West Virginia Code
Article 2. Powers and Duties of Public Service Commission
§24-2-1l. Modernization and Improvement of Coal-Fired Boilers at Electric Power Plants; Findings; Expedited Process; Requirements; Rulemaking

(a) The Legislature hereby finds that:
(1) West Virginia is rich in energy resources, which provide many advantages to the state, its economy and its citizens;
(2) West Virginia's abundant coal reserves have created, and will continue to create, many benefits to the state and its citizens;
(3) West Virginia is experiencing a significant downturn in the coal industry as a result of increasing environmental regulation and increased competition from natural gas and oil;
(4) Stabilization of the coal industry to maintain its accompanying benefits to the state and its citizens requires West Virginia to be proactive and focus on the modernization and improvement of coal-fired boilers used by electric utilities in this state to allow the more efficient use of coal in the generation of electricity with reduced environmental impact;
(5) A comprehensive program of modernizing, upgrading and improving coal-fired boilers at existing West Virginia power plants owned by electric utilities at reasonable cost to ratepayers, will benefit the customers of the electric utilities, the public in West Virginia and the economy of the state as a whole;
(6) A coal-fired boiler modernization and improvement program will create jobs, provide for continued and enhanced safety and reliability of aging electrical generation infrastructure, and provide for more economical generation of electricity from coal, all of which will benefit customers located throughout the state; and
(7) Efforts to modernize and improve coal-fired boilers owned by electric utilities and used to generate electricity in this state involve the investment of capital and the incurrence of associated incremental costs. Accordingly, in order for the electric utility undertaking those coal-fired boiler modernization and improvement programs to attract the necessary capital, the electric utility should be permitted to recover the incremental rate of return, related income taxes, depreciation and property taxes associated with the coal-fired boiler modernization and improvement programs commencing with the implementation of a coal-fired boiler modernization and improvement program approved by the commission without waiting for a full base rate tariff filing, as more fully described in subsection (f) of this section.
(b) Electric utilities may file with the commission an application for a multiyear comprehensive program for modernizing and improving coal-fired boilers at power plants located in this state and owned, in whole or in part, by the electric utility. Subject to commission review and approval, a program may be amended and updated by the electric utility as circumstances warrant. The recovery of costs in support of the program shall be allowed in the manner set forth in this section if the proposed program and related rates are found to be just, reasonable, and based on prudent investments that are used and useful to the utilities’ West Virginia ratepayers.
(c) The application is in lieu of a proceeding pursuant to section eleven of this article and shall contain the following:
(1) A description of the coal-fired boiler modernization and improvement program, in such detail as the commission prescribes, which may include costs associated with or incidental to the reduction of emissions or compliance with environmental requirements, the projected cost, and timing of the installation of equipment and facilities that the applicant proposes to replace, construct, modernize and/or improve;
(2) The projected net cost, on an annual basis, of the replacement, construction or improvements;
(3) The projected starting and completion dates for the modernization and improvement program;
(4) The projected cost of debt for the coal-fired boiler modernization and improvement program funding and the projected capital structure for coal-fired boiler modernization and improvement program funding;
(5) Testimony, exhibits or other evidence that demonstrates the need for the modernization and improvement of coal-fired boilers in order to provide and maintain adequate, efficient, safe, reliable and reasonably priced electrical generation;
(6) A proposed cost recovery mechanism consistent with this section; and
(7) Other information the applicant considers relevant or the commission requires.
(d) Upon filing of the application, the applicant shall publish, in the form the commission directs, which form shall include, but not be limited to, the anticipated rates and, if any, rate increase under the proposal, by average percentage and dollar amount for customers within a class of service, as a Class I legal advertisement in compliance with the provisions of article three, chapter fifty-nine of this code, the publication area to be each county in which service is provided by the electrical utility, a notice of the filing of the application and that the commission shall hold a hearing on the application within one-hundred eighty days of the notice; unless no opposition to the application is received by the Public Service Commission within one week of the proposed hearing date, in which case the hearing can be waived, and issue a final order within two-hundred seventy days of the application filing date.
(e) Upon notice and hearing, if required by the commission, the commission shall approve the coal-fired boiler modernization and improvement program and allow expedited recovery of costs related to the expenditures as provided in subsection (f) of this section if the commission finds that the expenditures and the associated rate requirements are just, reasonable, prudent, not contrary to the West Virginia public interest and will allow for the provision and maintenance of adequate, efficient, safe, reliable and reasonably priced electricity generated from coal.
(f) Upon commission approval, electric utilities will be authorized to implement the coal-fired boiler modernization and improvement programs and to recover related incremental capital and operation and maintenance costs, net of contributions to recovery of return and depreciation and property tax expenses directly attributable to the coal-fired boiler modernization and improvement program provided by electric utility’s customers, if any, as provided in the following:
(1) An allowance for return shall be calculated by applying a rate of return to the average planned net incremental increase to rate base attributable to the coal-fired boiler modernization and improvement program for the coming year, considering the projected amount and timing of expenditures under the coal-fired boiler modernization and improvement program plus any expenditures in previous years of the program. The rate of return shall be determined by utilizing the rate of return on equity authorized by the commission in the electric utility's most recent rate case proceeding or in the case of a settled rate case, a rate of return on equity as determined by the commission, and the projected cost of the electric utility's debt during the period of the coal-fired boiler modernization and improvement program to determine the weighted cost of capital based upon the electric utility's capital structure.
(2) Income taxes at the corporate statutory income rates applicable to the return allowed on the coal-fired boiler modernization and improvement program shall be calculated for inclusion in rates.
(3) Incremental depreciation and property tax expenses directly attributable to the coal-fired boiler modernization and improvement program shall be estimated for the upcoming year.
(4) Following commission approval of its coal-fired boiler modernization and improvement program, an electric utility shall place into effect rates that include an increment that recovers the allowance for return, operation and maintenance expense, related income taxes, depreciation and property tax expenses associated with the electric utility's estimated coal-fired boiler modernization and improvement program investments for the upcoming year, net of contributions to recovery of those incremental costs provided by the electric utility’s customers, if any, ("incremental cost recovery increment"). In each year subsequent to the order approving the coal-fired boiler modernization and improvement program and an incremental cost recovery increment, the electric utility shall file a petition with the commission setting forth a new proposed incremental cost recovery increment based on investments and expenses to be made in the subsequent year, plus any under-recovery or minus any over-recovery of actual incremental costs attributable to the coal-fired boiler modernization and improvement program investments, for the preceding year.
(g) The electric utility may make any accounting accruals necessary to establish a regulatory asset or liability through which actual incremental costs incurred and costs recovered through the rate mechanism are tracked.
(h) Electric utilities may defer incremental operation and maintenance expenditures attributable to regulatory and compliance-related requirements introduced after the electric utility's last rate case proceeding and not included in the electric utility's current base rates. In a future rate case, the commission shall allow recovery of the deferred costs amortized over a reasonable period of time to be determined by the commission if the commission finds that the costs were reasonable and prudently incurred and were not reflected in rates in prior rate cases.

