West Virginia Code
Article 3. Surface Coal Mining and Reclamation Act
§22-3-12. Site-Specific Bonding; Legislative Rule; Contents of Legislative Rule; Legislative Intent

(a) Notwithstanding the provisions of section eleven of this article, the secretary may establish and implement a site-specific bonding system in accordance with the provisions of this section.
(b) A legislative rule proposed or promulgated pursuant to this section must provide, at a minimum, for the following:
(1) The penal amount of a bond shall be not less than $1,000 nor more than $5,000 per acre or fraction thereof.
(2) Every bond, subject to the limitations of subdivision (1) of this subsection, shall reflect the relative potential cost of reclamation associated with the activities proposed to be permitted, which would not otherwise be reflected by bonds calculated by merely applying a specific dollar amount per acre for the permit.
(3) Every bond, subject to the provisions of subdivision (1) of this subsection, shall also reflect an analysis under the legislative rule of various factors, as applicable, which affect the cost of reclamation, including, but not limited to: (A) The general category of mining, whether surface or underground; (B) mining techniques and methods proposed to be utilized; (C) support facilities, fixtures, improvements and equipment; (D) topography and geology; and (E) the potential for degrading or improving water quality.
(c) A legislative rule proposed or promulgated pursuant to the provisions of this section may, in addition to the requirements of subsection (b) of this section, provide for a consideration of other factors determined to be relevant by the secretary. For example, the rule may provide for the following:
(1) A consideration as to whether the bond relates to a new permit application, a renewal of an existing permit, an application for an incidental boundary revision or the reactivation of an inactive permit;
(2) A consideration of factors which may result in environmental enhancement, as in a case where remining may improve water quality or reduce or eliminate existing highwalls, or a permitted operation may create or improve wetlands; or
(3) An analysis of various factors related to the specific permit applicant, including, but not limited to: (A) The prior mining experience of the applicant with the activities sought to be permitted; and (B) the history of the applicant as it relates to prior compliance with statutory and regulatory requirements designed to protect, maintain or enhance the environment in this or any other state.
(d) It is the intent of the Legislature that a legislative rule proposed or promulgated pursuant to the provisions of this section shall be constructed so that when the findings of fact by the Division of Environmental Protection with respect to the proposed mining activity and the particular permit applicant coincide with the particular factors or criteria to be considered and analyzed under the rule, the rule will direct a conclusion as to the amount of the bond to be required, subject to rebuttal and refutation of the findings by the applicant. To the extent practicable, the rule shall limit subjectivity and discretion by the secretary and the division in fixing the amount of the bond.

Structure West Virginia Code

West Virginia Code

Chapter 22. Environmental Resources

Article 3. Surface Coal Mining and Reclamation Act

§22-3-1. Short Title

§22-3-2. Legislative Findings and Purpose; Jurisdiction Vested in Division of Environmental Protection; Authority of Secretary; Inter-Departmental Cooperation

§22-3-3. Definitions

§22-3-4. Reclamation; Duties and Functions of Secretary

§22-3-5. Surface Mining Reclamation Supervisors and Inspectors; Appointment and Qualifications; Salary

§22-3-6. Duties of Surface Mining Reclamation Inspectors and Inspectors in Training

§22-3-7. Notice of Intention to Prospect, Requirements Therefor; Bonding; Secretary's Authority to Deny or Limit; Postponement of Reclamation; Prohibited Acts; Exceptions

§22-3-8. Prohibition of Surface Mining Without a Permit; Permit Requirements; Successor in Interest; Duration of Permits; Proof of Insurance; Termination of Permits; Permit Fees

§22-3-9. Permit Application Requirements and Contents

§22-3-10. Reclamation Plan Requirements

§22-3-11. Bonds; Amount and Method of Bonding; Bonding Requirements; Special Reclamation Tax and Funds; Prohibited Acts; Period of Bond Liability

§22-3-11a. Special Reclamation Tax; Clarification of Imposition of Tax; Procedures for Collection and Administration of Tax; Application of Tax Procedure and Administration Act and Tax Crimes and Penalties Act

§22-3-12. Site-Specific Bonding; Legislative Rule; Contents of Legislative Rule; Legislative Intent

§22-3-13. General Environmental Protection Performance Standards for Surface Mining; Variances

§22-3-13a. Preblast Survey Requirements

§22-3-14. General Environmental Protection Performance Standards for the Surface Effects of Underground Mining; Application of Other Provisions of Article to Surface Effects of Underground Mining

§22-3-15. Inspections; Monitoring; Right of Entry; Inspection of Records; Identification Signs; Progress Maps

§22-3-16. Cessation of Operation by Order of Inspector; Informal Conference; Imposition of Affirmative Obligations; Appeal

§22-3-17. Notice of Violation; Procedure and Actions; Enforcement; Permit Revocation and Bond Forfeiture; Civil and Criminal Penalties; Appeals to the Board; Prosecution; Injunctive Relief

§22-3-18. Approval, Denial, Revision and Prohibition of Permit

§22-3-19. Permit Revision and Renewal Requirements; Incidental Boundary Revisions; Requirements for Transfer; Assignment and Sale of Permit Rights; Operator Reassignment; and Procedures to Obtain Inactive Status

§22-3-20. Public Notice; Written Objections; Public Hearings; Informal Conferences

§22-3-21. Decision of Secretary on Permit Application; Hearing Thereon

§22-3-22. Designation of Areas Unsuitable for Surface Mining; Petition for Removal of Designation; Prohibition of Surface Mining on Certain Areas; Exceptions; Taxation of Minerals Underlying Land Designated Unsuitable

§22-3-22a. Blasting Restrictions; Site Specific Blasting Design Requirement

§22-3-23. Release of Bond or Deposits; Application; Notice; Duties of Secretary; Public Hearings; Final Maps on Grade Release

§22-3-24. Water Rights and Replacement; Waiver of Replacement

§22-3-25. Citizen Suits; Order of Court; Damages

§22-3-26. Surface Mining Operations Not Subject to Article

§22-3-27. Leasing of Lands Owned by State for Surface Mining of Coal

§22-3-28. Special Permits Authorization for Reclamation of Existing Abandoned Coal Processing Waste Piles; Coal Extraction Pursuant to a Government-Financed Reclamation Contract; Coal Extraction as an Incidental Part of Development of Land for Commer...

§22-3-29. Experimental Practices

§22-3-30. Certification and Training of Blasters

§22-3-30a. Blasting Requirements; Liability and Civil Penalties in the Event of Property Damage

§22-3-31. Conflict of Interest Prohibited; Criminal Penalties Therefor; Employee Protection

§22-3-32. Special Tax on Coal Production; Mines and Minerals Operations Fund

§22-3-32a. Special Tax on Coal; Clarification of Imposition of Tax; Procedures for Collection and Administration of Tax

§22-3-33. Attorney Fees and Costs

§22-3-34. Office of Explosives and Blasting Terminated; Transfer of Functions; Responsibilities, Personnel and Assets

§22-3-35. Legislative Rules on Surface-Mining Blasting; Disciplinary Procedures for Certified Blasters

§22-3-36. Claims Process for Blasting

§22-3-37. Rules, Orders and Permits to Remain in Effect Regarding Blasting; Proceedings Not Affected

§22-3-38. Transfer of Personnel and Assets