Sec. 28.038. ENVIRONMENTAL REPORT. If an environmental report, environmental assessment, or environmental impact statement of any kind that includes an analysis of the environmental impacts of the shaft construction or operation is required by any federal or state agency before approval to construct the shaft, the environmental document, along with evidence of the needed approvals that have been granted, must be submitted to the commission as part of the shaft permit application, and the commission shall make the environmental document available for public review and comment for a period of not less than 30 days before the application for the shaft permit is considered.
Added by Acts 1983, 68th Leg., p. 651, ch. 148, Sec. 1, eff. May 18, 1983. Amended by Acts 1985, 69th Leg., ch. 795, Sec. 1.127, eff. Sept. 1, 1985.
Structure Texas Statutes
Title 2 - Water Administration
Subtitle D - Water Quality Control
Chapter 28 - Water Wells and Drilled or Mined Shafts
Subchapter C. Drilled or Mined Shafts
Section 28.021. Permit From Commission
Section 28.022. Application for Permit
Section 28.023. Information Required of Applicant
Section 28.024. Application Fee
Section 28.025. Letter From Railroad Commission
Section 28.026. Inspection of Shaft Location
Section 28.027. Recommendations From Other Agencies
Section 28.028. Hearing on Permit Application
Section 28.029. Delegation of Hearing Powers
Section 28.031. Issuance of Permit
Section 28.032. Copies of Permit; Filing Requirements
Section 28.033. Record of Strata
Section 28.034. Geophysical and Drilling Log
Section 28.035. Seismic Reflection Survey
Section 28.036. Casing, Liner, and Seal Requirements
Section 28.037. Factors in Setting Casing, Liner, and Seal Requirements