Structure West Virginia Code

West Virginia Code

Chapter 24. Public Service Commission

Article 2. Powers and Duties of Public Service Commission

§24-2-1. Jurisdiction of Commission; Waiver of Jurisdiction

§24-2-1a. Authority of Commission to Enter and Inspect Railroad Property

§24-2-1b. Additional Jurisdiction of Commission

§24-2-1c. Certificates of Need Required for Solid Waste Facilities

§24-2-1d. Future Electric Generating Capacity Requirements

§24-2-1e. Rate Recovery for Construction of Electric Transmission Facilities

§24-2-1f. Jurisdiction of Commission Over Solid Waste Facilities

§24-2-1g. Rate Incentives for Utility Investment in Qualified Clean Coal and Clean Air Control Technology Facilities

§24-2-1h. Additional Powers and Duties of Commission to Control Flow of Solid Waste

§24-2-1i. Commission Authorized to Issue Emergency Certificate of Need to Certain Commercial Solid Waste Facilities; Division of Environmental Protection to Modify Facility Permit; Criteria for Emergency Certificates

§24-2-1j. Special Rates for Energy Intensive Industrial Consumers of Electric Power

§24-2-1k. Natural Gas Infrastructure Expansion, Development, Improvement and Job Creation; Findings; Expedited Process; Requirements; Rulemaking

§24-2-1l. Modernization and Improvement of Coal-Fired Boilers at Electric Power Plants; Findings; Expedited Process; Requirements; Rulemaking

