Connecticut General Statutes
Chapter 847 - Liens
Section 49-41a. - Enforcement of payment by general contractor to subcontractor and by subcontractor to its subcontractors.

(a) When any public work is awarded by a contract for which a payment bond is required by section 49-41, the contract for the public work shall contain the following provisions: (1) A requirement that the general contractor, within thirty days after payment to the contractor by the state or a municipality, pay any amounts due any subcontractor, whether for labor performed or materials furnished, when the labor or materials have been included in a requisition submitted by the contractor and paid by the state or a municipality; (2) a requirement that the general contractor shall include in each of its subcontracts a provision requiring each subcontractor to pay any amounts due any of its subcontractors, whether for labor performed or materials furnished, within thirty days after such subcontractor receives a payment from the general contractor which encompasses labor or materials furnished by such subcontractor.

(b) Each payment requisition submitted in accordance with the requirements of subsection (a) of this section, except for any such payment requisition submitted pursuant to a contract administered by or in conjunction with the Department of Transportation, shall include a statement showing the status of all pending construction change orders, other pending change directives and approved changes to the original contract or subcontract. Such statement shall identify the pending construction change orders and other pending change directives, and shall include the date such change orders and directives were initiated, the costs associated with their performance and a description of any work completed. As used in this section, “pending construction change order” or “other pending change directive” means an authorized directive for extra work that has been issued to a contractor or a subcontractor.
(c) If payment is not made by the general contractor or any of its subcontractors in accordance with such requirements, the subcontractor shall set forth his claim against the general contractor and the subcontractor of a subcontractor shall set forth its claim against the subcontractor through notice by registered or certified mail. Ten days after the receipt of that notice, the general contractor shall be liable to its subcontractor, and the subcontractor shall be liable to its subcontractor, for interest on the amount due and owing at the rate of one per cent per month. In addition, the general contractor, upon written demand of its subcontractor, or the subcontractor, upon written demand of its subcontractor, shall be required to place funds in the amount of the claim, plus interest of one per cent, in an interest-bearing escrow account in a bank in this state, provided the general contractor or subcontractor may refuse to place the funds in escrow on the grounds that the subcontractor has not substantially performed the work according to the terms of his or its employment. In the event that such general contractor or subcontractor refuses to place such funds in escrow, and the party making a claim against it under this section is found to have substantially performed its work in accordance with the terms of its employment in any arbitration or litigation to determine the validity of such claim, then such general contractor or subcontractor shall pay the attorney's fees of such party.
(d) No payment may be withheld from a subcontractor for work performed because of a dispute between the general contractor and another contractor or subcontractor.
(e) This section shall not be construed to prohibit progress payments prior to final payment of the contract and is applicable to all subcontractors for material or labor whether they have contracted directly with the general contractor or with some other subcontractor on the work.
(1969, P.A. 427, S. 1, 2; P.A. 75-626; P.A. 76-164; P.A. 79-602, S. 99; P.A. 80-115; P.A. 86-12, S. 1; P.A. 05-229, S. 5; P.A. 06-59, S. 1; P.A. 09-146, S. 2.)
History: P.A. 75-626 added provisions re deposit of claim amount in escrow account and prohibiting withholding of payment from subcontractor for work performed because of dispute between general or prime contractor and another contractor or subcontractor; P.A. 76-164 substituted reference to requirements included in contract for reference to requirements issued by public works commissioner and added references to payments by municipalities; P.A. 79-602 divided section into Subsecs. and made minor changes in wording, substituting “the” or “that” for “such”, etc.; P.A. 80-115 restated provisions, eliminating references to “prime” contractors and added Subsec. (a)(2) re requirements of subcontracts; P.A. 86-12 changed time limits for payment by general contractor to subcontractor and subcontractor to subcontractor from 45 and 20 days respectively, to 30 days in each case; P.A. 05-229 amended Subsec. (b) to require the general contractor to place funds claimed in an escrow account if a surety bond is not in place; P.A. 06-59 amended Subsec. (b) to delete “if a surety bond is not in place,” re placing funds in escrow; P.A. 09-146 added new Subsec. (b) re payment requisition statement requirements and redesignated existing Subsecs. (b) to (d) as Subsecs. (c) to (e), effective July 1, 2009.
See chapter 60, part II re public building contracts.
Remedies afforded by this section and Sec. 49-42 are independent of each other. 207 C. 468. Cited. 238 C. 293; 239 C. 708.
Cited. 5 CA 61; 13 CA 253; 15 CA 504; 32 CA 118; 40 CA 89.

Structure Connecticut General Statutes

Connecticut General Statutes

Title 49 - Mortgages and Liens

Chapter 847 - Liens

Section 49-32. - Liens in favor of the United States.

Section 49-32a. - Federal liens.

Section 49-33. - Mechanic's lien. Precedence. Rights of subcontractors.

Section 49-34. - Certificate of lien to be recorded and notice given to owner.

Section 49-35. - Notice of intent. Liens of subcontractors and materialmen.

Section 49-35a. - Application for reduction or discharge. Forms. Hearing. Entry fee.

Section 49-35b. - Burden of proof at hearing. Authority of court.

Section 49-35c. - Appeal.

Section 49-35d. - Validation of lien recorded prior to April 22, 1975.

Section 49-36. - Liens limited; apportionment; payments to original contractor.

Section 49-37. - Dissolution of mechanic's lien by substitution of bond. Joinder of actions on claim and bond.

Section 49-37a. - Lien validated when bond substituted prior to April 22, 1975.

Section 49-38. - Lien on railroad for services or materials in construction.

Section 49-39. - Time limitation of mechanic's lien. Action to foreclose privileged.

Section 49-40. - Record of discharge of mechanic's and judgment liens.

