refund any costs charged to customers due to failure to substantially comply with a plan or failure to reasonably and prudently manage project costs.
Structure Massachusetts General Laws
Part I - Administration of the Government
Chapter 164 - Manufacture and Sale of Gas and Electricity
Section 1b - Service Territories for Distribution Companies; Rates
Section 1c - Marketing Companies
Section 1f - Consumer Protections; Rules and Regulations
Section 1g - Transition Costs and Charges
Section 1k - Penalties to Be Credited Back to Customers
Section 3 - Corporations Governed by Chapter
Section 4 - Application of Chapter 156b
Section 4a - State Secretary; Examination of Documents; Approval; Instances of Corporate Omission
Section 5 - Organization of Corporation; Certification by State Secretary
Section 5a - Name; Restrictions; Injunctive Relief
Section 6 - Articles of Organization; Contents
Section 8 - Amendment of Articles of Organization; Changes in Capital Stock or Corporate Name
Section 8b - Articles of Amendment; Submission to State Secretary; Effective Date; Filing
Section 9a - Electric Companies Providing Electricity to Other Companies; Ownership of Stock
Section 10 - Issuance of Capital Stock; Notification of Department
Section 11 - Payment of Price of Share
Section 12 - Improper Issue of Stock or Scrip Certificates; Effect; Penalty
Section 12a - Convertible Debentures
Section 13 - Mortgage of Property
Section 13a - Issuance and Pledge of Bonds Secured by Prior Liens
Section 15 - Invitation for Proposals for Purchase of Bonds
Section 15a - Issue or Sale of Bonds, Etc. at Less Than Par Value or Face Amount
Section 16 - Making Good Impairment of Capital Stock
Section 17 - Improper Issue of Stock, Bonds or Other Securities; Penalty
Section 17a - Investments; Approval of Department; Violations by Officers; Penalty
Section 18 - Disposition of Shares
Section 19 - Sale of Unissued Capital Stock; Terms; Auction Sale
Section 20 - Commencement of Business; Liability of Officers, Contribution
Section 23 - Voting by Stockholders; Proxy
Section 24 - Voting by Stockholders; Articles of Organization or By-Laws Controlling
Section 29 - Change of Officers; Filing of Certificate of Change
Section 30 - Change of Location
Section 31 - Amount of Stock in Gas Companies Held by Corporation
Section 33 - Fees for Filing Certificates, Articles and Copies of Votes
Section 33a - Promotional or Political Advertising Expenditures
Section 34a - Municipal Street Lighting Service
Section 34b - Replacement of Existing Poles
Section 35 - Vote of City to Acquire Plant
Section 36 - Vote of Town to Acquire Plant
Section 37 - Certification of Vote of City or Town to Department
Section 38 - Certification of Subsequent Votes
Section 39 - Failure to Certify Vote; Penalty
Section 40 - Debt Incurred for Establishing, Purchasing, Extending, etc., Light Plant
Section 41 - Enlargement of Plant
Section 42 - Purchase of Existing Plant
Section 45 - Purchase of Property in Adjoining Town
Section 46 - Distribution to Adjoining Town
Section 47 - Extension of Services to Adjoining Town
Section 47b - Facilities and Equipment Located Outside Municipal Limits
Section 47c - Municipal Lighting Plant Cooperatives
Section 47d - Exemption From Public Records and Open Meeting Requirements in Certain Instances
Section 51 - Purchase of Gas, Electricity, Equipment, Supplies or Materials From Another Town
Section 52 - Purchase of Electricity by Town From Street Railway
Section 53 - Delivery by Street Railway; Metering
Section 54 - Disagreement as to Price Paid to Street Railway; Action of Department
Section 55 - Municipal Light Board
Section 55a - Agreements Between Municipal Light Boards and Cities or Towns
Section 56 - Management of Plant
Section 56a - Municipal Light Commission; Definition; Contracts of Members
Section 56b - Contracts of Commission; Requisites
Section 56d - Contracts of Commission; Advertisements and Bids; Application of Section
Section 56e - Removal of Members; Notice and Hearing; Appeal
Section 57 - Manager's Annual Financial Report; Tax Levy; Expenditure of Income
Section 57a - Appropriations for Maintenance and Operation; Payment in Advance of Receipts
Section 57c - Appropriations From Insurance Escrow Account
Section 58 - Schedule of Prices for Gas and Electricity
Section 58a - Advance Deposit; Shut Off for Non-Payment; Removal of Appliances for Distribution
Section 58b - Lien Upon Real Estate for Nonpayment of Service Charges
Section 58c - Time for and Length of Lien
Section 58d - Unpaid Charges Added to Real Estate Taxes
Section 58e - Interest on Taxes Due by Reason of Unpaid Charges
