(a) In all matters wherein a formal petition, application, request or appeal must be submitted to a zoning commission, planning and zoning commission or zoning board of appeals under this chapter, a planning commission under chapter 126 or an inland wetlands agency under chapter 440 or an aquifer protection agency under chapter 446i and a hearing is required or otherwise held on such petition, application, request or appeal, such hearing shall commence within sixty-five days after receipt of such petition, application, request or appeal and shall be completed within thirty-five days after such hearing commences, unless a shorter period of time is required under this chapter, chapter 126, chapter 440 or chapter 446i. Notice of the hearing shall be published in a newspaper having a general circulation in such municipality where the land that is the subject of the hearing is located at least twice, at intervals of not less than two days, the first not more than fifteen days or less than ten days and the last not less than two days before the date set for the hearing. In addition to such notice, such commission, board or agency may, by regulation, provide for additional notice. Such regulations shall include provisions that the notice be mailed to persons who own land that is adjacent to the land that is the subject of the hearing or be provided by posting a sign on the land that is the subject of the hearing, or both. For purposes of such additional notice, (1) proof of mailing shall be evidenced by a certificate of mailing, (2) the person who owns land shall be the owner indicated on the property tax map or on the last-completed grand list as of the date such notice is mailed, and (3) a title search or any other additional method of identifying persons who own land that is adjacent to the land that is the subject of the hearing shall not be required. All applications and maps and documents relating thereto shall be open for public inspection. At such hearing, any person or persons may appear and be heard and may be represented by agent or by attorney. All decisions on such matters shall be rendered not later than sixty-five days after completion of such hearing, unless a shorter period of time is required under this chapter, chapter 126, chapter 440 or chapter 446i. The petitioner or applicant may consent to one or more extensions of any period specified in this subsection, provided the total extension of all such periods shall not be for longer than sixty-five days, or may withdraw such petition, application, request or appeal.
(b) Notwithstanding the provisions of subsection (a) of this section, whenever the approval of a site plan is the only requirement to be met or remaining to be met under the zoning regulations for any building, use or structure, a decision on an application for approval of such site plan shall be rendered not later than sixty-five days after receipt of such site plan. Whenever a decision is to be made on an application for subdivision approval under chapter 126 on which no hearing is held, such decision shall be rendered not later than sixty-five days after receipt of such application. Whenever a decision is to be made on an inland wetlands and watercourses application under chapter 440 on which no hearing is held, such decision shall be rendered not later than sixty-five days after receipt of such application. Whenever a decision is to be made on an aquifer protection area application under chapter 446i on which no hearing is held, such decision shall be rendered not later than sixty-five days after receipt of such application. The applicant may consent to one or more extensions of such period, provided the total period of any such extension or extensions shall not exceed sixty-five days or may withdraw such plan or application.
(c) For purposes of subsection (a) or (b) of this section and section 7-246a, the date of receipt of a petition, application, request or appeal shall be the day of the next regularly scheduled meeting of such commission, board or agency, immediately following the day of submission to such commission, board or agency or its agent of such petition, application, request or appeal or thirty-five days after such submission, whichever is sooner. If the commission, board or agency does not maintain an office with regular office hours, the office of the clerk of the municipality shall act as the agent of such commission, board or agency for the receipt of any petition, application, request or appeal.
(d) The provisions of subsection (a) of this section shall not apply to any action initiated by any zoning commission, planning commission or planning and zoning commission regarding adoption or change of any zoning regulation or boundary or any subdivision regulation.
(e) Notwithstanding the provisions of this section, if an application involves an activity regulated pursuant to sections 22a-36 to 22a-45, inclusive, and the time for a decision by a zoning commission or planning and zoning commission established pursuant to this section would elapse prior to the thirty-fifth day after a decision by the inland wetlands agency, the time period for a decision shall be extended to thirty-five days after the decision of such agency. The provisions of this subsection shall not be construed to apply to any extension consented to by an applicant or petitioner.
(f) The zoning commission, planning commission, zoning and planning commission, zoning board of appeals, inland wetlands agency or aquifer protection agency shall notify the clerk of any adjoining municipality of the pendency of any application, petition, appeal, request or plan concerning any project on any site in which: (1) Any portion of the property affected by a decision of such commission, board or agency is within five hundred feet of the boundary of the adjoining municipality; (2) a significant portion of the traffic to the completed project on the site will use streets within the adjoining municipality to enter or exit the site; (3) a significant portion of the sewer or water drainage from the project on the site will flow through and significantly impact the drainage or sewerage system within the adjoining municipality; or (4) water runoff from the improved site will impact streets or other municipal or private property within the adjoining municipality. Such notice shall be made by certified mail, return receipt requested, and shall be mailed within seven days of the date of receipt of the application, petition, request or plan. Such adjoining municipality may, through a representative, appear and be heard at any hearing on any such application, petition, appeal, request or plan.
