§ 45-23-43. General provisions — Major land development and major subdivision — Final plan.
(a) Submission requirements.
(1) The applicant shall submit to the administrative officer the items required by the local regulations for the final plan, as well as all material required by the planning board when the application was given preliminary approval.
(2) Arrangements for completion of the required public improvements, including construction schedule and/or financial guarantees.
(3) Certification by the tax collector that all property taxes are current.
(4) For phased projects, the final plan for phases following the first phase, shall be accompanied by copies of as-built drawings not previously submitted of all existing public improvements for prior phases.
(b) Certification. The application for final plan approval shall be certified complete or incomplete by the administrative officer in writing, within twenty-five (25) days, according to the provisions of § 45-23-36(b). This time period may be extended to forty-five (45) days by written notice from the administrative officer to the applicant where the final plans contain changes to or elements not included in the preliminary plan approval. The running of the time period set forth herein shall be deemed stopped upon the issuance of a certificate of incompleteness of the application by the administrative officer and shall recommence upon the resubmission of a corrected application by the applicant. However, in no event shall the administrative officer be required to certify a corrected submission as complete or incomplete less than fourteen (14) days after its resubmission. If the administrative officer certifies the application as complete and does not require submission to the planning board as per subsection (c) below, the final plan shall be considered approved.
(c) Referral to the planning board. If the administrative officer determines that an application for final approval does not meet the requirements set by local regulations or by the planning board at preliminary approval, the administrative officer shall refer the final plans to the planning board for review. The planning board shall, within forty-five (45) days after the certification of completeness, or within a further amount of time that may be consented to by the applicant, approve or deny the final plan as submitted.
(d) Failure to act. Failure of the planning board to act within the prescribed period constitutes approval of the final plan and a certificate of the administrative officer as to the failure of the planning board to act within the required time and the resulting approval shall be issued on request of the applicant.
(e) Expiration of approval. The final approval of a major subdivision or land development project expires one year from the date of approval with the right to extend for one year upon written request by the applicant, who must appear before the planning board for the annual review, unless, within that period, the plat or plan has been submitted for signature and recording as specified in § 45-23-64. Thereafter, the planning board may, for good cause shown, extend the period for recording for an additional period.
(f) Acceptance of public improvements. Signature and recording as specified in § 45-23-64 constitute the acceptance by the municipality of any street or other public improvement or other land intended for dedication. Final plan approval shall not impose any duty upon the municipality to maintain or improve those dedicated areas until the governing body of the municipality accepts the completed public improvements as constructed in compliance with the final plans.
(g) Validity of recorded plans. The approved final plan, once recorded, remains valid as the approved plan for the site unless and until an amendment to the plan is approved under the procedure stated in § 45-23-65, or a new plan is approved by the planning board.
History of Section.P.L. 1992, ch. 385, § 1; P.L. 1996, ch. 404, § 36; P.L. 1999, ch. 157, § 1; P.L. 2008, ch. 224, § 1; P.L. 2008, ch. 294, § 1; P.L. 2008, ch. 464, § 1.
Structure Rhode Island General Laws
Chapter 45-23 - Subdivision of Land
Section 45-23-1 - — 45-23-24. Repealed.
Section 45-23-26. - Requirement in all municipalities.
Section 45-23-27. - Applicability.
Section 45-23-28. - Continuation of ordinances — Supersession — Relation to other statutes.
Section 45-23-29. - Legislative findings and intent.
Section 45-23-32. - Definitions.
Section 45-23-33. - General provisions — Required contents of local regulations.
Section 45-23-34. - General provisions — Definitions.
Section 45-23-35. - General provisions — Pre-application meetings and concept review.
Section 45-23-37. - General provisions — Administrative subdivision.
Section 45-23-38. - General provisions — Minor land development and minor subdivision review.
Section 45-23-39. - General provisions — Major land development and major subdivision review stages.
Section 45-23-40. - General provisions — Major land development and major subdivision — Master plan.
Section 45-23-43. - General provisions — Major land development and major subdivision — Final plan.
Section 45-23-44. - General provisions — Physical design requirements.
Section 45-23-45. - General provisions — Public design and improvement standards.
Section 45-23-46. - General provisions — Construction and/or improvement guarantees.
Section 45-23-48. - Special provisions — Phasing of projects.
Section 45-23-49. - Special provisions — Land development projects.
Section 45-23-49.1. - Farmland residential compounds.
Section 45-23-50. - Special provisions — Development plan review.
Section 45-23-50.1. - Special provisions — Unified development review.
Section 45-23-51. - Local regulations — Authority to create and administer regulations.
Section 45-23-52. - Local regulations — Procedure for adoption and amendment.
Section 45-23-53. - Local regulations — Public hearing and notice requirements.
Section 45-23-54. - Local regulations — Publication and availability.
Section 45-23-55. - Administration — The administrative officer.
Section 45-23-56. - Administration — Technical review committee.
Section 45-23-57. - Administration — The board of appeal.
Section 45-23-58. - Administration — Administrative fees.
Section 45-23-59. - Administration — Violations and penalties.
Section 45-23-60. - Procedure — Required findings.
Section 45-23-62. - Procedure — Waivers — Modifications and reinstatement of plans.
Section 45-23-63.1. - Procedure — Tolling of expiration periods.
Section 45-23-64. - Procedure — Signing and recording of plats and plans.
Section 45-23-65. - Procedure — Changes to recorded plats and plans.
Section 45-23-66. - Appeals — Right of appeal.
Section 45-23-67. - Appeals — Process of appeal.
Section 45-23-68. - Appeals — Stay of proceedings.
Section 45-23-69. - Appeals — Public hearing.
Section 45-23-70. - Appeals — Standards of review.
Section 45-23-71. - Appeals to the superior court.
Section 45-23-72. - Appeals to the superior court — Enactment of or amendment of local regulations.
Section 45-23-73. - Appeals to the superior court — Priority in judicial proceedings.