(a) Whenever feasible, elimination of duplicative application, study and reporting requirements;
(b) Hydroelectric Application Review Team use of information generated and documents prepared for the federal agency review;
(c) Development with the federal agency and reliance on a joint record to address applicable state standards;
(d) Whenever feasible, joint hearings and issuance of a state water right decision in a time frame consistent with the federal agency review; and
(e) To the extent consistent with applicable state standards, establishment of conditions in any state hydroelectric water right that are consistent with the conditions established, or required to be incorporated into licensing, by the federal agency.
(2) In order to better coordinate with the review of the project by the Federal Energy Regulatory Commission, the team may, at the request of an applicant, make changes to the process set forth in ORS 543A.060 to 543A.115, if the changes do not diminish opportunities for public input otherwise provided by ORS 543A.060 to 543A.115. [1997 c.449 ยง12]
Structure 2021 Oregon Revised Statutes
Volume : 15 - Water Resources, Agriculture and Food
Chapter 543A - Reauthorizing and Decommissioning Hydroelectric Projects
Section 543A.005 - Definitions.
Section 543A.025 - Minimum standards for decision on reauthorization of water right; rules.
Section 543A.030 - Notice of intent.
Section 543A.035 - Reauthorization application and public comment.
Section 543A.040 - Process determination.
Section 543A.045 - Public scoping meeting.
Section 543A.060 - Coordination of state and federal reauthorization processes.
Section 543A.065 - Changes to expiration date of water right for existing project.
Section 543A.080 - Submission of preliminary application information.
Section 543A.085 - Public scoping meeting.
Section 543A.090 - Mid-study status report; public meeting; period for comment on status report.
Section 543A.095 - Draft application.
Section 543A.110 - Water quality certification.
Section 543A.115 - Final unified state position.
Section 543A.120 - Proposed final order.
Section 543A.125 - Approval or rejection of application for reauthorization.
Section 543A.130 - Contested case hearing; final order.
Section 543A.135 - Exceptions to final order.
Section 543A.140 - Terms, limitations and conditions of water right.
Section 543A.145 - Water right certificate.
Section 543A.150 - Modification of time limits.
Section 543A.300 - Decommissioning; rules.
Section 543A.305 - Conversion of hydroelectric water right to in-stream water right; exceptions.
Section 543A.400 - Duties of Hydroelectric Application Review Team.
Section 543A.405 - Application fees.
Section 543A.410 - Fee schedule; appeal.
Section 543A.800 - Effect of hydroelectric reauthorization process on existing rights.