(g) (1) Any zoning commission, planning commission or planning and zoning commission initiating any action regarding adoption or change of any zoning regulation or boundary or any subdivision regulation or regarding the preparation or amendment of the plan of conservation and development shall provide notice of such action in accordance with this subsection in addition to any other notice required under any provision of the general statutes.
(2) A zoning commission, planning commission or planning and zoning commission shall establish a public notice registry of landowners, electors and nonprofit organizations qualified as tax-exempt organizations under the provisions of Section 501(c) of the Internal Revenue Code of 1986, or any subsequent corresponding internal revenue code of the United States, as from time to time amended, requesting notice under this subsection. Each municipality shall notify residents of such registry and the process for registering for notice under this subsection. The zoning commission, planning commission or planning and zoning commission shall place on such registry the names and addresses of any such landowner, elector or organization upon written request of such landowner, elector or organization. A landowner, elector or organization may request such notice be sent by mail or by electronic mail. The name and address of a landowner, elector or organization who requests to be placed on the public notice registry shall remain on such registry for a period of three years after the establishment of such registry. Thereafter any land owner, elector or organization may request to be placed on such registry for additional periods of three years.
(3) Any notice under this subsection shall be mailed to all landowners, electors and organizations in the public notice registry not later than seven days prior to the commencement of the public hearing on such action, if feasible. Such notice may be mailed by electronic mail if the zoning commission, planning commission or planning and zoning commission or the municipality has an electronic mail service provider.
(4) No zoning commission, planning commission or planning and zoning commission shall be civilly liable to any landowner, elector or nonprofit organization requesting notice under this subsection with respect to any act done or omitted in good faith or through a bona fide error that occurred despite reasonable procedures maintained by the zoning commission, planning commission or planning and zoning commission to prevent such errors in complying with the provisions of this section.
(1971, P.A. 862, S. 12; P.A. 77-450, S. 4; P.A. 78-104, S. 1; P.A. 82-81, S. 1; P.A. 87-533, S. 10, 14; P.A. 93-385, S. 2; P.A. 99-21, S. 1; P.A. 03-177, S. 5; P.A. 04-257, S. 6; P.A. 06-80, S. 1; P.A. 07-85, S. 1; P.A. 15-68, S. 2.)
History: P.A. 77-450 reworded previous provisions and designated them as Subsec. (c) and inserted new Subsecs. (a) and (b) before and new Subsec. (d) after; P.A. 78-104 amended Subsec. (a) to allow more than one extension and changed maximum extension time from double the original period to a time equaling the original period, made Subsec. (b) applicable to cases where site plan approval is only requirement to be met or remaining to be met and clarified Subsec. (c) by replacing references to “official receipt” with references to “submission”; P.A. 82-81 provided that town clerk would act as agent for receipt of documents for any board or commission not having regular office hours; P.A. 87-533 added Subsec. (e) regarding applications involving activity regulated pursuant to Secs. 22a-36 to 22a-45, inclusive; P.A. 93-385 amended Subsec. (b) by applying provisions to all buildings, uses or structures instead of limiting applications to proposals; P.A. 99-21 amended Subsec. (a) to extend the time for completion of a hearing from 30 to 35 days after commencement; P.A. 03-177 amended Subsec. (a) to apply provisions to planning commissions and inland wetlands agencies and add provisions re public hearings, amended Subsec. (b) to add provisions re date for rendering decisions, amended Subsec. (c) to add reference to Sec. 7-246a and make conforming changes and added new Subsec. (f) re notification to adjoining municipalities, effective October 1, 2003, and applicable to applications filed on or after that date; P.A. 04-257 made technical changes in Subsec. (a), effective June 14, 2004; P.A. 06-80 amended Subsec. (a) to add provisions re mailing and posting of additional notice, amended Subsec. (d) to add reference to planning commission and to any subdivision regulation and added Subsec. (g) re a public notice registry for changes initiated by commissions for zoning regulations or boundaries, subdivision regulations or the plan of conservation and development; P.A. 07-85 amended Subsecs. (a), (b) and (f) to apply provisions to aquifer protection agency and made technical changes in Subsecs. (a) and (b); P.A. 15-68 amended Subsec. (a) by adding Subdiv. (3) re title search or other method of identifying owners of adjacent land not required for purposes of additional notice, effective June 19, 2015.
Cited. 192 C. 353; 194 C. 187; 206 C. 554; 211 C. 331; 219 C. 352; 222 C. 269; 224 C. 44; 225 C. 432; Id., 575; 230 C. 641. If site plan and accompanying documents are separable, time constraints in section do not apply. 253 C. 183. When approval for site plan and special exception are separate actions, provisions re statutory timelines do not apply. Id., 195.
Cited. 3 CA 556; 7 CA 684; 15 CA 561; 17 CA 405. Requirements satisfied only by commencement of timely public hearing. 27 CA 412. Cited. 29 CA 469; 35 CA 599; 43 CA 512. When site plan is separable from its accompanying documents and the special permit application is for a use not permitted as of right, section is not applicable, and where the special permit application must contain a site plan, automatic approval under section may not occur if commission does not meet the time limits in Sec. 8-3c. 60 CA 504. Zoning board required to hold a hearing on plaintiff's zoning application. 69 CA 230. The absence of proposed locations contemplated by an applicant in the public notice renders such notice insufficient. 116 CA 542.
