(1) Except as provided in ORS 543A.065 (2), be for a period of not more than 50 years;
(2) If for a federally licensed project, be for the period established in the new Federal Energy Regulatory Commission license;
(3) For the quantity of water authorized for use under the expiring water right for the project, retain the same priority date as the expiring water right for the project. For enlargement of the water right beyond the amount of water authorized in the expiring water right, the priority date for the additional amount shall be the date of filing a reauthorization application under ORS 543A.035, or a notice of intent under ORS 543A.075, whichever is applicable;
(4) If for a federally licensed project, include a provision allowing the Water Resources Department to amend conditions or limitations on the water right after the Federal Energy Regulatory Commission issues the federal license for the project; and
(5) Include conditions allowing the department to reopen the certificate on a clear showing of a significant threat to the public health or safety or the environment that was not identified and addressed during the most recent project authorization proceeding, and that requires modification of the certificate. [1997 c.449 ยง29]
Structure 2021 Oregon Revised Statutes
Volume : 15 - Water Resources, Agriculture and Food
Chapter 543A - Reauthorizing and Decommissioning Hydroelectric Projects
Section 543A.005 - Definitions.
Section 543A.025 - Minimum standards for decision on reauthorization of water right; rules.
Section 543A.030 - Notice of intent.
Section 543A.035 - Reauthorization application and public comment.
Section 543A.040 - Process determination.
Section 543A.045 - Public scoping meeting.
Section 543A.060 - Coordination of state and federal reauthorization processes.
Section 543A.065 - Changes to expiration date of water right for existing project.
Section 543A.080 - Submission of preliminary application information.
Section 543A.085 - Public scoping meeting.
Section 543A.090 - Mid-study status report; public meeting; period for comment on status report.
Section 543A.095 - Draft application.
Section 543A.110 - Water quality certification.
Section 543A.115 - Final unified state position.
Section 543A.120 - Proposed final order.
Section 543A.125 - Approval or rejection of application for reauthorization.
Section 543A.130 - Contested case hearing; final order.
Section 543A.135 - Exceptions to final order.
Section 543A.140 - Terms, limitations and conditions of water right.
Section 543A.145 - Water right certificate.
Section 543A.150 - Modification of time limits.
Section 543A.300 - Decommissioning; rules.
Section 543A.305 - Conversion of hydroelectric water right to in-stream water right; exceptions.
Section 543A.400 - Duties of Hydroelectric Application Review Team.
Section 543A.405 - Application fees.
Section 543A.410 - Fee schedule; appeal.
Section 543A.800 - Effect of hydroelectric reauthorization process on existing rights.