Effective: September 10, 2012
Latest Legislation: Senate Bill 315 - 129th General Assembly
The power siting board shall:
(A) Require such information from persons subject to its jurisdiction as it considers necessary to assist in the conduct of hearings and any investigations or studies it may undertake;
(B) Conduct any studies or investigations that it considers necessary or appropriate to carry out its responsibilities under this chapter;
(C) Adopt rules establishing criteria for evaluating the effects on environmental values of proposed and alternative sites, and projected needs for electric power, and such other rules as are necessary and convenient to implement this chapter, including rules governing application fees, supplemental application fees, and other reasonable fees to be paid by persons subject to the board's jurisdiction. The board shall make an annual accounting of its collection and use of these fees and shall issue an annual report of its accounting, in the form and manner prescribed by its rules, not later than the last day of June of the year following the calendar year to which the report applies.
(D) Approve, disapprove, or modify and approve applications for certificates;
(E) Notwithstanding sections 4906.06 to 4906.14 of the Revised Code, the board may adopt rules to provide for an accelerated review of an application for a construction certificate for construction of a major utility facility related to a coal research and development project as defined in section 1555.01 of the Revised Code, or to a coal development project as defined in section 1551.30 of the Revised Code, submitted to the Ohio coal development office for review under division (B)(7) of section 1551.33 of the Revised Code. Applications for construction certificates for construction of major utility facilities for Ohio coal research and development shall be filed with the board on the same day as the proposed facility or project is submitted to the Ohio coal development office for review.
The board shall render a decision on an application for a construction certificate within ninety days after receipt of the application and all of the data and information it may require from the applicant. In rendering a decision on an application for a construction certificate, the board shall only consider the criteria and make the findings and determinations set forth in divisions (A)(2), (3), (5), and (7) and division (B) of section 4906.10 of the Revised Code.
(F) Notwithstanding sections 4906.06 to 4906.14 of the Revised Code, the board shall adopt rules to provide for an accelerated review of an application for a construction certificate for any of the following:
(1) An electric transmission line that is:
(a) Not more than two miles in length;
(b) Primarily needed to attract or meet the requirements of a specific customer or specific customers;
(c) Necessary to maintain reliable electric service as a result of the retirement or shutdown of an electric generating facility located within the state; or
(d) A rebuilding of an existing transmission line.
(2) An electric generating facility that uses waste heat or natural gas and is primarily within the current boundary of an existing industrial or electric generating facility;
(3) A gas pipeline that is not more than five miles in length or is primarily needed to meet the requirements of a specific customer or specific customers.
The board shall adopt rules that provide for the automatic certification to any entity described in this division when an application by any such entity is not suspended by the board, an administrative law judge, or the chairperson or executive director of the board for good cause shown, within ninety days of submission of the application. If an application is suspended, the board shall approve, disapprove, or modify and approve the application not later than ninety days after the date of the suspension.
Structure Ohio Revised Code
Section 4906.01 | Power Siting Definitions.
Section 4906.02 | Power Siting Board Organization.
Section 4906.021 | Ad Hoc Member Requirement, Qualifications.
Section 4906.022 | Ad Hoc Member Designation.
Section 4906.023 | Limitation on Ad Hoc Member of Intervening Township or County.
Section 4906.024 | Ex Parte Communication Exemption and Requirements for Ad Hoc Members.
Section 4906.025 | Ad Hoc Member Confidentiality Requirements.
Section 4906.03 | Powers and Duties of Power Siting Board.
Section 4906.04 | Certificate Required for Construction of Major Utility Facility.
Section 4906.05 | Certificate Exemptions.
Section 4906.06 | Certificate Application.
Section 4906.07 | Public Hearing on Application.
Section 4906.08 | Parties - Testimony.
Section 4906.09 | Record of Hearing.
Section 4906.10 | Basis for Decision Granting or Denying Certificate.
Section 4906.101 | No Power Siting Board Certificate or Amendment in Restricted Area.
Section 4906.102 | No Power Siting Board Certificate or Amendment Where Prohibited.
Section 4906.103 | No Power Siting Board Certificate or Amendment Where Limited.
Section 4906.105 | Report to the General Assembly.
Section 4906.11 | Opinion Stating Reason for Decision.
Section 4906.12 | Procedures of Public Utilities Commission to Be Followed.
Section 4906.13 | No Local Jurisdiction.
Section 4906.14 | Joint Proceedings.
Section 4906.20 | Certificate Required to Construct Certain Wind Farms.
Section 4906.201 | Setback Requirements.
Section 4906.21 | Decommissioning Plan for Solar and Wind Generation Required.
Section 4906.211 | Decommissioning Plan Requirements and Estimated Costs.
Section 4906.212 | Decommissioning Estimated Costs Recalculation.
Section 4906.22 | Decommissioning Performance Bond Required.
Section 4906.221 | Decommissioning Performance Bond Amount.
Section 4906.222 | Decommissioning Performance Bond Update.
Section 4906.30 | No Power Siting Board Certificate or Amendment for Nonconformity.
Section 4906.31 | Power Siting Board Application Provided to Township and County.
Section 4906.97 | Notice and Hearing of Complaint.