2021 Oregon Revised Statutes
Chapter 543A - Reauthorizing and Decommissioning Hydroelectric Projects
Section 543A.120 - Proposed final order.


(2) The proposed final order shall cite findings of fact and conclusions of law and shall include but need not be limited to:
(a) Confirmation or modification of the preliminary determinations made in the initial review;
(b) A brief statement that explains the criteria considered relevant to the decision, including the applicable basin program, the compatibility of the proposed use with applicable land use plans and information set forth in the application report or final report on studies;
(c) An assessment of water availability and the amount of water necessary for the proposed use;
(d) An assessment of whether the proposed use would result in injury to existing water rights;
(e) An assessment of whether the proposed use would impair or be detrimental to the public interest as provided in ORS 543A.025;
(f) A draft certificate, including any proposed conditions, or a recommendation to deny the application; and
(g) The date by which protests to the proposed final order must be received by the department.
(3) The department shall mail copies of the proposed final order, as submitted by the team, to the applicant and to persons who have requested copies and paid the fee required under ORS 536.050 (1)(p). The department also shall give public notice of the proposed final order in the weekly notice published by the department.
(4) Any person may request standing for purposes of participating in any contested case proceeding on the proposed final order or for judicial review of a final order. A request for standing shall be in writing and shall be accompanied by the fee established under ORS 536.050 (1)(n).
(5) Any person may submit a protest against a proposed final order. A protest shall be in writing and shall include:
(a) The name, address and telephone number of the protestant;
(b) A description of the protestant’s interest in the proposed final order and, if the protestant claims to represent the public interest, a precise statement of the public interest represented;
(c) A detailed description of how the action proposed in the proposed final order would impair or be detrimental to the protestant’s interest;
(d) A detailed description of how the proposed final order is in error or deficient and how to correct the alleged error or deficiency;
(e) Any citation of legal authority supporting the protest, if known; and
(f) The protest fee required under ORS 536.050 (1)(j).
(6) Requests for standing and protests on the proposed final order shall be submitted within 45 days after publication of the notice of the proposed final order in the weekly notice published by the department. Any person who asks to receive a copy of the department’s final order shall submit to the department the fee required under ORS 536.050 (1)(p), unless the person has previously requested copies and paid the required fee.
(7) The Hydroelectric Application Review Team shall review any protest received and provide to the Water Resources Director a recommended response to any protest received.
(8) Within 120 days after the close of the period for receiving protests and after consultation with the Hydroelectric Application Review Team, the director shall:
(a) Issue a final order as provided under ORS 543A.130; or
(b) Schedule a contested case hearing if a protest has been submitted and if:
(A) Upon review of the issues, the director finds that there are significant disputes related to the proposed reauthorization of the project; or
(B) Within 30 days after the close of the period for submitting protests, the applicant requests a contested case hearing.
(9) At the request of the applicant, the department may extend the time periods set forth in subsection (8) of this section for a reasonable period of time.
(10) If the application is for reauthorization of a water right for a federally licensed project, the department may postpone the issuance of the final order until the Federal Energy Regulatory Commission license is issued. [1997 c.449 §23; 2013 c.644 §13]

Structure 2021 Oregon Revised Statutes

2021 Oregon Revised Statutes

Volume : 15 - Water Resources, Agriculture and Food

Chapter 543A - Reauthorizing and Decommissioning Hydroelectric Projects

Section 543A.005 - Definitions.

Section 543A.020 - Policy.

Section 543A.025 - Minimum standards for decision on reauthorization of water right; rules.

Section 543A.030 - Notice of intent.

Section 543A.035 - Reauthorization application and public comment.

Section 543A.040 - Process determination.

Section 543A.045 - Public scoping meeting.

Section 543A.055 - Hydroelectric Application Review Team review of application; draft proposed final order; public comment.

Section 543A.060 - Coordination of state and federal reauthorization processes.

Section 543A.065 - Changes to expiration date of water right for existing project.

Section 543A.071 - Water Resources Department notification to holder of hydroelectric license or water right for hydroelectric purposes; response of holder.

Section 543A.075 - Notice of intent to apply for reauthorization of right to use water for hydroelectric purposes.

Section 543A.080 - Submission of preliminary application information.

Section 543A.085 - Public scoping meeting.

Section 543A.090 - Mid-study status report; public meeting; period for comment on status report.

Section 543A.095 - Draft application.

Section 543A.105 - Hydroelectric Application Review Team review of final application; unified state position in federal proceeding.

Section 543A.110 - Water quality certification.

Section 543A.115 - Final unified state position.

Section 543A.120 - Proposed final order.

Section 543A.125 - Approval or rejection of application for reauthorization.

Section 543A.130 - Contested case hearing; final order.

Section 543A.135 - Exceptions to final order.

Section 543A.140 - Terms, limitations and conditions of water right.

Section 543A.145 - Water right certificate.

Section 543A.150 - Modification of time limits.

Section 543A.300 - Decommissioning; rules.

Section 543A.305 - Conversion of hydroelectric water right to in-stream water right; exceptions.

Section 543A.400 - Duties of Hydroelectric Application Review Team.

Section 543A.405 - Application fees.

Section 543A.410 - Fee schedule; appeal.

Section 543A.800 - Effect of hydroelectric reauthorization process on existing rights.

Section 543A.810 - Effect of amendment or repeal of law.