Minnesota Statutes
Chapter 161 — Trunk Highways
Section 161.3209 — Construction Manager/general Contractor; Procedures.

Subdivision 1. Solicitation of proposals. If the commissioner determines that a construction manager/general contractor method of procurement is appropriate for a project, the commissioner shall establish a two-phase procedure for awarding the construction manager/general contractor contract, as described in subdivisions 2 and 3.
Subd. 2. Phase 1 - request for proposals. (a) The commissioner shall prepare or have prepared an RFP for each construction manager/general contractor contract as provided in this section. The RFP must contain, at a minimum, the following elements:
(1) the minimum qualifications of the construction manager/general contractor;
(2) the procedures for submitting proposals and the criteria for evaluation of qualifications and the relative weight for each criteria;
(3) the form of the contract to be awarded;
(4) the scope of intended construction work;
(5) a listing of the types of preconstruction services that will be required;
(6) an anticipated schedule for commencing and completing the project;
(7) any applicable budget limits for the project;
(8) the requirements for insurance, statutorily required performance, and payment bonds;
(9) the requirements that the construction manager/general contractor provide a letter from a surety or insurance company stating that the construction manager/general contractor is capable of obtaining a performance bond and payment bond covering the estimated contract cost;
(10) the method for how construction manager/general contractor fees for the preconstruction services contract will be negotiated;
(11) a statement that past performance or experience does not include the exercise or assertion of a person's legal rights; and
(12) any other information desired by the commissioner.
(b) Before receiving any responses to the RFP:
(1) the commissioner shall appoint a technical review committee of at least five individuals, of which one is a Department of Transportation manager who is also a licensed professional engineer in Minnesota;
(2) the technical review committee shall evaluate the construction manager/general contractor proposals according to criteria and subcriteria published in the RFP and procedures established by the commissioner. The commissioner shall, as designated in the RFP, evaluate construction manager/general contractor proposals on the basis of best value as defined in section 16C.05, or using the qualifications-based selection process set forth in section 16C.087, except that subdivision 1 of section 16C.087 shall not apply. If the commissioner does not receive at least two proposals from construction managers, the commissioner may:
(i) solicit new proposals;
(ii) revise the RFP and thereafter solicit new proposals using the revised RFP;
(iii) select another allowed procurement method; or
(iv) reject the proposals; and
(3) the technical review committee shall evaluate the responses to the request for proposals and rank the construction manager/general contractor based on the predefined criteria set forth in the RFP in accordance with paragraph (a), clause (2).
(c) Unless all proposals are rejected, the commissioner shall conduct contract negotiations for a preconstruction services contract with the construction manager/general contractor with the highest ranking. If the construction manager/general contractor with the highest ranking declines or is unable to reach an agreement, the commissioner may begin contract negotiations with the next highest ranked construction manager/general contractor.
(d) Before issuing the RFP, the commissioner may elect to issue a request for qualifications (RFQ) and short-list the most highly qualified construction managers/general contractors. The RFQ must include the procedures for submitting statements of qualification, the criteria for evaluation of qualifications, and the relative weight for each criterion. The statements of qualifications must be evaluated by the technical review committee.
Subd. 3. Phase 2 - construction manager/general contractor contract. (a) Before conducting any construction-related services, the commissioner shall:
(1) conduct an independent cost estimate for the project or each work package; and
(2) conduct contract negotiations with the construction manager/general contractor to develop a construction manager/general contractor contract. This contract must include a minimum construction manager/general contractor self-performing requirement of 30 percent of the negotiated cost. Items designated in the construction manager/general contractor contract as specialty items may be subcontracted and the cost of any specialty item performed under the subcontract will be deducted from the cost before computing the amount of work required to be performed by the contractor.
(b) If the construction manager/general contractor and the commissioner are unable to negotiate a contract, the commissioner may use other contract procurement processes or may readvertise the construction manager/general contractor contract. The construction manager/general contractor may: (1) bid or propose on the project if advertised under section 161.32 or 161.3206; or (2) join a design-build team if advertised under sections 161.3410 to 161.3426.
(c) The commissioner shall provide to all bidders or design-build teams all data shared between the commissioner and the construction manager/general contractor during the contract negotiations under this subdivision.
History: 2012 c 287 art 3 s 4; 2014 c 196 art 2 s 15; 2015 c 21 art 1 s 29; 1Sp2021 c 5 art 4 s 122
NOTE: This section, as added by Laws 2012, chapter 287, article 3, section 4, expires one year following the acceptance of 20 construction manager/general contractor contracts. Laws 2012, chapter 287, article 3, section 4, the effective date, as amended by Laws 2021, First Special Session chapter 5, article 4, section 122.

Structure Minnesota Statutes

Minnesota Statutes

Chapters 160 - 174A — Transportation

Chapter 161 — Trunk Highways

Section 161.01 — Definitions.

Section 161.04 — Trunk Highway Fund.

Section 161.045 — Highway User Tax Distribution Fund Appropriations; Trunk Highway Fund Appropriations.

Section 161.081 — Highway User Tax, Distribution, Investment.

Section 161.082 — County Turnback Account, Expenditures.

Section 161.083 — Municipal Turnback Account, Expenditure.

Section 161.084 — Surplus Funds In Turnback Accounts.

Section 161.085 — Appropriation From Turnback Accounts.

Section 161.088 — Corridors Of Commerce Program.

