1. To qualify to receive a preference in bidding pursuant to subsection 2 of NRS 338.1389, subsection 2 of NRS 338.147, subsection 3 of NRS 338.1693, subsection 3 of NRS 338.1727 or subsection 2 of NRS 408.3886, a contractor, an applicant or a design-build team, respectively, must submit to the public body sponsoring or financing a public work a signed affidavit which certifies that, for the duration of the project, collectively, and not on any specific day:
(a) At least 50 percent of the workers employed on the public work, including, without limitation, any employees of the contractor, applicant or design-build team and of any subcontractor engaged on the public work, will hold a valid driver’s license or identification card issued by the Department of Motor Vehicles of the State of Nevada;
(b) All vehicles used primarily for the public work will be:
(1) Registered and partially apportioned to Nevada pursuant to the International Registration Plan, as adopted by the Department of Motor Vehicles pursuant to NRS 706.826; or
(2) Registered in this State;
(c) If applying to receive a preference in bidding pursuant to subsection 3 of NRS 338.1727 or subsection 2 of NRS 408.3886, at least 50 percent of the design professionals working on the public work, including, without limitation, employees of the design-build team and of any subcontractor or consultant engaged in the design of the public work, will have a valid driver’s license or identification card issued by the Department of Motor Vehicles of the State of Nevada; and
(d) The contractor, applicant or design-build team and any subcontractor engaged on the public work will maintain and make available for inspection within this State his or her records concerning payroll relating to the public work.
2. Any contract for a public work that is awarded to a contractor, applicant or design-build team who submits the affidavit described in subsection 1 as a result of the contractor, applicant or design-build team receiving a preference in bidding described in subsection 1 must:
(a) Include a provision in the contract that substantially incorporates the requirements of paragraphs (a) to (d), inclusive, of subsection 1; and
(b) Provide that a failure to comply with any requirement of paragraphs (a) to (d), inclusive, of subsection 1 entitles the public body to a penalty only as provided in subsections 5 and 6.
3. A person who submitted a bid on the public work or an entity who believes that a contractor, applicant or design-build team has obtained a preference in bidding as described in subsection 1 but has failed to comply with a requirement of paragraphs (a) to (d), inclusive, of subsection 1 may file, before the substantial completion of the public work, a written objection with the public body for which the contractor, applicant or design-build team is performing the public work. A written objection authorized pursuant to this subsection must set forth proof or substantiating evidence to support the belief of the person or entity that the contractor, applicant or design-build team has failed to comply with a requirement of paragraphs (a) to (d), inclusive, of subsection 1.
4. If a public body receives a written objection pursuant to subsection 3, the public body shall determine whether the objection is accompanied by the proof or substantiating evidence required pursuant to that subsection. If the public body determines that the objection is not accompanied by the required proof or substantiating evidence, the public body shall dismiss the objection. If the public body determines that the objection is accompanied by the required proof or substantiating evidence or if the public body determines on its own initiative that proof or substantiating evidence of a failure to comply with a requirement of paragraphs (a) to (d), inclusive, of subsection 1 exists, the public body shall determine whether the contractor, applicant or design-build team has failed to comply with a requirement of paragraphs (a) to (d), inclusive, of subsection 1 and the public body or its authorized representative may proceed to award the contract accordingly or, if the contract has already been awarded, seek the remedy authorized in subsection 5.
5. In addition to any other remedy or penalty provided by law, a public body may recover, by civil action against the party responsible for a failure to comply with a requirement of paragraphs (a) to (d), inclusive, of subsection 1, a penalty as described in subsection 6 for a failure to comply with a requirement of paragraphs (a) to (d), inclusive, of subsection 1. If a public body recovers a penalty pursuant to this subsection, the public body shall report to the State Contractors’ Board the date of the failure to comply, the name of each entity which failed to comply and the cost of the contract to which the entity that failed to comply was a party. The Board shall maintain this information for not less than 6 years. Upon request, the Board shall provide this information to any public body or its authorized representative.
6. If a contractor, applicant or design-build team submits the affidavit described in subsection 1, receives a preference in bidding described in subsection 1 and is awarded the contract as a result of that preference, the contract between the contractor, applicant or design-build team and the public body, each contract between the contractor, applicant or design-build team and a subcontractor and each contract between a subcontractor and a lower tier subcontractor must provide that:
(a) If a party to the contract causes the contractor, applicant or design-build team to fail to comply with a requirement of paragraphs (a) to (d), inclusive, of subsection 1, the party is liable to the public body for a penalty in the amount of 1 percent of the cost of the largest contract to which he or she is a party;
(b) The right to recover the amount determined pursuant to paragraph (a) by the public body pursuant to subsection 5 may be enforced by the public body directly against the party that caused the failure to comply with a requirement of paragraphs (a) to (d), inclusive, of subsection 1; and
(c) No other party to the contract is liable to the public body for a penalty.
