1. After selecting the finalists pursuant to NRS 338.1725, the public body shall provide to each finalist a request for final proposals for the public work. The request for final proposals must:
(a) Set forth the factors that the public body will use to select a design-build team to design and construct the public work, including the relative weight to be assigned to each factor; and
(b) Set forth the date by which final proposals must be submitted to the public body.
2. If one or more of the finalists selected pursuant to NRS 338.1725 is disqualified or withdraws, the public body may select a design-build team from the remaining finalist or finalists.
3. Except as otherwise provided in this subsection, in assigning the relative weight to each factor for selecting a design-build team pursuant to subsection 1, the public body shall assign, without limitation, a relative weight of 5 percent to the possession of both a certificate of eligibility to receive a preference in bidding on public works by all contractors on the design-build team if the contractors submit signed affidavits that meet the requirements of subsection 1 of NRS 338.0117, and a certificate of eligibility to receive a preference when competing for public works by all design professionals on the design-build team, and a relative weight of at least 30 percent to the proposed cost of design and construction of the public work. If any federal statute or regulation precludes the granting of federal assistance or reduces the amount of that assistance for a particular public work because of the provisions of this subsection relating to a preference in bidding on public works, or a preference when competing for public works, those provisions of this subsection do not apply insofar as their application would preclude or reduce federal assistance for that public work.
4. A final proposal submitted by a design-build team pursuant to this section must be prepared thoroughly and be responsive to the criteria that the public body will use to select a design-build team to design and construct the public work described in subsection 1. A design-build team that submits a final proposal which is not responsive shall not be awarded the contract and shall not be eligible for the partial reimbursement of costs provided for in subsection 7.
5. A final proposal is exempt from the requirements of NRS 338.141.
6. After receiving and evaluating the final proposals for the public work, the public body or its authorized representative shall enter into negotiations with the most qualified applicant, as determined pursuant to the criteria set forth pursuant to subsections 1 and 3, and award the design-build contract to the design-build team whose proposal is selected. If the public body or its authorized representative is unable to negotiate with the most qualified applicant a contract that is determined by the parties to be fair and reasonable, the public body may terminate negotiations with that applicant. The public body or its authorized representative may then undertake negotiations with the next most qualified applicant in sequence until an agreement is reached and, if the negotiation is undertaken by an authorized representative of the public body, approved by the public body or until a determination is made by the public body to reject all applicants.
7. If a public body selects a final proposal and awards a design-build contract pursuant to subsection 6, the public body shall:
(a) Partially reimburse the unsuccessful finalists if partial reimbursement was provided for in the request for preliminary proposals pursuant to paragraph (j) of subsection 2 of NRS 338.1723. The amount of reimbursement must not exceed, for each unsuccessful finalist, 3 percent of the total amount to be paid to the design-build team as set forth in the design-build contract.
(b) Make available to the public the results of the evaluation of final proposals that was conducted and the ranking of the design-build teams who submitted final proposals. The public body shall not release to a third party, or otherwise make public, financial or proprietary information submitted by a design-build team.
8. A contract awarded pursuant to this section:
(a) Must comply with the provisions of NRS 338.020 to 338.090, inclusive.
(b) Must specify:
(1) An amount that is the maximum amount that the public body will pay for the performance of all the work required by the contract, excluding any amount related to costs that may be incurred as a result of unexpected conditions or occurrences as authorized by the contract;
(2) An amount that is the maximum amount that the public body will pay for the performance of the professional services required by the contract; and
(3) A date by which performance of the work required by the contract must be completed.
(c) May set forth the terms by which the design-build team agrees to name the public body, at the cost of the public body, as an additional insured in an insurance policy held by the design-build team.
(d) Except as otherwise provided in paragraph (e), must not require the design professional to defend, indemnify or hold harmless the public body or the employees, officers or agents of that public body from any liability, damage, loss, claim, action or proceeding caused by the negligence, errors, omissions, recklessness or intentional misconduct of the employees, officers and agents of the public body.
(e) May require the design-build team to defend, indemnify and hold harmless the public body, and the employees, officers and agents of the public body from any liabilities, damages, losses, claims, actions or proceedings, including, without limitation, reasonable attorneys’ fees, that are caused by the negligence, errors, omissions, recklessness or intentional misconduct of the design-build team or the employees or agents of the design-build team in the performance of the contract.
(f) Must require that the design-build team to whom a contract is awarded assume overall responsibility for ensuring that the design and construction of the public work is completed in a satisfactory manner.
