Revised Code of Washington
Chapter 39.10 - Alternative Public Works Contracting Procedures.
39.10.460 - Job order procedure—Required information.

RCW 39.10.460
Job order procedure—Required information.

Each public body shall maintain and make available the following information for each job order contract:
(1) A list of work orders issued;
(2) The cost of each work order;
(3) A list of subcontractors hired under each work order, including whether those subcontractors were certified small, minority, women, or veteran-owned businesses; and
(4) A copy of the intent to pay prevailing wage and the affidavit of wages paid for each work order subcontract.

[ 2021 c 230 § 17; 2012 c 102 § 3; 2007 c 494 § 405.]
NOTES:

Sunset Act application: See note following chapter digest.


Effective date—2021 c 230: See note following RCW 39.10.210.

Structure Revised Code of Washington

Revised Code of Washington

Title 39 - Public Contracts and Indebtedness

Chapter 39.10 - Alternative Public Works Contracting Procedures.

39.10.200 - Finding—Purpose—Intent.

39.10.210 - Definitions.

39.10.220 - Board—Membership—Vacancies.

39.10.230 - Board—Powers and duties.

39.10.240 - Project review committee—Creation—Members.

39.10.250 - Project review committee—Duties.

39.10.260 - Project review committee—Meetings—Open and public.

39.10.270 - Project review committee—Certification of public bodies.

39.10.280 - Project review committee—Project approval process.

39.10.290 - Appeal process.

39.10.300 - Design-build procedure—Uses—Washington State University may perform design-build demonstration projects.

39.10.320 - Design-build procedure—Project management and contracting requirements.

39.10.330 - Design-build contract award process.

39.10.340 - General contractor/construction manager procedure—Uses.

39.10.350 - General contractor/construction manager procedure—Project management and contracting requirements.

39.10.360 - General contractor/construction manager procedure—Contract award process.

39.10.370 - General contractor/construction manager procedure—Maximum allowable construction cost.

39.10.380 - General contractor/construction manager procedure—Subcontract bidding procedure.

39.10.385 - General contractor/construction manager procedure—Alternative subcontractor selection process.

39.10.390 - General contractor/construction manager procedure—Subcontract work.

39.10.400 - General contractor/construction manager procedure—Prebid determination of subcontractor eligibility.

39.10.410 - General contractor/construction manager procedure—Subcontract agreements.

39.10.420 - Job order procedure—Public bodies may authorize and use.

39.10.430 - Job order procedure—Contract award process.

39.10.440 - Job order procedure—Contract requirements.

39.10.450 - Job order procedure—Work orders.

39.10.460 - Job order procedure—Required information.

39.10.470 - Public inspection of certain records—Protection of trade secrets—Protection of documents submitted.

39.10.480 - Construction of chapter—Waiver of other limits and requirements.

39.10.490 - Application of chapter.

39.10.900 - Captions not law—1994 c 132.

39.10.901 - Severability—1994 c 132.

39.10.903 - Part headings and captions not law—2007 c 494.

39.10.904 - Effective dates—2007 c 494.

39.10.905 - Severability—2007 c 494.

39.10.908 - General contractor/construction manager method for heavy civil construction projects—Requirements.