7. A public body that awards a contract for a public work to a contractor, applicant or design-build team who submits the affidavit described in subsection 1 and who receives a preference in bidding described in subsection 1 shall, on or before July 31 of each year, submit a written report to the Director of the Legislative Counsel Bureau for transmittal to the Legislative Commission. The report must include information on each contract for a public work awarded to a contractor, applicant or design-build team who submits the affidavit described in subsection 1 and who receives a preference in bidding described in subsection 1, including, without limitation, the name of the contractor, applicant or design-build team who was awarded the contract, the cost of the contract, a brief description of the public work and a description of the degree to which the contractor, applicant or design-build team and each subcontractor complied with the requirements of paragraphs (a) to (d), inclusive, of subsection 1.
8. As used in this section:
(a) "Lower tier subcontractor" means a subcontractor who contracts with another subcontractor to provide labor, materials or services to the other subcontractor for a construction project.
(b) "Vehicle used primarily for the public work" does not include any vehicle that is present at the site of the public work only occasionally and for a purpose incidental to the public work including, without limitation, the delivery of materials. Notwithstanding the provisions of this paragraph, the term includes any vehicle which is:
(1) Owned or operated by the contractor or any subcontractor who is engaged on the public work; and
(2) Present at the site of the public work.
(Added to NRS by 2011, 39; A 2011, 2576; 2013, 1388, 2964; 2017, 4035, 4111; 2021, 736, 2218)
Structure Nevada Revised Statutes
NRS 338.0116 - Legislative findings and declarations.
NRS 338.012 - Regulations of Labor Commissioner.
NRS 338.015 - Enforcement by Labor Commissioner and Attorney General.
NRS 338.025 - Prevailing wage regions.
NRS 338.030 - Procedure for determination of prevailing wage in region; duration of rates.
NRS 338.040 - Workers deemed to be employed on public works; regulations.
NRS 338.050 - Contractual relationships: Applicability of NRS 338.010 to 338.090, inclusive.
NRS 338.072 - Requirement for subcontractor to hold state business license.
NRS 338.130 - Preferential employment in construction of public works.
NRS 338.1376 - State public works: Qualification of subcontractors; disqualification; appeal.
NRS 338.1377 - Local government public works: Adoption of criteria for qualification of bidders.
NRS 338.1382 - Local government public works: Alternative procedure for qualification of bidders.
NRS 338.13842 - "Local business" defined.
NRS 338.13843 - "Veteran with a service-connected disability" defined.
NRS 338.13844 - Amount of preferences.
NRS 338.13845 - Fraudulent acts.
NRS 338.13846 - Duty of State Public Works Division to report to Legislature.
NRS 338.13862 - Requirements for awarding contract for smaller public work to contractor.
NRS 338.139 - Awarding of contract to specialty contractor: Conditions.
NRS 338.148 - Awarding of contract to specialty contractor: Conditions.
NRS 338.155 - Provisions relating to design professional who is not member of design-build team.
NRS 338.1581 - "Concession" defined.
NRS 338.1582 - "Private partner" defined.
NRS 338.1583 - "Public-private partnership" defined.
NRS 338.1584 - "Transportation facility" defined.
NRS 338.1585 - "User fee" defined.
NRS 338.1587 - Public-private partnership: Authority to enter; authorized provisions.
NRS 338.1589 - Alternative methods: Authorization.
NRS 338.159 - Alternative methods: Submission of request to public body; contents of request.
NRS 338.1591 - Alternative methods: Request for submission of proposals by public body.
NRS 338.1598 - Contract for services under alternative methods.
NRS 338.1599 - Federal, state or local assistance.
NRS 338.1601 - Eminent domain.
NRS 338.1602 - Applicability of state and federal laws.
NRS 338.161 - "Transportation facility" defined.
NRS 338.162 - Alternative methods of authorization.
NRS 338.163 - Submission of request to public body; contents of request.
NRS 338.164 - Request for submission of proposals by public body.
NRS 338.167 - Contract for transportation services.
NRS 338.168 - Federal, state or local assistance.
NRS 338.1685 - Declaration of legislative intent.
NRS 338.1691 - Qualifications for construction manager at risk.
NRS 338.1715 - Procedure for selecting design-build team.
NRS 338.1718 - Contract with construction manager as agent.
NRS 338.1721 - Qualifications of design-build team.
NRS 338.1723 - Advertisement for preliminary proposals.
NRS 338.193 - Standards for plumbing fixtures.
NRS 338.415 - "Progress bill" defined.
NRS 338.420 - "Progress payment" defined.
NRS 338.425 - "Retainage" defined.
NRS 338.430 - "Retainage bill" defined.
NRS 338.435 - "Retainage payment" defined.
NRS 338.455 - Methods to be used for providing notice.
NRS 338.460 - Period for accrual of interest on retainage.
NRS 338.480 - Provisions inapplicable to certain contracts made by Department of Transportation.
NRS 338.510 - Submittal of progress bills.
NRS 338.530 - Payment of interest on amounts withheld improperly.
NRS 338.550 - Time for making payments; amounts paid.
NRS 338.555 - Amounts withheld as retainage; payment of interest.
NRS 338.565 - Payment of interest on amounts withheld improperly.
NRS 338.590 - Time for making payments; amounts paid.
NRS 338.595 - Amounts withheld as retainage; payment of interest.
NRS 338.605 - Payment of interest on amounts withheld improperly.
NRS 338.635 - Action by subcontractor or supplier to remedy unjustified or excessive withholding.
NRS 338.640 - Award of reasonable costs and attorney’s fees to prevailing party.