§24-2-1m. Commission Jurisdiction Does Not Extend to Materials Recovery Facilities, Mixed Waste Processing Facilities, and Certain Mixed Waste Processing and Resource Recovery Facilities

§24-2-1n. West Virginia Business Ready Sites Program

§24-2-1o. Renewable Energy Facilities Program

§24-2-1p. Middle-Mile Fiber Broadband Infrastructure Expansion Program

§24-2-1q. Base Fuel Supply Requirements for Electric Grid Resiliency

§24-2-2. General Power of Commission to Regulate Public Utilities

§24-2-3. General Power of Commission With Respect to Rates

§24-2-3a. Advance Notice of Filing of General Rate Case Required

§24-2-3b. Transitional Suspension of Schedule; Legislative Findings; Procedure

§24-2-3c. Cessation of Jurisdiction Over Rates for Certain Services Subject to Competition

§24-2-4. Procedure for Changing Rates

§24-2-4a. Procedure for Changing Rates After June 30, 1981

§24-2-4b. Procedures for Changing Rates of Electric and Natural Gas Cooperatives, Local Exchange Services of Telephone Cooperatives, and Municipally Operated Public Utilities

§24-2-4c. Rate Increases for Natural Gas Public Utilities Relating to Purchase of Natural Gas From Suppliers; Obtaining New Supplies of Natural Gas to Meet Obligations

§24-2-4d. Procedures for Intrastate Rail Carrier Rate-Making and Compliants

§24-2-4e. Environmental Control Bonds

§24-2-4f. Consumer Rate Relief Bonds

§24-2-4g. Establishing the Value of Utility Assets in the Context of the Acquisition of a Utility or Utility Assets and Providing for the Combination or Allocation of Water and Wastewater Revenue Requirements

§24-2-5. Supervision of Public Utilities Licensed by Municipalities, County Courts or Otherwise; Right to Enter Premises, Inspect and Correct Meters

§24-2-6. Power as to Connecting Telephone and Telegraph Services

§24-2-7. Unreasonable, etc., Regulations, Practices and Services; Receivership; Procedures Respecting Receivership; Appointment and Compensation of Receiver; Liquidation

§24-2-8. System of Accounts to Be Kept by Public Utilities; Uniform Accounting System for Public Service Districts and Municipally Owned Public Utilities

§24-2-9. Information Concerning Rates, etc., of Public Utilities May Be Required and Published by Commission

§24-2-10. Power to Subpoena Witnesses, Take Testimony and Administer Oaths; Contempt; Self-Incrimination

§24-2-11. Requirements for Certificate of Public Convenience and Necessity

§24-2-11a. Requirement for Certificate of Public Convenience and Necessity Before Beginning Construction of High Voltage Transmission Line; Contents of Application; Notice; Hearing; Criteria for Granting or Denying Certificate; Regulations

§24-2-11b. Continuing Prudence Reviews

§24-2-11c. Siting Certificates for Certain Electric Generating Facilities or Material Modifications Thereof

§24-2-11d. Revocation of Certificate of Public Convenience and Necessity; Acquisition of Facilities by Capable Public Utility

§24-2-12. What Acts May Not Be Done Without Consent of Commission; Consent in Advance of Exemption of Transactions; When Sale, etc., of Franchises, Mergers, etc., Void

§24-2-12a. Issuance of Stock; Requirement of Applying to Commission for Orders Authorizing Issuance; Hearing and Investigation on Application; Order; When Issuance Is Void

§24-2-13. Enforcement of Federal Acts

§24-2-14. Reports Required to Be Filed by Generating Electric Utilities; Contents; Powers of Commission to Obtain Information; Availability to the Public; Certain Studies Required

§24-2-15. Automatic Adjustment Clauses or Fuel Adjustment Clauses Prohibited

§24-2-16. Anticompetitive Clauses in Natural Gas Contracts Prohibited

§24-2-17. Registry of Electric Customers on Life Support Systems; Notification Prior to Scheduled Outages; Priority of Service Restoration; Limitation of Liability; Life Support Defined

§24-2-18. Legislative Findings on Electric Service; Jurisdictionof the Commission to Determine Public Interest Inpermitting Retail Access to Competitive Power Supply Markets; Participation of Interested Parties; Development of Deregulation Plan; Legi...

§24-2-19. Integrated Resource Planning Required

§24-2-20. Direct Use of Natural Gas

§24-2-21. Required Notice for Power Plant Closure or Sale