Effective: October 11, 2021
Latest Legislation: Senate Bill 52 - 134th General Assembly
(A) The decommissioning plan submitted to the power siting board under section 4906.21 of the Revised Code shall be prepared by a professional engineer registered with the state board of registration for professional engineers and surveyors. The board may reject the engineer chosen by the applicant and to require the applicant to choose another qualified engineer.
(B) The plan shall contain the following:
(1) A list of all parties responsible for decommissioning;
(2) A schedule of decommissioning activities, not to extend beyond twelve months from the date the utility facility ceases operation;
(3) An estimate of the full costs of decommissioning the utility facility, including the proper disposal of all facility components and restoration of the land on which the facility is located to its pre-construction state. The estimate shall not take into account the salvage value of any materials from the facility.
Last updated July 23, 2021 at 4:51 PM
Structure Ohio Revised Code
Section 4906.01 | Power Siting Definitions.
Section 4906.02 | Power Siting Board Organization.
Section 4906.021 | Ad Hoc Member Requirement, Qualifications.
Section 4906.022 | Ad Hoc Member Designation.
Section 4906.023 | Limitation on Ad Hoc Member of Intervening Township or County.
Section 4906.024 | Ex Parte Communication Exemption and Requirements for Ad Hoc Members.
Section 4906.025 | Ad Hoc Member Confidentiality Requirements.
Section 4906.03 | Powers and Duties of Power Siting Board.
Section 4906.04 | Certificate Required for Construction of Major Utility Facility.
Section 4906.05 | Certificate Exemptions.
Section 4906.06 | Certificate Application.
Section 4906.07 | Public Hearing on Application.
Section 4906.08 | Parties - Testimony.
Section 4906.09 | Record of Hearing.
Section 4906.10 | Basis for Decision Granting or Denying Certificate.
Section 4906.101 | No Power Siting Board Certificate or Amendment in Restricted Area.
Section 4906.102 | No Power Siting Board Certificate or Amendment Where Prohibited.
Section 4906.103 | No Power Siting Board Certificate or Amendment Where Limited.
Section 4906.105 | Report to the General Assembly.
Section 4906.11 | Opinion Stating Reason for Decision.
Section 4906.12 | Procedures of Public Utilities Commission to Be Followed.
Section 4906.13 | No Local Jurisdiction.
Section 4906.14 | Joint Proceedings.
Section 4906.20 | Certificate Required to Construct Certain Wind Farms.
Section 4906.201 | Setback Requirements.
Section 4906.21 | Decommissioning Plan for Solar and Wind Generation Required.
Section 4906.211 | Decommissioning Plan Requirements and Estimated Costs.
Section 4906.212 | Decommissioning Estimated Costs Recalculation.
Section 4906.22 | Decommissioning Performance Bond Required.
Section 4906.221 | Decommissioning Performance Bond Amount.
Section 4906.222 | Decommissioning Performance Bond Update.
Section 4906.30 | No Power Siting Board Certificate or Amendment for Nonconformity.
Section 4906.31 | Power Siting Board Application Provided to Township and County.
Section 4906.97 | Notice and Hearing of Complaint.