Cited. 42 CS 57.
Subsec. (a):
Cited. 209 C. 812; 222 C. 911.
Cited. 14 CA 365; 23 CA 256; 33 CA 281; 35 CA 317; Id., 599. Trial court properly determined that failure of planning and zoning commission to comply with statutory notice and hearing requirements entitled individual plaintiffs to automatic approval of their application for special permit and site plan approval; notice of commission hearing was invalid and because failure to give notice was a jurisdictional defect, action of commission in denying plaintiffs' application was void. 52 CA 763. There is no language in section indicating that if the commission chose to impose on an applicant a supplemental notice requirement by regulation, that the applicant's failure to comply with the supplemental notice provision would be attributable to the commission and trigger the lengthy appeal period in Sec. 8-8(r). 165 CA 488.
Cited. 41 CS 196.
Subsec. (b):
Cited. 194 C. 152; 209 C. 812; 211 C. 331; 222 C. 269; 226 C. 684. Applicant's submission of revised site plan did not create a new 65-day period within which planning and zoning commission could act. 278 C. 408.
Cited. 2 CA 489; 21 CA 347; Id., 421; 35 CA 317. Section not unconstitutional just because it does not expressly provide for a right of appeal from automatic approval of site plan applications. Id., 599. Cited. 37 CA 348.
Subsec. (f):
It is implicit in Subdiv. (2) that a zoning commission cannot unilaterally bind an adjoining town to a determination that the streets are adequate to handle traffic from a permitted land use in the first town, therefore adjoining town's claim that it had no choice but to close adjoining road has no merit. 295 C. 802.
Structure Connecticut General Statutes
Title 8 - Zoning, Planning, Housing and Economic and Community Development
Section 8-1. - Zoning commissions.
Section 8-1aa. - Ridgeline protection: Definitions.
Section 8-1b. - Alternate members of zoning commission or combined planning and zoning commission.
Section 8-1bb. - Temporary health care structures. Municipal permit required. Municipal opt-out.
Section 8-1c. - Fees for municipal land use applications.
Section 8-1d. - Hours for holding land use public hearings.
Section 8-2a. - Copies of zoning and subdivision regulations to be available.
Section 8-2b. - Use of maps of Soil Conservation Service as standard.
Section 8-2c. - Payment of a fee in lieu of parking requirements.
Section 8-2d. - Planned unit developments under former chapter 124a continue to be valid.
Section 8-2e. - Municipal agreements regarding development rights.
Section 8-2f. - Joint applications necessary for transfer of development rights.
Section 8-2g. - Special exemption from density limits for construction of affordable housing.
Section 8-2i. - Inclusionary zoning.
Section 8-2k. - Zoning regulations re construction near lakes.
Section 8-2l. - Zoning regulations re structures or uses located in floodplain.
Section 8-2m. - Floating and overlay zones and flexible zoning districts.
Section 8-2n. - Zoning regulations re crematories.
Section 8-2o. - Zoning regulations re accessory apartments. Municipal opt-out; exception.
Section 8-2p. - Municipal opt-out re dwelling unit parking space limitations.
Section 8-3b. - Notice to regional council of governments of proposed zone or zone use change.
Section 8-3g. - Regulation of community residences for mentally ill adults and UCONN 2000 projects.
Section 8-3h. - Notice to adjoining municipalities.
Section 8-3j. - Regulation of family child care homes.
Section 8-4. - Zoning commission may be designated as planning and zoning commission.
Section 8-4a. - Zoning or planning commission may be designated as planning and zoning commission.
Section 8-4b. - Change from combined commission to separate commissions.
Section 8-5. - Zoning board of appeals. Alternate members.
Section 8-5a. - Designation of alternate members to act.
Section 8-5b. - Ordinance may provide for appointment of alternate members.
Section 8-6. - Powers and duties of board of appeals.
Section 8-6a. - Appeal to be heard before variance when both joined.
Section 8-7b. - Notice to contiguous municipalities of variance applications.
Section 8-7c. - Disclosure of beneficiaries of real property held in trust.
Section 8-7e. - Notice to adjoining municipalities of applications or requests.
Section 8-8. - Appeal from board to court. Mediation. Review by Appellate Court.
Section 8-8a. - Process for mediation.
Section 8-10. - Appeals procedure to apply to all municipalities.
Section 8-11. - Disqualification of members of zoning authorities.
Section 8-11a. - Disqualification of board member as enforcement officer.
Section 8-12. - Procedure when regulations are violated.
Section 8-12a. - Establishment of municipal penalties for violations of regulations.
Section 8-13. - Controlling requirement in case of variation.
Section 8-13a. - Nonconforming buildings, structures and land uses.