Ohio Revised Code
Chapter 4906 | Power Siting
Section 4906.21 | Decommissioning Plan for Solar and Wind Generation Required.

Effective: October 11, 2021
Latest Legislation: Senate Bill 52 - 134th General Assembly
(A) For the purposes of this section and sections 4906.21 to 4906.232 of the Revised Code:
(1) "Applicant" means an applicant for a certificate, or a material amendment to an existing certificate, from the power siting board to construct, operate, or maintain a utility facility, and includes any subsequent person to whom the certificate is transferred.
(2) "Material amendment" and "utility facility" have the same meanings as in section 303.57 of the Revised Code.
(B) At least sixty days prior to the commencement of construction of a utility facility, the applicant shall submit a comprehensive decommissioning plan for review and approval by the power siting board.
Last updated August 18, 2021 at 11:36 AM

Structure Ohio Revised Code

Ohio Revised Code

Title 49 | Public Utilities

Chapter 4906 | Power Siting

Section 4906.01 | Power Siting Definitions.

Section 4906.02 | Power Siting Board Organization.

Section 4906.021 | Ad Hoc Member Requirement, Qualifications.

Section 4906.022 | Ad Hoc Member Designation.

Section 4906.023 | Limitation on Ad Hoc Member of Intervening Township or County.

Section 4906.024 | Ex Parte Communication Exemption and Requirements for Ad Hoc Members.

Section 4906.025 | Ad Hoc Member Confidentiality Requirements.

Section 4906.03 | Powers and Duties of Power Siting Board.

Section 4906.04 | Certificate Required for Construction of Major Utility Facility.

Section 4906.05 | Certificate Exemptions.

Section 4906.06 | Certificate Application.

Section 4906.07 | Public Hearing on Application.

Section 4906.08 | Parties - Testimony.

Section 4906.09 | Record of Hearing.

Section 4906.10 | Basis for Decision Granting or Denying Certificate.

Section 4906.101 | No Power Siting Board Certificate or Amendment in Restricted Area.

Section 4906.102 | No Power Siting Board Certificate or Amendment Where Prohibited.

Section 4906.103 | No Power Siting Board Certificate or Amendment Where Limited.

Section 4906.105 | Report to the General Assembly.

Section 4906.11 | Opinion Stating Reason for Decision.

Section 4906.12 | Procedures of Public Utilities Commission to Be Followed.

Section 4906.13 | No Local Jurisdiction.

Section 4906.14 | Joint Proceedings.

Section 4906.20 | Certificate Required to Construct Certain Wind Farms.

Section 4906.201 | Setback Requirements.

Section 4906.21 | Decommissioning Plan for Solar and Wind Generation Required.

Section 4906.211 | Decommissioning Plan Requirements and Estimated Costs.

Section 4906.212 | Decommissioning Estimated Costs Recalculation.

Section 4906.22 | Decommissioning Performance Bond Required.

Section 4906.221 | Decommissioning Performance Bond Amount.

Section 4906.222 | Decommissioning Performance Bond Update.

Section 4906.30 | No Power Siting Board Certificate or Amendment for Nonconformity.

Section 4906.31 | Power Siting Board Application Provided to Township and County.

Section 4906.97 | Notice and Hearing of Complaint.

Section 4906.98 | Prohibited Acts.

Section 4906.99 | Penalty.