Sec. 382.05183. EXISTING FACILITY PERMIT. (a) The owner or operator of a facility affected by Section 382.0518(g) may apply for a permit to operate the facility under this section.
(b) The commission shall grant a permit under this section if, from the information available to the commission, the commission finds that the facility will use a control method at least as beneficial as that described by Section 382.003(9)(E)(ii), considering the age and the remaining useful life of the facility.
(c) The commission may issue an existing facility flexible permit for some or all of the facilities at a site affected by Section 382.0518(g) and facilities permitted under Section 382.0519 in order to implement the requirements of this section. Permits issued under this subsection shall follow the same permit issuance, modification, and renewal procedures as existing facility permits.
(d) If the commission finds that the emissions from the facility will contravene the standards under Subsection (b) or the intent of this chapter, including protection of the public's health and physical property, the commission may not grant the permit under this section.
(e) A person planning the modification of a facility previously permitted under this section must comply with Section 382.0518 before modifying.
(f) The commission may adopt rules as necessary to implement and administer this section.
Added by Acts 2001, 77th Leg., ch. 965, Sec. 5.03, eff. Sept. 1, 2001.

Structure Texas Statutes

Texas Statutes

Health and Safety Code

Title 5 - Sanitation and Environmental Quality

Subtitle C - Air Quality

Chapter 382 - Clean Air Act

Subchapter C. Permits

Section 382.051. Permitting Authority of Commission; Rules

Section 382.05101. De Minimis Air Contaminants

Section 382.05102. Permitting Authority of Commission; Greenhouse Gas Emissions

Section 382.0511. Permit Consolidation and Amendment

Section 382.0512. Modification of Existing Facility

Section 382.0513. Permit Conditions

Section 382.0514. Sampling, Monitoring, and Certification

Section 382.0515. Application for Permit

Section 382.05155. Expedited Processing of Application

Section 382.0516. Notice to State Senator, State Representative, and Certain Local Officials

Section 382.0517. Determination of Administrative Completion of Application

Section 382.0518. Preconstruction Permit

Section 382.05181. Permit Required

Section 382.05182. Notice of Shutdown

Section 382.05183. Existing Facility Permit

Section 382.05184. Small Business Stationary Source Permit

Section 382.05185. Electric Generating Facility Permit

Section 382.05186. Pipeline Facilities Permits

Section 382.051865. Stationary Natural Gas Engines Used in Combined Heating and Power System

Section 382.051866. Emissions Reductions Incentives Account

Section 382.0519. Voluntary Emissions Reduction Permit

Section 382.05191. Emissions Reduction Permits: Notice and Hearing

Section 382.05192. Review and Renewal of Emissions Reduction and Multiple Plant Permits

Section 382.05193. Emissions Permits Through Emissions Reduction

Section 382.05194. Multiple Plant Permit

Section 382.05195. Standard Permit

Section 382.05196. Permits by Rule

Section 382.051961. Permit for Certain Oil and Gas Facilities

Section 382.051962. Authorization for Planned Maintenance, Start-Up, or Shutdown Activities Relating to Certain Oil and Gas Facilities

Section 382.051964. Aggregation of Facilities

Section 382.05197. Multiple Plant Permit: Notice and Hearing

Section 382.05198. Standard Permit for Certain Concrete Plants

Section 382.05199. Standard Permit for Certain Concrete Batch Plants: Notice and Hearing

Section 382.052. Permit to Construct or Modify Facility Within 3,000 Feet of School

Section 382.053. Prohibition on Issuance of Construction Permit for Lead Smelting Plant at Certain Locations

Section 382.054. Federal Operating Permit

Section 382.0541. Administration and Enforcement of Federal Operating Permit

Section 382.0542. Issuance of Federal Operating Permit; Appeal of Delay

Section 382.0543. Review and Renewal of Federal Operating Permit

Section 382.055. Review and Renewal of Preconstruction Permit

Section 382.056. Notice of Intent to Obtain Permit or Permit Review; Hearing

Section 382.0561. Federal Operating Permit: Hearing

Section 382.0562. Notice of Decision

Section 382.0563. Public Petition to the Administrator

Section 382.0564. Notification to Other Governmental Entities

Section 382.0565. Clean Coal Project Permitting Procedure

Section 382.0566. Advanced Clean Energy Project Permitting Procedure

Section 382.0567. Proof That Technology Is Commercially Feasible Not Required; Consideration of Technology to Be Achievable for Certain Purposes Prohibited

Section 382.057. Exemption

Section 382.058. Notice of and Hearing on Construction of Concrete Plant Under Permit by Rule, Standard Permit, or Exemption

Section 382.059. Hearing and Decision on Permit Amendment Application of Certain Electric Generating Facilities

Section 382.0591. Denial of Application for Permit; Assistance Provided by Former or Current Employees

Section 382.061. Delegation of Powers and Duties

Section 382.062. Application, Permit, and Inspection Fees

Section 382.0621. Operating Permit Fee

Section 382.0622. Clean Air Act Fees

Section 382.063. Issuance of Emergency Order Because of Catastrophe

Section 382.064. Initial Application Date

Section 382.065. Certain Locations for Operating Concrete Crushing Facility Prohibited

Section 382.066. Shipyard Facilities

Section 382.068. Poultry Facility Odor; Response to Complaints