1. If a subcontractor and another subcontractor or supplier enter into a subcontract for a public work, the subcontractor may withhold as retainage not more than 5 percent from the amount of any progress payment due under a subcontract which is made before 50 percent of the work has been completed under the subcontract.
2. After 50 percent of the work required by the subcontractor or supplier has been performed, the subcontractor shall pay any additional progress payments due under the subcontract without withholding any additional retainage if, in the opinion of the subcontractor, satisfactory progress is being made in the work under the subcontract. The payment must be equal to that paid by the contractor to the subcontractor for the work performed or supplies provided by his or her subcontractor or supplier. If the subcontractor continues to withhold retainage from remaining progress payments:
(a) If the subcontractor does not withhold any amount pursuant to NRS 338.600:
(1) The subcontractor may not withhold more than 2.5 percent of the amount of any progress payment; and
(2) Before withholding any amount pursuant to subparagraph (1), the subcontractor must pay to the subcontractor or supplier 50 percent of the amount of any retainage that was withheld from progress payments pursuant to subsection 1; or
(b) If the subcontractor withholds any amount pursuant to NRS 338.600:
(1) The subcontractor may not withhold more than 5 percent of the amount of any progress payment; and
(2) The subcontractor may continue to retain the amount of any retainage that was withheld from progress payments pursuant to subsection 1.
3. If the subcontractor receives a payment of interest earned on the retainage or an amount withheld from a progress payment, the subcontractor shall, within 10 days after receiving the money, pay to each of his or her subcontractors or suppliers that portion of the interest received from the contractor which is attributable to the retainage or amount withheld from a progress payment by the subcontractor to his or her subcontractor or supplier.
4. If, pursuant to subsection 4 of NRS 338.555, the contractor pays to the subcontractor the portion of any retainage withheld by the contractor pursuant to NRS 338.555 for the portion of the work which has been performed by the subcontractor, the subcontractor must pay to the subcontractor’s subcontractors and suppliers the portion of any retainage withheld by the subcontractor pursuant to this section for the portion of the work.
(Added to NRS by 1999, 1987; A 2003, 2449; 2011, 1623; 2015, 2628)
Structure Nevada Revised Statutes
NRS 338.0116 - Legislative findings and declarations.
NRS 338.012 - Regulations of Labor Commissioner.
NRS 338.015 - Enforcement by Labor Commissioner and Attorney General.
NRS 338.025 - Prevailing wage regions.
NRS 338.030 - Procedure for determination of prevailing wage in region; duration of rates.
NRS 338.040 - Workers deemed to be employed on public works; regulations.
NRS 338.050 - Contractual relationships: Applicability of NRS 338.010 to 338.090, inclusive.
NRS 338.072 - Requirement for subcontractor to hold state business license.
NRS 338.130 - Preferential employment in construction of public works.
NRS 338.1376 - State public works: Qualification of subcontractors; disqualification; appeal.
NRS 338.1377 - Local government public works: Adoption of criteria for qualification of bidders.
NRS 338.1382 - Local government public works: Alternative procedure for qualification of bidders.
NRS 338.13842 - "Local business" defined.
NRS 338.13843 - "Veteran with a service-connected disability" defined.
NRS 338.13844 - Amount of preferences.
NRS 338.13845 - Fraudulent acts.
NRS 338.13846 - Duty of State Public Works Division to report to Legislature.
NRS 338.13862 - Requirements for awarding contract for smaller public work to contractor.
NRS 338.139 - Awarding of contract to specialty contractor: Conditions.
NRS 338.148 - Awarding of contract to specialty contractor: Conditions.
NRS 338.155 - Provisions relating to design professional who is not member of design-build team.
NRS 338.1581 - "Concession" defined.
NRS 338.1582 - "Private partner" defined.
NRS 338.1583 - "Public-private partnership" defined.
NRS 338.1584 - "Transportation facility" defined.
NRS 338.1585 - "User fee" defined.
NRS 338.1587 - Public-private partnership: Authority to enter; authorized provisions.
NRS 338.1589 - Alternative methods: Authorization.
NRS 338.159 - Alternative methods: Submission of request to public body; contents of request.
NRS 338.1591 - Alternative methods: Request for submission of proposals by public body.
NRS 338.1598 - Contract for services under alternative methods.
NRS 338.1599 - Federal, state or local assistance.
NRS 338.1601 - Eminent domain.
NRS 338.1602 - Applicability of state and federal laws.
NRS 338.161 - "Transportation facility" defined.
NRS 338.162 - Alternative methods of authorization.
NRS 338.163 - Submission of request to public body; contents of request.
NRS 338.164 - Request for submission of proposals by public body.
NRS 338.167 - Contract for transportation services.
NRS 338.168 - Federal, state or local assistance.
NRS 338.1685 - Declaration of legislative intent.
NRS 338.1691 - Qualifications for construction manager at risk.
NRS 338.1715 - Procedure for selecting design-build team.
NRS 338.1718 - Contract with construction manager as agent.
NRS 338.1721 - Qualifications of design-build team.
NRS 338.1723 - Advertisement for preliminary proposals.
NRS 338.193 - Standards for plumbing fixtures.
NRS 338.415 - "Progress bill" defined.
NRS 338.420 - "Progress payment" defined.
NRS 338.425 - "Retainage" defined.
NRS 338.430 - "Retainage bill" defined.
NRS 338.435 - "Retainage payment" defined.
NRS 338.455 - Methods to be used for providing notice.
NRS 338.460 - Period for accrual of interest on retainage.
NRS 338.480 - Provisions inapplicable to certain contracts made by Department of Transportation.
NRS 338.510 - Submittal of progress bills.
NRS 338.530 - Payment of interest on amounts withheld improperly.
NRS 338.550 - Time for making payments; amounts paid.
NRS 338.555 - Amounts withheld as retainage; payment of interest.
NRS 338.565 - Payment of interest on amounts withheld improperly.
NRS 338.590 - Time for making payments; amounts paid.
NRS 338.595 - Amounts withheld as retainage; payment of interest.
NRS 338.605 - Payment of interest on amounts withheld improperly.
NRS 338.635 - Action by subcontractor or supplier to remedy unjustified or excessive withholding.
NRS 338.640 - Award of reasonable costs and attorney’s fees to prevailing party.