Revised Code of Washington
Chapter 39.10 - Alternative Public Works Contracting Procedures.
39.10.240 - Project review committee—Creation—Members.

RCW 39.10.240
Project review committee—Creation—Members.

(1) The board shall establish a project review committee to review and approve public works projects using the design-build and general contractor/construction manager contracting procedures authorized in RCW 39.10.300 and 39.10.340 and to certify public bodies as provided in RCW 39.10.270.
(2) The board shall, by a majority vote of the board, appoint persons to the committee who are knowledgeable in the use of the design-build and general contractor/construction manager contracting procedures. Appointments must represent a balance of public and private sector representatives of the board listed in RCW 39.10.220, and must include at least one member representing the interests of disadvantaged business enterprises.
(a) Each member of the committee shall be appointed for a term of three years. However, for initial appointments, the board shall stagger the appointment of committee members so that the first members are appointed to serve terms of one, two, or three years from the date of appointment. Appointees may be reappointed to serve more than one term.
(b) The committee shall, by a majority vote, elect a chair and vice chair for the committee.
(c) The committee chair may select a person or persons on a temporary basis as a nonvoting member if project specific expertise is needed to assist in a review.
(3) The chair of the committee, in consultation with the vice chair, may appoint one or more panels of at least six committee members to carry out the duties of the committee. Each panel shall have balanced representation of the private and public sector representatives serving on the committee, and shall include a member representing the interests of disadvantaged business enterprises.
(4) Any member of the committee directly or indirectly affiliated with a submittal before the committee must recuse himself or herself from the committee consideration of that submittal.
(5) Any person who sits on the committee or panel is not precluded from subsequently bidding on or participating in projects that have been reviewed by the committee.
(6) The committee shall meet as often as necessary to ensure that certification and approvals are completed in a timely manner.

[ 2021 c 230 § 4; 2013 c 222 § 4; 2007 c 494 § 104.]
NOTES:

Sunset Act application: See note following chapter digest.


Effective date—2021 c 230: See note following RCW 39.10.210.


Effective date—2013 c 222: See note following RCW 39.10.210.

Structure Revised Code of Washington

Revised Code of Washington

Title 39 - Public Contracts and Indebtedness

Chapter 39.10 - Alternative Public Works Contracting Procedures.

39.10.200 - Finding—Purpose—Intent.

39.10.210 - Definitions.

39.10.220 - Board—Membership—Vacancies.

39.10.230 - Board—Powers and duties.

39.10.240 - Project review committee—Creation—Members.

39.10.250 - Project review committee—Duties.

39.10.260 - Project review committee—Meetings—Open and public.

39.10.270 - Project review committee—Certification of public bodies.

39.10.280 - Project review committee—Project approval process.

39.10.290 - Appeal process.

39.10.300 - Design-build procedure—Uses—Washington State University may perform design-build demonstration projects.

39.10.320 - Design-build procedure—Project management and contracting requirements.

39.10.330 - Design-build contract award process.

39.10.340 - General contractor/construction manager procedure—Uses.

39.10.350 - General contractor/construction manager procedure—Project management and contracting requirements.

39.10.360 - General contractor/construction manager procedure—Contract award process.

39.10.370 - General contractor/construction manager procedure—Maximum allowable construction cost.

39.10.380 - General contractor/construction manager procedure—Subcontract bidding procedure.

39.10.385 - General contractor/construction manager procedure—Alternative subcontractor selection process.

39.10.390 - General contractor/construction manager procedure—Subcontract work.

39.10.400 - General contractor/construction manager procedure—Prebid determination of subcontractor eligibility.

39.10.410 - General contractor/construction manager procedure—Subcontract agreements.

39.10.420 - Job order procedure—Public bodies may authorize and use.

39.10.430 - Job order procedure—Contract award process.

39.10.440 - Job order procedure—Contract requirements.

39.10.450 - Job order procedure—Work orders.

39.10.460 - Job order procedure—Required information.

39.10.470 - Public inspection of certain records—Protection of trade secrets—Protection of documents submitted.

39.10.480 - Construction of chapter—Waiver of other limits and requirements.

39.10.490 - Application of chapter.

39.10.900 - Captions not law—1994 c 132.

39.10.901 - Severability—1994 c 132.

39.10.903 - Part headings and captions not law—2007 c 494.

39.10.904 - Effective dates—2007 c 494.

39.10.905 - Severability—2007 c 494.

39.10.908 - General contractor/construction manager method for heavy civil construction projects—Requirements.