West Virginia Code
Article 2. Powers and Duties of Public Service Commission
§24-2-11a. Requirement for Certificate of Public Convenience and Necessity Before Beginning Construction of High Voltage Transmission Line; Contents of Application; Notice; Hearing; Criteria for Granting or Denying Certificate; Regulations

(a) No public utility, person or corporation may begin construction of a high voltage transmission line of two hundred thousand volts or over, which line is not an ordinary extension of an existing system in the usual course of business as defined by the Public Service Commission, unless and until it or he or she has obtained from the Public Service Commission a certificate of public convenience and necessity approving the construction and proposed location of the transmission line.
(b) The application for the certificate shall be in the form the commission prescribes and shall contain:
(1) A description, in such detail as the commission prescribes, of the location and type of line facilities which the applicant proposes to construct;
(2) A statement justifying the need for the facilities;
(3) A statement of the environmental impact of the line facilities; and
(4) Other information the applicant considers relevant or the commission requires.
(c) Upon the filing of the application, the applicant shall publish, in the form the commission directs, as a Class II legal advertisement in compliance with the provisions of article three, chapter fifty-nine of this code, the publication area for the publication to be each county in which any portion of the proposed transmission line is to be constructed, a notice of the filing of the application and that the commission may approve the application unless within fifteen days after completion of publication a written request for a hearing on the application has been received by the commission from a person or persons alleging that the proposed transmission line or its location is against the public interest. If the request is timely received, the commission shall set the matter for hearing on a date within sixty days from completion of the publication, and shall require the applicant to publish notice of the time and place of hearing in the same manner as is required for the publication of notice of the filing of the application. At least thirty business days before the deadline set by the Public Service Commission to file a petition to intervene with regard to the application, the applicant shall serve notice by certified mail to all owners of surface real estate that lie within the preferred corridor of the proposed transmission line. Notice received by a named owner who is the recipient of record of the most recent tax bill that has been issued by the county sheriff's office for a parcel of land at the time of the filing of the application is sufficient notice regarding that parcel for purposes of this subsection.
(d) Within sixty days after the filing of the application, or if hearing is held on the application, within ninety days after final submission on oral argument or brief, the commission may approve the application if it finds that the proposed transmission line:
(1) Will economically, adequately and reliably contribute to meeting the present and anticipated requirements for electric power of the customers served by the applicant or is necessary and desirable for present and anticipated reliability of service for electric power for its service area or region;
(2) Will be in the best interest of West Virginia customers and its citizens; and
(3) Will result in an acceptable balance between reasonable power needs and reasonable environmental factors.
(e) The commission may impose conditions upon its approval of the application, or modify the applicant's proposal, to achieve an acceptable balance between reasonable power needs and reasonable environmental factors.
(f) The provisions of this section do not apply to the construction of line facilities which will be part of a transmission line for which any right-of-way has been acquired prior to January 1, 1973.
(g) The commission shall prescribe rules it considers proper for the administration and enforcement of the provisions of this section, which rules shall be promulgated in accordance with the applicable provisions of chapter twenty-nine-a of this code.
(h) Notwithstanding any other provision of the law to the contrary, the commission shall determine, in its discretion, which transmission line or lines crossing above the Ohio River must be marked to be made visible to airborne traffic flying in any area where the lines exist, and shall promulgate rules requiring that all public utilities or persons who install or maintain the lines make the necessary markings.

Structure West Virginia Code

West Virginia Code

Chapter 24. Public Service Commission

Article 2. Powers and Duties of Public Service Commission

§24-2-1. Jurisdiction of Commission; Waiver of Jurisdiction

§24-2-1a. Authority of Commission to Enter and Inspect Railroad Property

§24-2-1b. Additional Jurisdiction of Commission

§24-2-1c. Certificates of Need Required for Solid Waste Facilities

§24-2-1d. Future Electric Generating Capacity Requirements

§24-2-1e. Rate Recovery for Construction of Electric Transmission Facilities

§24-2-1f. Jurisdiction of Commission Over Solid Waste Facilities

§24-2-1g. Rate Incentives for Utility Investment in Qualified Clean Coal and Clean Air Control Technology Facilities

§24-2-1h. Additional Powers and Duties of Commission to Control Flow of Solid Waste

§24-2-1i. Commission Authorized to Issue Emergency Certificate of Need to Certain Commercial Solid Waste Facilities; Division of Environmental Protection to Modify Facility Permit; Criteria for Emergency Certificates

§24-2-1j. Special Rates for Energy Intensive Industrial Consumers of Electric Power

§24-2-1k. Natural Gas Infrastructure Expansion, Development, Improvement and Job Creation; Findings; Expedited Process; Requirements; Rulemaking

