1. If a public body enters into a contract with a construction manager at risk for preconstruction services pursuant to NRS 338.1693, after the public body has finalized the design for the public work, or any portion thereof sufficient to determine the provable cost of that portion, the public body shall enter into negotiations with the construction manager at risk for a contract to construct the public work or the portion thereof for the public body for:
(a) The cost of the work, plus a fee, with a guaranteed maximum price;
(b) A fixed price; or
(c) A fixed price plus reimbursement for overhead and other costs and expenses related to the construction of the public work or portion thereof.
2. If the public body is unable to negotiate a satisfactory contract with the construction manager at risk to construct the public work or portion thereof, the public body shall terminate negotiations with that applicant and:
(a) May award the contract for the public work:
(1) If the public body is not a local government, pursuant to the provisions of NRS 338.1377 to 338.139, inclusive.
(2) If the public body is a local government, pursuant to the provisions of NRS 338.1377 to 338.139, inclusive, or 338.143 to 338.148, inclusive; and
(b) Shall accept a bid to construct the public work from the construction manager at risk with whom the public body entered into a contract for preconstruction services.
3. Before entering into a contract with the public body to construct a public work or a portion thereof pursuant to subsection 1, the construction manager at risk shall:
(a) Provide the public body with a list of the labor or portions of the work which are estimated by the construction manager at risk to exceed 1 percent of the estimated cost of the public work; and
(b) Select each subcontractor who is to provide labor or a portion of the work which is estimated by the construction manager at risk to exceed 1 percent of the estimated cost of the public work in accordance with NRS 338.16991 and 338.16995 and provide the names of each selected subcontractor to the public body.
4. Except as otherwise provided in subsection 13 of NRS 338.16995, a public body shall not interfere with the right of the construction manager at risk to select the subcontractor whom the construction manager at risk determines to have submitted the best proposal pursuant to NRS 338.16995.
(Added to NRS by 2007, 2893; A 2009, 440; 2011, 3697; 2013, 2977; R 2013, 2986; R 2017, 4035; A 2021, 736, 2218)
Structure Nevada Revised Statutes
NRS 338.0116 - Legislative findings and declarations.
NRS 338.012 - Regulations of Labor Commissioner.
NRS 338.015 - Enforcement by Labor Commissioner and Attorney General.
NRS 338.025 - Prevailing wage regions.
NRS 338.030 - Procedure for determination of prevailing wage in region; duration of rates.
NRS 338.040 - Workers deemed to be employed on public works; regulations.
NRS 338.050 - Contractual relationships: Applicability of NRS 338.010 to 338.090, inclusive.
NRS 338.072 - Requirement for subcontractor to hold state business license.
NRS 338.130 - Preferential employment in construction of public works.
NRS 338.1376 - State public works: Qualification of subcontractors; disqualification; appeal.
NRS 338.1377 - Local government public works: Adoption of criteria for qualification of bidders.
NRS 338.1382 - Local government public works: Alternative procedure for qualification of bidders.
NRS 338.13842 - "Local business" defined.
NRS 338.13843 - "Veteran with a service-connected disability" defined.
NRS 338.13844 - Amount of preferences.
NRS 338.13845 - Fraudulent acts.
NRS 338.13846 - Duty of State Public Works Division to report to Legislature.
NRS 338.13862 - Requirements for awarding contract for smaller public work to contractor.
NRS 338.139 - Awarding of contract to specialty contractor: Conditions.
NRS 338.148 - Awarding of contract to specialty contractor: Conditions.
NRS 338.155 - Provisions relating to design professional who is not member of design-build team.
NRS 338.1581 - "Concession" defined.
NRS 338.1582 - "Private partner" defined.
NRS 338.1583 - "Public-private partnership" defined.
NRS 338.1584 - "Transportation facility" defined.
NRS 338.1585 - "User fee" defined.
NRS 338.1587 - Public-private partnership: Authority to enter; authorized provisions.
NRS 338.1589 - Alternative methods: Authorization.
NRS 338.159 - Alternative methods: Submission of request to public body; contents of request.
NRS 338.1591 - Alternative methods: Request for submission of proposals by public body.
NRS 338.1598 - Contract for services under alternative methods.
NRS 338.1599 - Federal, state or local assistance.
NRS 338.1601 - Eminent domain.
NRS 338.1602 - Applicability of state and federal laws.
NRS 338.161 - "Transportation facility" defined.
NRS 338.162 - Alternative methods of authorization.
NRS 338.163 - Submission of request to public body; contents of request.
NRS 338.164 - Request for submission of proposals by public body.
NRS 338.167 - Contract for transportation services.
NRS 338.168 - Federal, state or local assistance.
NRS 338.1685 - Declaration of legislative intent.
NRS 338.1691 - Qualifications for construction manager at risk.
NRS 338.1715 - Procedure for selecting design-build team.
NRS 338.1718 - Contract with construction manager as agent.
NRS 338.1721 - Qualifications of design-build team.
NRS 338.1723 - Advertisement for preliminary proposals.
NRS 338.193 - Standards for plumbing fixtures.
NRS 338.415 - "Progress bill" defined.
NRS 338.420 - "Progress payment" defined.
NRS 338.425 - "Retainage" defined.
NRS 338.430 - "Retainage bill" defined.
NRS 338.435 - "Retainage payment" defined.
NRS 338.455 - Methods to be used for providing notice.
NRS 338.460 - Period for accrual of interest on retainage.
NRS 338.480 - Provisions inapplicable to certain contracts made by Department of Transportation.
NRS 338.510 - Submittal of progress bills.
NRS 338.530 - Payment of interest on amounts withheld improperly.
NRS 338.550 - Time for making payments; amounts paid.
NRS 338.555 - Amounts withheld as retainage; payment of interest.
NRS 338.565 - Payment of interest on amounts withheld improperly.
NRS 338.590 - Time for making payments; amounts paid.
NRS 338.595 - Amounts withheld as retainage; payment of interest.
NRS 338.605 - Payment of interest on amounts withheld improperly.
NRS 338.635 - Action by subcontractor or supplier to remedy unjustified or excessive withholding.
NRS 338.640 - Award of reasonable costs and attorney’s fees to prevailing party.