9. Upon award of the design-build contract, the public body shall make available to the public copies of all preliminary and final proposals received.
(Added to NRS by 1999, 3471; A 2001, 1272, 2017, 2022; 2003, 33, 119, 2027, 2132, 2442; 2005, 1812; 2011, 51, 3699, 3701)
Structure Nevada Revised Statutes
NRS 338.0116 - Legislative findings and declarations.
NRS 338.012 - Regulations of Labor Commissioner.
NRS 338.015 - Enforcement by Labor Commissioner and Attorney General.
NRS 338.025 - Prevailing wage regions.
NRS 338.030 - Procedure for determination of prevailing wage in region; duration of rates.
NRS 338.040 - Workers deemed to be employed on public works; regulations.
NRS 338.050 - Contractual relationships: Applicability of NRS 338.010 to 338.090, inclusive.
NRS 338.072 - Requirement for subcontractor to hold state business license.
NRS 338.130 - Preferential employment in construction of public works.
NRS 338.1376 - State public works: Qualification of subcontractors; disqualification; appeal.
NRS 338.1377 - Local government public works: Adoption of criteria for qualification of bidders.
NRS 338.1382 - Local government public works: Alternative procedure for qualification of bidders.
NRS 338.13842 - "Local business" defined.
NRS 338.13843 - "Veteran with a service-connected disability" defined.
NRS 338.13844 - Amount of preferences.
NRS 338.13845 - Fraudulent acts.
NRS 338.13846 - Duty of State Public Works Division to report to Legislature.
NRS 338.13862 - Requirements for awarding contract for smaller public work to contractor.
NRS 338.139 - Awarding of contract to specialty contractor: Conditions.
NRS 338.148 - Awarding of contract to specialty contractor: Conditions.
NRS 338.155 - Provisions relating to design professional who is not member of design-build team.
NRS 338.1581 - "Concession" defined.
NRS 338.1582 - "Private partner" defined.
NRS 338.1583 - "Public-private partnership" defined.
NRS 338.1584 - "Transportation facility" defined.
NRS 338.1585 - "User fee" defined.
NRS 338.1587 - Public-private partnership: Authority to enter; authorized provisions.
NRS 338.1589 - Alternative methods: Authorization.
NRS 338.159 - Alternative methods: Submission of request to public body; contents of request.
NRS 338.1591 - Alternative methods: Request for submission of proposals by public body.
NRS 338.1598 - Contract for services under alternative methods.
NRS 338.1599 - Federal, state or local assistance.
NRS 338.1601 - Eminent domain.
NRS 338.1602 - Applicability of state and federal laws.
NRS 338.161 - "Transportation facility" defined.
NRS 338.162 - Alternative methods of authorization.
NRS 338.163 - Submission of request to public body; contents of request.
NRS 338.164 - Request for submission of proposals by public body.
NRS 338.167 - Contract for transportation services.
NRS 338.168 - Federal, state or local assistance.
NRS 338.1685 - Declaration of legislative intent.
NRS 338.1691 - Qualifications for construction manager at risk.
NRS 338.1715 - Procedure for selecting design-build team.
NRS 338.1718 - Contract with construction manager as agent.
NRS 338.1721 - Qualifications of design-build team.
NRS 338.1723 - Advertisement for preliminary proposals.
NRS 338.193 - Standards for plumbing fixtures.
NRS 338.415 - "Progress bill" defined.
NRS 338.420 - "Progress payment" defined.
NRS 338.425 - "Retainage" defined.
NRS 338.430 - "Retainage bill" defined.
NRS 338.435 - "Retainage payment" defined.
NRS 338.455 - Methods to be used for providing notice.
NRS 338.460 - Period for accrual of interest on retainage.
NRS 338.480 - Provisions inapplicable to certain contracts made by Department of Transportation.
NRS 338.510 - Submittal of progress bills.
NRS 338.530 - Payment of interest on amounts withheld improperly.
NRS 338.550 - Time for making payments; amounts paid.
NRS 338.555 - Amounts withheld as retainage; payment of interest.
NRS 338.565 - Payment of interest on amounts withheld improperly.
NRS 338.590 - Time for making payments; amounts paid.
NRS 338.595 - Amounts withheld as retainage; payment of interest.
NRS 338.605 - Payment of interest on amounts withheld improperly.
NRS 338.635 - Action by subcontractor or supplier to remedy unjustified or excessive withholding.
NRS 338.640 - Award of reasonable costs and attorney’s fees to prevailing party.