Section 58f - Abatement of Real Estate Tax Imposed by Reason of Unpaid Charges
Section 59 - Notice of Change of Price to Department
Section 60 - Entitlement to Service; Review by Department
Section 61 - Assessment of Cost of Establishing Service
Section 62 - Protection of Plant; Municipal Ordinances
Section 63 - Duties of Municipality and Its Officers; Violations; Penalties
Section 65 - Application of Chapter to Plants Authorized by Special Act
Section 66 - Application of Chapter and By-Laws of Town to Plant Authorized by Special Act
Section 67 - Revocation of Rights, Locations or Licenses
Section 68 - Sale of Plant by Town
Section 69 - Enforcement by Supreme Judicial Court
Section 69a - Purchase, Sale and Distribution of Natural Gas by Municipality
Section 69c - Cadet Engineers; Power of City or Town to Contract for Training; Contents of Contract
Section 69d - Cadet Engineers; Selection
Section 69e - Cadet Engineers; Civil Service Laws; Retirement Benefits; Workmen's Compensation
Section 69h - Energy Facilities Siting Board
Section 69h1/2 - Hydropower Generation Facilities
Section 69i - Long-Range Forecasts of Electric and Gas Companies; Filing; Hearings; Approval
Section 69j1/4 - Construction of Generating Facility
Section 69j1/2 - Fees for Applications to Construct Electricity Facilities
Section 69l1/2 - Application for Certificate With Respect to a Generating Facility
Section 69n - Parties in Interest to Proceedings
Section 69o - Decision Granting or Denying Application; Findings and Opinions; Applicability
Section 70 - Opening of Streets by Gas Company; Liability; Repairing Streets
Section 70a - Application to Department to Lay Main; Hearing; Determination; Fees
Section 71 - Construction of Transmission Lines
Section 72 - Taking Land for Transmission Lines
Section 72a - Survey Preliminary to Eminent Domain Proceedings; Notice to Landowners; Damages
Section 73 - Pipes, Mains, Wires and Conduits Crossing Railroads
Section 74 - Recovery by Town of Damages Paid as Result of Defect in Street
Section 75 - Regulation by Municipal Authorities
Section 75a - Installation of Gas Meters; Compliance With Regulations for Preventing Escape of Gas
Section 75b - Qualifying to Do Business
Section 75c - Right of Eminent Domain
Section 75d - Survey Preliminary to Eminent Domain Proceedings; Liability
Section 75e - Regulation of Construction and Operation
Section 75f - Restoration of Ground Surface Following Installation
Section 75g - Marking of Location of Underground Line
Section 75h - Licenses, Permits, etc., for Pipeline Maintenance, Construction and Operation
Section 76 - Supervisory Authority of Department
Section 76a - Dealings With Affiliated Companies
Section 76b - Streets or Ways; Construction Over, Across or Along High Pressure Gas Mains
Section 76c - Rules and Regulations
Section 76d - Utility Underground Plant Damage Prevention System; Establishment
Section 77 - Annual Report of Department
Section 78 - Notice of Violation
Section 79 - Enforcement of Orders of Department; Equity Jurisdiction
Section 80 - Location of Office of Company; Records; Inspection of Records by Department
Section 81 - Form of Books and Accounts
Section 82 - Form of Records of Work at Manufacturing Station
Section 83 - Annual Return; Form; Other Information to Department
Section 84 - Failure to Make or Amend Return; Penalty
Section 84a - Condensed Return of Business and Financial Condition
Section 85a - Filing Copies of Existing Contracts With Affiliated Companies
Section 86 - Consent of Municipality to Entry of Another Gas Company
Section 87 - Consent of Municipality to Entry of Another Electric Company
Section 88 - Review of Decision Issued Under Secs. 86 or 87
Section 89 - Rights of Another Municipality to Enter Another Town
Section 90 - Conditions Imposed Upon Entry of Supplier of Electricity in Bulk
Section 91 - Enforcement of Conditions Imposed Under Sec. 90
Section 92 - Right of User to Gas or Electricity
Section 92a - Right of User in Bulk to Gas
Section 93 - Price or Quality of Gas or Electricity; Public Hearing; Notice
Section 941/2 - Sales of Compressed Natural Gas for Use as a Motor Fuel
Section 94a - Contracts for Purchase of Gas or Electricity; Review of Price Paid
Section 94b - Contracts With Affiliated Companies; Approval by Department
Section 94c - Dealings Between Gas or Electric Affiliated Company; Burden of Proof
Section 94d - Penalties for Delinquencies and Discounts
Section 94e - Notification of Termination of Contract Filed Under Sec. 94
Section 94f - Rates, Prices and Charges of Gas Companies; Effect of Orders of f.p.c.