Section 161.089 — Report On Dedicated Fund Expenditures.

Section 161.09 — Department Orders, Files, And Records.

Section 161.095 — Travel Expense For Job Applicants.

Section 161.10 — Investigations, Recommendations, Reports.

Section 161.11 — Compensation Insurance.

Section 161.114 — Constitutional Trunk Highways.

Section 161.115 — Additional Trunk Highways.

Section 161.117 — Trunk Highways; Additional Routes.

Section 161.12 — Additional Routes Added; Federal Aid.

Section 161.122 — Restrictions On Marked Trunk Highway 51.

Section 161.1231 — Parking Facilities For I-394.

Section 161.1245 — Highway Construction; Authorizations And Restrictions.

Section 161.125 — Sound Abatement Along Highways.

Section 161.139 — Highway Designation Costs.

Section 161.14 — Names And Designations Of Certain Highways.

Section 161.141 — Northwest Angle, Connecting Highway; Federal Approval.

Section 161.1419 — Mississippi River Parkway Commission.

Section 161.142 — Great River Road.

Section 161.148 — Great River Road, Location Of Route.

Section 161.15 — Specific Location; Limitation On Deviations.

Section 161.16 — Highway Designation, Vacation, Reversion, Survey.

Section 161.162 — Definitions.

Section 161.163 — Highway Project Review.

Section 161.164 — Final Layout Approval Process.

Section 161.165 — Commissioner Action; Interstate Highways.

Section 161.166 — Commissioner Action; Other Highways.

Section 161.167 — Reimbursement Of Expenses.

Section 161.18 — Prior Easements Vest In State.

Section 161.19 — Certain Records Obtained And Filed.

Section 161.20 — General Powers Of Commissioner.

Section 161.202 — Replacement Of Public Lands.

Section 161.21 — Studies.

Section 161.23 — Excess Acquisition.

Section 161.231 — Appropriation; Proceeds From State Property.

Section 161.24 — Changes Required By Construction Of Trunk Highway.

Section 161.241 — Relocation Of Railroad Tracks, Acquisition Of Land.

Section 161.242 — Junk Yard Act.

Section 161.25 — Temporary Trunk Highway Detour; Haul Road.

Section 161.26 — Highway Maintained Across Portion Of Adjoining State.

Section 161.261 — Connector Segments With Other States.

Section 161.27 — Trunk Highways Across Bodies Of Water.

Section 161.28 — Altering Public Drainage Ditch By Trunk Highway.

Section 161.29 — Acquiring Toll Bridge For Trunk Highway System.

Section 161.30 — Marking Design.

Section 161.31 — Maps And Pamphlets.

Section 161.315 — Protection Of Public Contracts.

Section 161.32 — Contracting For Work On Trunk Highway.

Section 161.3203 — Contracts For Work For Trunk Highway.

Section 161.3206 — Best-value Contracting Authority.

Section 161.3207 — Construction Manager/general Contractor Contracts; Definitions.

Section 161.3208 — Construction Manager/general Contractor; Authority.

Section 161.3209 — Construction Manager/general Contractor; Procedures.

Section 161.321 — Small Business Contracts.

Section 161.3212 — Working Capital Fund.

Section 161.322 — Payment Of Interest To Contractors.

Section 161.33 — Employee Interest In Contract, Unlawful.

Section 161.34 — Contract Claims Against State.

Section 161.3410 — Design-build Contracts; Definitions.

Section 161.3412 — Design-build Authority.

Section 161.3414 — Determination To Use Design-build Selection Method.

Section 161.3416 — Design-build Notice; Report.

Section 161.3418 — Licensing Requirements.

Section 161.3420 — Design-build Rfq; Selection Team; Evaluation.

Section 161.3422 — Rfp For Design-build.

Section 161.3424 — Replacing Team Members.

Section 161.3426 — Design-build Award.

Section 161.36 — Federal Aid.

Section 161.361 — Advance Funding For Trunk Highway Projects.

Section 161.365 — Highway Contract Specifications; Minimum Wage.

Section 161.366 — Construction Contract; Taconite Relief Area.

Section 161.368 — Highway Contracts With Tribal Authorities.

Section 161.37 — Surplus Government Materials.

Section 161.38 — Special Agreements For Highways In Municipalities.

Section 161.39 — Aid To Other Road Authorities And State Departments.

Section 161.391 — Pavement Striping.

Section 161.40 — Joint Facilities With Division Of Emergency Management.

Section 161.41 — Surplus Property Not Needed For Highway Purposes.

Section 161.411 — Sale Of Surplus Earth Material.

Section 161.42 — Leasing Or Sale Of Sounding And Testing Equipment.

Section 161.43 — Relinquishment Of Highway Easement.

Section 161.431 — Leasing Of Highway Easement.

Section 161.433 — Use Of Highway Airspace And Subsurface.

Section 161.434 — Interstate And Trunk Highway Rights-of-way; Limited Use.

Section 161.44 — Relinquishment Of Land No Longer Needed.

Section 161.441 — Land Acquisition Agreement With Others.

Section 161.442 — Reconveyance To Former Owner.

Section 161.45 — Utility On Highway Right-of-way; Relocation.

Section 161.46 — Reimbursement Of Utility.

Section 161.462 — Fiber Collaboration Database.

Section 161.465 — Reimbursement For Fire Services.

Section 161.475 — Snow And Ice Control Materials.

Section 161.53 — Research Activities.