Section 49-40a. - Mechanic's liens expired by limitation of time.

Section 49-41. - Public buildings and public works. Bonds for protection of employees and materialmen. Performance bonds. Limits on use of owner-controlled insurance programs. Certain surety contract provisions.

Section 49-41a. - Enforcement of payment by general contractor to subcontractor and by subcontractor to its subcontractors.

Section 49-41b. - Release of payments on construction projects.

Section 49-41c. - State contractor to make payment to subcontractor within thirty days.

Section 49-42. - Enforcement of right to payment on bond. Suit on bond, procedure and judgment.

Section 49-43. - Certified copies of bonds and contracts for public works.

Section 49-44 to 49-46. - Recording of judgment lien; when it holds from attachment. Lien only on land liable to execution at date of judgment. Owner of judgment may file lien; foreclosure, limitation of time, notice of lis pendens.

Section 49-47a. - Form of mechanic's lien foreclosure certificates.

Section 49-49. - When insolvency proceedings set aside lien.

Section 49-51. - Discharge of invalid lien.

Section 49-52. - Pendency of action to foreclose lien on personalty not to be notice.

Section 49-53. - Duty of officer serving process in such action. Record by town clerk.

Section 49-55. - Vessel lien in connection with building, repairing, mooring, dockage or storage.

Section 49-55a. - Notice of vessel lien. Substitution of bond. Sale of vessel and satisfaction of lien.

Section 49-55b. - Form of notice of vessel lien.

Section 49-55c. - Dissolution of lien. Action by person claiming lien.

Section 49-55d. - Obtaining of lien without possession of vessel. Writ of attachment. Judicial sale.

Section 49-56. - Notice of vessel lien to be filed with Secretary of the State. Duration of lien. Discharge.

Section 49-56a. - Termination or removal of notice of lien.

Section 49-57. - Form of certificate of lien on vessel.

Section 49-58. - Lien not to exceed contract price.

Section 49-59. - Discharge of liens. Penalty for failure to discharge.

Section 49-60. - Jewelers' liens. Television and radio service dealers' liens.

Section 49-61. - Release of lien on substitution of bond. Lien on motor vehicle or special mobile equipment; notice of intent to sell to commissioner or bailor. Sale.

Section 49-62. - Form of application.

Section 49-63. - Notice of application. Hearing.

Section 49-64. - Form of bond.

Section 49-65. - Dissolution of lien to be recorded.

Section 49-66. - Pleadings may be amended.

Section 49-67. - Limitation of action on bond.

Section 49-68. - Liens of boardinghouse keepers.

Section 49-69. - Liens of hotel keepers.

Section 49-70. - Lien on animals for their keep. Transfer of abandoned animals.

Section 49-71. - Lien of manufacturers on materials.

Section 49-72. - Liens for rates or charges owed to private water company.

Section 49-73. - Liens on accident and liability policies in favor of hospitals and ambulance services. Service of process on insurer and defendant.

Section 49-73a. - Liens on proceeds of fire insurance for outstanding municipal taxes.

Section 49-73b. - Municipalities authorized to recover expenses. Liens on real estate and fire insurance proceeds.

Section 49-73c. - Certificate of lien to constitute constructive notice.

Section 49-73d. - Insurance company to notify town clerk of demand in writing of a statement of liens.

Section 49-73e. - Precedence and priority of liens.

Section 49-73f. - Municipal ordinance providing for release or return of insurance proceeds.

Section 49-73g. - Insurance company not to be held liable for payments to municipality.

Section 49-73h. - Applicability of lien provisions.

Section 49-73i. - Provisions re liens on insurance proceeds not to be deemed to affect other liens on real estate.

Section 49-74. - Liens for cleaning, storage and other charges.

Section 49-75. - Sale of property subject to lien for other than storage charges.

Section 49-76. - Sale of property subject to lien for storage charges.

Section 49-77 to 49-85. - Liens of factors on merchandise, generally.

Section 49-86. - Bond in lieu of attachment. Notice of lien.

Section 49-87. - Certificate of dissolution of bond, filing.

Section 49-88. - Duration of lien on real estate. Discharge upon expiration.

Section 49-89. - When judgment lien to date back to notice.

Section 49-90. - Certificate of court clerk upon happening of certain events or lien becoming ineffective.

Section 49-91. - Certificate of plaintiff removing lien upon happening of certain events or lien becoming ineffective.

Section 49-92. - Other lien rights not affected. Compliance with other statutes.

Section 49-92a. - Purchaser's lien. Precedence. Foreclosure. Recording of notice.

Section 49-92b. - Dissolution on substitution of bond. Joinder of actions on claim and bond.

Section 49-92c. - Limitation of lien.

Section 49-92d. - Record of discharge.

Section 49-92e. - Action to claim discharge.

Section 49-92f. - Certificate of removal of lien.

Section 49-92g. - Aircraft liens.

Section 49-92h. - Notice of aircraft lien. Substitution of bond. Sale of aircraft and satisfaction of lien.

Section 49-92i. - Form of notice of aircraft lien.

Section 49-92j. - Dissolution of aircraft lien. Action by person claiming lien.

Section 49-92k. - Discharge of aircraft lien. Penalty for failure to discharge.

Section 49-92o. - Assignment of liens by regional sewer authorities for unpaid sewer assessments or connection or use charges. Powers and rights of assignee. Contract to memorialize assignment required. Notice of assignment. Notice prior to commencin...

Section 49-92p. - Assignment of liens by regional water authorities for unpaid water assessments or connection and use charges. Powers and rights of assignee. Contract to memorialize assignment required. Notice of assignment. Notice prior to commenci...

Section 49-92s. - Provision of payoff statement by judgment lienholder. Imposition of fee or charge for first payoff statement, when allowed.