§24-2-1l. Modernization and Improvement of Coal-Fired Boilers at Electric Power Plants; Findings; Expedited Process; Requirements; Rulemaking

§24-2-1m. Commission Jurisdiction Does Not Extend to Materials Recovery Facilities, Mixed Waste Processing Facilities, and Certain Mixed Waste Processing and Resource Recovery Facilities

§24-2-1n. West Virginia Business Ready Sites Program

§24-2-1o. Renewable Energy Facilities Program

§24-2-1p. Middle-Mile Fiber Broadband Infrastructure Expansion Program

§24-2-1q. Base Fuel Supply Requirements for Electric Grid Resiliency

§24-2-2. General Power of Commission to Regulate Public Utilities

§24-2-3. General Power of Commission With Respect to Rates

§24-2-3a. Advance Notice of Filing of General Rate Case Required

§24-2-3b. Transitional Suspension of Schedule; Legislative Findings; Procedure

§24-2-3c. Cessation of Jurisdiction Over Rates for Certain Services Subject to Competition

§24-2-4. Procedure for Changing Rates

§24-2-4a. Procedure for Changing Rates After June 30, 1981

§24-2-4b. Procedures for Changing Rates of Electric and Natural Gas Cooperatives, Local Exchange Services of Telephone Cooperatives, and Municipally Operated Public Utilities

§24-2-4c. Rate Increases for Natural Gas Public Utilities Relating to Purchase of Natural Gas From Suppliers; Obtaining New Supplies of Natural Gas to Meet Obligations

§24-2-4d. Procedures for Intrastate Rail Carrier Rate-Making and Compliants

§24-2-4e. Environmental Control Bonds

§24-2-4f. Consumer Rate Relief Bonds

§24-2-4g. Establishing the Value of Utility Assets in the Context of the Acquisition of a Utility or Utility Assets and Providing for the Combination or Allocation of Water and Wastewater Revenue Requirements

§24-2-5. Supervision of Public Utilities Licensed by Municipalities, County Courts or Otherwise; Right to Enter Premises, Inspect and Correct Meters

§24-2-6. Power as to Connecting Telephone and Telegraph Services

§24-2-7. Unreasonable, etc., Regulations, Practices and Services; Receivership; Procedures Respecting Receivership; Appointment and Compensation of Receiver; Liquidation

§24-2-8. System of Accounts to Be Kept by Public Utilities; Uniform Accounting System for Public Service Districts and Municipally Owned Public Utilities

§24-2-9. Information Concerning Rates, etc., of Public Utilities May Be Required and Published by Commission

§24-2-10. Power to Subpoena Witnesses, Take Testimony and Administer Oaths; Contempt; Self-Incrimination

§24-2-11. Requirements for Certificate of Public Convenience and Necessity

§24-2-11a. Requirement for Certificate of Public Convenience and Necessity Before Beginning Construction of High Voltage Transmission Line; Contents of Application; Notice; Hearing; Criteria for Granting or Denying Certificate; Regulations

§24-2-11b. Continuing Prudence Reviews

§24-2-11c. Siting Certificates for Certain Electric Generating Facilities or Material Modifications Thereof

§24-2-11d. Revocation of Certificate of Public Convenience and Necessity; Acquisition of Facilities by Capable Public Utility

§24-2-12. What Acts May Not Be Done Without Consent of Commission; Consent in Advance of Exemption of Transactions; When Sale, etc., of Franchises, Mergers, etc., Void

§24-2-12a. Issuance of Stock; Requirement of Applying to Commission for Orders Authorizing Issuance; Hearing and Investigation on Application; Order; When Issuance Is Void

§24-2-13. Enforcement of Federal Acts

§24-2-14. Reports Required to Be Filed by Generating Electric Utilities; Contents; Powers of Commission to Obtain Information; Availability to the Public; Certain Studies Required

§24-2-15. Automatic Adjustment Clauses or Fuel Adjustment Clauses Prohibited

§24-2-16. Anticompetitive Clauses in Natural Gas Contracts Prohibited

§24-2-17. Registry of Electric Customers on Life Support Systems; Notification Prior to Scheduled Outages; Priority of Service Restoration; Limitation of Liability; Life Support Defined

§24-2-18. Legislative Findings on Electric Service; Jurisdictionof the Commission to Determine Public Interest Inpermitting Retail Access to Competitive Power Supply Markets; Participation of Interested Parties; Development of Deregulation Plan; Legi...

§24-2-19. Integrated Resource Planning Required

§24-2-20. Direct Use of Natural Gas

§24-2-21. Required Notice for Power Plant Closure or Sale