RCW 39.10.270
Project review committee—Certification of public bodies.
(1) A public body may apply for certification to use the design-build or general contractor/construction manager contracting procedure, or both. Once certified, a public body may use the contracting procedure for which it is certified on individual projects without seeking committee approval for a period of three years. A public body seeking certification must submit to the committee an application in a format and manner as prescribed by the committee. The application must include a description of the public body's qualifications, its capital plan during the certification period, and its intended use of alternative contracting procedures.
(2) A public body seeking certification for the design-build procedure must demonstrate successful management of at least one design-build project within the previous five years. A public body seeking certification for the general contractor/construction manager procedure must demonstrate successful management of at least one general contractor/construction manager project within the previous five years.
(3) To certify a public body, the committee shall determine that the public body:
(a) Has the necessary experience and qualifications to determine which projects are appropriate for using alternative contracting procedures;
(b) Has the necessary experience and qualifications to carry out the alternative contracting procedure including, but not limited to: (i) Project delivery knowledge and experience; (ii) personnel with appropriate construction experience; (iii) a management plan and rationale for its alternative public works projects; (iv) demonstrated success in managing public works projects; (v) the ability to properly manage its capital facilities plan including, but not limited to, appropriate project planning and budgeting experience; and (vi) the ability to meet requirements of this chapter; and
(c) Has resolved any audit findings on previous public works projects in a manner satisfactory to the committee.
(4) The committee shall make its determination at the public meeting during which an application for certification is reviewed. Public comments must be considered before a determination is made. Within ten business days of the public meeting, the committee shall provide a written determination to the public body, and make its determination available to the public on the committee's website.
(5) The committee may revoke any public body's certification upon a finding, after a public hearing, that its use of design-build or general contractor/construction manager contracting procedures no longer serves the public interest.
(6) The committee may renew the certification of a public body for additional three-year periods. The public body must submit an application for recertification at least three months before the initial certification expires. The committee may accept late applications, if administratively feasible, to avoid expiration of certification on a case-by-case basis. The application shall include updated information on the public body's experience and current staffing with the procedure it is applying to renew, and any other information requested in advance by the committee. The committee must review the application for recertification at a meeting held before expiration of the applicant's initial certification period. A public body must reapply for certification under the process described in subsection (1) of this section once the period of recertification expires.
(7) Certified public bodies must submit project data information as required in RCW 39.10.320 and 39.10.350.
[ 2019 c 212 § 3; 2017 c 211 § 1; 2013 c 222 § 7; 2009 c 75 § 3; 2007 c 494 § 107.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
Structure Revised Code of Washington
Title 39 - Public Contracts and Indebtedness
Chapter 39.10 - Alternative Public Works Contracting Procedures.
39.10.200 - Finding—Purpose—Intent.
39.10.220 - Board—Membership—Vacancies.
39.10.230 - Board—Powers and duties.
39.10.240 - Project review committee—Creation—Members.
39.10.250 - Project review committee—Duties.
39.10.260 - Project review committee—Meetings—Open and public.
39.10.270 - Project review committee—Certification of public bodies.
39.10.280 - Project review committee—Project approval process.
39.10.320 - Design-build procedure—Project management and contracting requirements.
39.10.330 - Design-build contract award process.
39.10.340 - General contractor/construction manager procedure—Uses.
39.10.360 - General contractor/construction manager procedure—Contract award process.
39.10.370 - General contractor/construction manager procedure—Maximum allowable construction cost.
39.10.380 - General contractor/construction manager procedure—Subcontract bidding procedure.
39.10.390 - General contractor/construction manager procedure—Subcontract work.
39.10.410 - General contractor/construction manager procedure—Subcontract agreements.
39.10.420 - Job order procedure—Public bodies may authorize and use.
39.10.430 - Job order procedure—Contract award process.
39.10.440 - Job order procedure—Contract requirements.
39.10.450 - Job order procedure—Work orders.
39.10.460 - Job order procedure—Required information.
39.10.480 - Construction of chapter—Waiver of other limits and requirements.
39.10.490 - Application of chapter.
39.10.900 - Captions not law—1994 c 132.
39.10.901 - Severability—1994 c 132.
39.10.903 - Part headings and captions not law—2007 c 494.
39.10.904 - Effective dates—2007 c 494.