Effective: October 11, 2021
Latest Legislation: Senate Bill 52 - 134th General Assembly
(A) The power siting board shall render a decision upon the record either granting or denying the application as filed, or granting it upon such terms, conditions, or modifications of the construction, operation, or maintenance of the major utility facility as the board considers appropriate. The certificate shall be subject to sections 4906.101, 4906.102, and 4906.103 of the Revised Code and conditioned upon the facility being in compliance with standards and rules adopted under section 4561.32 and Chapters 3704., 3734., and 6111. of the Revised Code. An applicant may withdraw an application if the board grants a certificate on terms, conditions, or modifications other than those proposed by the applicant in the application.
The board shall not grant a certificate for the construction, operation, and maintenance of a major utility facility, either as proposed or as modified by the board, unless it finds and determines all of the following:
(1) The basis of the need for the facility if the facility is an electric transmission line or gas pipeline;
(2) The nature of the probable environmental impact;
(3) That the facility represents the minimum adverse environmental impact, considering the state of available technology and the nature and economics of the various alternatives, and other pertinent considerations;
(4) In the case of an electric transmission line or generating facility, that the facility is consistent with regional plans for expansion of the electric power grid of the electric systems serving this state and interconnected utility systems and that the facility will serve the interests of electric system economy and reliability;
(5) That the facility will comply with Chapters 3704., 3734., and 6111. of the Revised Code and all rules and standards adopted under those chapters and under section 4561.32 of the Revised Code. In determining whether the facility will comply with all rules and standards adopted under section 4561.32 of the Revised Code, the board shall consult with the office of aviation of the division of multi-modal planning and programs of the department of transportation under section 4561.341 of the Revised Code.
(6) That the facility will serve the public interest, convenience, and necessity;
(7) In addition to the provisions contained in divisions (A)(1) to (6) of this section and rules adopted under those divisions, what its impact will be on the viability as agricultural land of any land in an existing agricultural district established under Chapter 929. of the Revised Code that is located within the site and alternative site of the proposed major utility facility. Rules adopted to evaluate impact under division (A)(7) of this section shall not require the compilation, creation, submission, or production of any information, document, or other data pertaining to land not located within the site and alternative site.
(8) That the facility incorporates maximum feasible water conservation practices as determined by the board, considering available technology and the nature and economics of the various alternatives.
(B) If the board determines that the location of all or a part of the proposed facility should be modified, it may condition its certificate upon that modification, provided that the municipal corporations and counties, and persons residing therein, affected by the modification shall have been given reasonable notice thereof.
(C) A copy of the decision and any opinion issued therewith shall be served upon each party.
Last updated July 23, 2021 at 8:10 AM
Structure Ohio Revised Code
Section 4906.01 | Power Siting Definitions.
Section 4906.02 | Power Siting Board Organization.
Section 4906.021 | Ad Hoc Member Requirement, Qualifications.
Section 4906.022 | Ad Hoc Member Designation.
Section 4906.023 | Limitation on Ad Hoc Member of Intervening Township or County.
Section 4906.024 | Ex Parte Communication Exemption and Requirements for Ad Hoc Members.
Section 4906.025 | Ad Hoc Member Confidentiality Requirements.
Section 4906.03 | Powers and Duties of Power Siting Board.
Section 4906.04 | Certificate Required for Construction of Major Utility Facility.
Section 4906.05 | Certificate Exemptions.
Section 4906.06 | Certificate Application.
Section 4906.07 | Public Hearing on Application.
Section 4906.08 | Parties - Testimony.
Section 4906.09 | Record of Hearing.
Section 4906.10 | Basis for Decision Granting or Denying Certificate.
Section 4906.101 | No Power Siting Board Certificate or Amendment in Restricted Area.
Section 4906.102 | No Power Siting Board Certificate or Amendment Where Prohibited.
Section 4906.103 | No Power Siting Board Certificate or Amendment Where Limited.
Section 4906.105 | Report to the General Assembly.
Section 4906.11 | Opinion Stating Reason for Decision.
Section 4906.12 | Procedures of Public Utilities Commission to Be Followed.
Section 4906.13 | No Local Jurisdiction.
Section 4906.14 | Joint Proceedings.
Section 4906.20 | Certificate Required to Construct Certain Wind Farms.
Section 4906.201 | Setback Requirements.
Section 4906.21 | Decommissioning Plan for Solar and Wind Generation Required.
Section 4906.211 | Decommissioning Plan Requirements and Estimated Costs.
Section 4906.212 | Decommissioning Estimated Costs Recalculation.
Section 4906.22 | Decommissioning Performance Bond Required.
Section 4906.221 | Decommissioning Performance Bond Amount.
Section 4906.222 | Decommissioning Performance Bond Update.
Section 4906.30 | No Power Siting Board Certificate or Amendment for Nonconformity.
Section 4906.31 | Power Siting Board Application Provided to Township and County.
Section 4906.97 | Notice and Hearing of Complaint.