2021 Oregon Revised Statutes
Chapter 543A - Reauthorizing and Decommissioning Hydroelectric Projects
Section 543A.095 - Draft application.


(a) A draft application for a water right for the project, which shall be the Federal Energy Regulatory Commission draft application; and
(b) Information regarding potential water quality impacts of the project.
(2) The applicant shall provide the team with copies of any agency and public comment submitted to the applicant in the Federal Energy Regulatory Commission proceedings or in the state reauthorization proceedings.
(3) The applicant shall include with the application required under subsection (1) of this section the final report on the studies conducted pursuant to ORS 543A.085.
(4) Upon receipt of the draft application, the team shall identify in writing to the applicant any informational and analytical deficiencies. Subject to any identified deficiencies, the team shall prepare a provisional state position on:
(a) Whether, and under what conditions, the Water Resources Department should issue the water right;
(b) Whether the project would comply with ORS 468B.040 and water quality standards adopted by the Environmental Quality Commission, and what conditions might be appropriate under 33 U.S.C. 1341(d); and
(c) Recommendations to the Federal Energy Regulatory Commission under 16 U.S.C. 803(j).
(5) Upon completion of the provisional state position, the team shall give public notice of the availability of the provisional state position. The notice shall allow 30 days for the public to comment on the provisional state position.
(6) Based on comments received during the 30-day public comment period allowed under subsection (5) of this section, the team may revise the provisional state position. The team also shall resolve any conflict between agencies about the provisional state position.
(7) After considering agency and public comments, resolving interagency conflicts and making any necessary revisions, but no later than 160 days before the date by which the final application must be filed with the Federal Energy Regulatory Commission, the team shall provide the applicant with the provisional unified position of the state. However, the provisional unified position shall not constitute a final agency determination or action under any authority. [1997 c.449 §19; 2001 c.369 §3]

Structure 2021 Oregon Revised Statutes

2021 Oregon Revised Statutes

Volume : 15 - Water Resources, Agriculture and Food

Chapter 543A - Reauthorizing and Decommissioning Hydroelectric Projects

Section 543A.005 - Definitions.

Section 543A.020 - Policy.

Section 543A.025 - Minimum standards for decision on reauthorization of water right; rules.

Section 543A.030 - Notice of intent.

Section 543A.035 - Reauthorization application and public comment.

Section 543A.040 - Process determination.

Section 543A.045 - Public scoping meeting.

Section 543A.055 - Hydroelectric Application Review Team review of application; draft proposed final order; public comment.

Section 543A.060 - Coordination of state and federal reauthorization processes.

Section 543A.065 - Changes to expiration date of water right for existing project.

Section 543A.071 - Water Resources Department notification to holder of hydroelectric license or water right for hydroelectric purposes; response of holder.

Section 543A.075 - Notice of intent to apply for reauthorization of right to use water for hydroelectric purposes.

Section 543A.080 - Submission of preliminary application information.

Section 543A.085 - Public scoping meeting.

Section 543A.090 - Mid-study status report; public meeting; period for comment on status report.

Section 543A.095 - Draft application.

Section 543A.105 - Hydroelectric Application Review Team review of final application; unified state position in federal proceeding.

Section 543A.110 - Water quality certification.

Section 543A.115 - Final unified state position.

Section 543A.120 - Proposed final order.

Section 543A.125 - Approval or rejection of application for reauthorization.

Section 543A.130 - Contested case hearing; final order.

Section 543A.135 - Exceptions to final order.

Section 543A.140 - Terms, limitations and conditions of water right.

Section 543A.145 - Water right certificate.

Section 543A.150 - Modification of time limits.

Section 543A.300 - Decommissioning; rules.

Section 543A.305 - Conversion of hydroelectric water right to in-stream water right; exceptions.

Section 543A.400 - Duties of Hydroelectric Application Review Team.

Section 543A.405 - Application fees.

Section 543A.410 - Fee schedule; appeal.

Section 543A.800 - Effect of hydroelectric reauthorization process on existing rights.

Section 543A.810 - Effect of amendment or repeal of law.