Effective: March 13, 1997
Latest Legislation: Senate Bill 287 - 121st General Assembly
For the purpose of carrying into effect sections 5525.02 to 5525.09 of the Revised Code, and ensuring that the award of all contracts is made to competent and responsible bidders or the lowest and best bidders for environmental remediation and specialty work for which there are no classes of work set out in the rules adopted by the director, subject to and in accordance with Chapter 119. of the Revised Code, the director of transportation may adopt such rules as the director considers proper. The rules may cover the requirements of the department of transportation with respect to classes of work, joint ventures, subcontracting procedures, causes for revocation or nonrenewal of a certificate of qualification, establishment of a debarment process, equipment, past record and experience of applicant, personnel of organization, and any other matters the director considers necessary to enable the director to pass upon the qualifications of applicants. The director may make public lists of qualified bidders, but the lists shall not indicate the bidders' prequalification amounts.
Structure Ohio Revised Code
Title 55 | Roads-Highways-Bridges
Chapter 5525 | Construction Contracts
Section 5525.01 | Advertisement for Bids - Awarding of Contracts - Odot Letting Fund.
Section 5525.011 | Complying With Federal Surface Transportation Assistance Act.
Section 5525.02 | Qualification and Classification of Bidders.
Section 5525.03 | Application for Qualification.
Section 5525.04 | Financial Statement and Financial Audit.
Section 5525.05 | Rules - Lists of Qualified Bidders.
Section 5525.06 | Subcontractor Must Be Properly Qualified.
Section 5525.061 | Subcontract Approval.
Section 5525.07 | Notification of Final Action - Prequalification Review Board.
Section 5525.08 | Disposition of Bids of Unqualified Bidders - Nonresponsive Bids.
Section 5525.09 | False Statement With Respect to Financial Worth.
Section 5525.10 | Contracts Not to Be Awarded for More Than Cost Plus Five per Cent.
Section 5525.11 | Contract Upon a Unit Price Basis.
Section 5525.12 | Lumber Deemed Material.
Section 5525.13 | Limitation of Surety Bond and Insurance.
Section 5525.14 | Written Change Orders or Orders for Extra Work.
Section 5525.15 | Cost Estimates May Be Confidential.
Section 5525.16 | Contract Performance Bond and Payment Bond.
Section 5525.17 | Failure of Contractor or Surety to Complete Work.
Section 5525.18 | Contract With Foreign Corporation.
Section 5525.19 | Payment of Costs.
Section 5525.20 | Incentive and Disincentive Contract Provisions.
Section 5525.21 | Authorizing Minimal Amount of Foreign Steel Products in Bridge Projects.
Section 5525.22 | Demolition Contracts.
Section 5525.23 | Binding Dispute Resolution for Contract Controversies.
Section 5525.25 | Warranty Specifications in Bidding Documents.