Effective: June 29, 2005
Latest Legislation: House Bill 68 - 126th General Assembly
(A) For each fiscal year, not more than one-fifth of the department of transportation's capital construction projects shall be bid requiring a warranty as specified in the bidding documents and in division (B) of this section.
(B) A warranty period under this section shall be:
(1) Not more than seven years, for pavement in the case of new construction;
(2) Not more than five years, in the case of bridge painting and pavement resurfacing and rehabilitation;
(3) Not more than two years, in the case of pavement preventative maintenance, pavement markings, raised pavement markers, guardrail, and other project items as determined by the director.
This section does not apply to contracts the director makes on behalf of a political subdivision.
Structure Ohio Revised Code
Title 55 | Roads-Highways-Bridges
Chapter 5525 | Construction Contracts
Section 5525.01 | Advertisement for Bids - Awarding of Contracts - Odot Letting Fund.
Section 5525.011 | Complying With Federal Surface Transportation Assistance Act.
Section 5525.02 | Qualification and Classification of Bidders.
Section 5525.03 | Application for Qualification.
Section 5525.04 | Financial Statement and Financial Audit.
Section 5525.05 | Rules - Lists of Qualified Bidders.
Section 5525.06 | Subcontractor Must Be Properly Qualified.
Section 5525.061 | Subcontract Approval.
Section 5525.07 | Notification of Final Action - Prequalification Review Board.
Section 5525.08 | Disposition of Bids of Unqualified Bidders - Nonresponsive Bids.
Section 5525.09 | False Statement With Respect to Financial Worth.
Section 5525.10 | Contracts Not to Be Awarded for More Than Cost Plus Five per Cent.
Section 5525.11 | Contract Upon a Unit Price Basis.
Section 5525.12 | Lumber Deemed Material.
Section 5525.13 | Limitation of Surety Bond and Insurance.
Section 5525.14 | Written Change Orders or Orders for Extra Work.
Section 5525.15 | Cost Estimates May Be Confidential.
Section 5525.16 | Contract Performance Bond and Payment Bond.
Section 5525.17 | Failure of Contractor or Surety to Complete Work.
Section 5525.18 | Contract With Foreign Corporation.
Section 5525.19 | Payment of Costs.
Section 5525.20 | Incentive and Disincentive Contract Provisions.
Section 5525.21 | Authorizing Minimal Amount of Foreign Steel Products in Bridge Projects.
Section 5525.22 | Demolition Contracts.
Section 5525.23 | Binding Dispute Resolution for Contract Controversies.
Section 5525.25 | Warranty Specifications in Bidding Documents.