Section 94h - Condominiums; Common Areas; Rates
Section 94i - Cost-Allocation Method for Determining Base Distribution Rates
Section 95 - Reports of Accidents
Section 96 - Purchase, Sale, Consolidation or Merger; Procedure; Public Interest Determination
Section 97 - Acquisition of Water Storage Reservoir or Hydro-Electric Plant by Electric Company
Section 98 - Rights of Company Acquiring Water Storage Reservoir or Hydro-Electric Plant
Section 99 - Increase of Capital Stock to Affect Acquisition
Section 99a - Property Held as Tenants in Common by Electric Companies
Section 100 - Sale of Property to Another Gas or Electric Company; Exceptions
Section 101 - Time for Filing Applications for Approval of Sales or Consolidations
Section 102 - Consolidation of Boston Consolidated Gas and Boston Edison
Section 102b - Certificate of Consolidation or Merger; Issuance; Fee
Section 102c - Enforcement of Consumer Protection Provisions; Arbitration
Section 103 - Accuracy of Meters; Records
Section 104 - Fees of Department for Examining, Comparing and Testing Gas Meters
Section 106 - Regulation of Quality of Gas
Section 108 - Calorimeter Provided by Company
Section 109 - Inspection of Gas by Department; Establishing New Standards of Purity
Section 110 - Gas Below Standard; Forfeiture
Section 111 - Unit of Measure for Sale of Gas
Section 113 - Use of Gas Meters Not Tested, Sealed or Stamped; Penalty
Section 114 - Testing Gas Meters in Use; Cost of Test
Section 115 - Easy Ascertainment of Gas Meter Reading
Section 115a - Replacement of Gas Meters
Section 116 - Entry on Premises to Examine and Maintain Gas or Electric Meters
Section 116a - Disconnection of Services in Case of Fire, Explosion or Other Disaster
Section 117 - Written Statement of Amount Recorded Given by Meter Reader
Section 118 - Easy Ascertainment of Electric Meter Reading
Section 120 - Testing Electric Meters in Use; Cost of Test
Section 122 - Use of Incorrect Meter; Refund
Section 123 - Prepayment Meters; Risk of Loss of Deposits
Section 124 - Entry of Premises to Stop Gas or Electricity
Section 124a - Shutting Off or Failing to Restore Service During Serious Illness
Section 124b - Shutting Off Gas or Electric Service for Failure to Pay for Appliances; Prohibition
Section 124d - Shutting Off Gas or Electric Service to Tenants Not Customer of Record
Section 124e - Termination of Gas and Electric Service; Households With Residents 65 or Older
Section 124f - Shutting Off Service During Financial Hardship
Section 124g - Restoration of Service Upon Payment
Section 124h - Shutting Off Service in Residence Where Infant Domiciled
Section 125 - Refusal to Supply Because of Default of Previous Occupant
Section 125a - Supply to Commonwealth or Municipality After Expiration of Contract; Price
Section 126a - Impersonating an Officer or Servant of a Gas or Electric Company; Penalties
Section 127 - Intentional Injury to Electric Meter or Other Property; Penalty; Prima Facie Evidence
Section 132 - Exemption of Trust Fund From Certain Insurance Laws
Section 133 - Emergency Mutual Aid
Section 134 - Load Aggregation Programs
Section 135 - Corporate Retail Load Aggregators
Section 139a - Small Hydroelectric Power Net Metering Facilities Program
Section 140 - Neighborhood Net Metering Facility; Election of Net Metering; Rules and Regulations
Section 141 - Decisions or Actions Regarding Rate Design; Adjustment to Low-Income Rate Discount
Section 145 - Plan for Replacement or Improvement of Aging or Leaking Natural Gas Infrastructure