75-20-208. Certain electric transmission lines -- verification of requirements. (1) Prior to constructing a transmission line under 75-20-104(10)(a)(ii), the person planning to construct the line shall provide to the department within 36 months of the date of the public notice provided under 75-20-207, unless extended by the department for good cause:
(a) copies of the right-of-way agreements or options for a right-of-way containing sufficient information to establish landowner consent to construct the line; and
(b) sufficient information for the department to verify that the requirements of 75-20-104(10)(a)(ii) are satisfied.
(2) The provisions of 75-20-104(10)(a)(ii) do not apply to any facility for which public notice under 75-20-207 has been given but for which the requirements of subsection (1) of this section have not been complied with.
History: En. Sec. 3, Ch. 597, L. 1987; amd. Sec. 216, Ch. 418, L. 1995; amd. Sec. 537, Ch. 546, L. 1995; amd. Sec. 8, Ch. 329, L. 1997; amd. Sec. 4, Ch. 293, L. 2001; amd. Sec. 4, Ch. 447, L. 2019; amd. Sec. 8, Ch. 13, L. 2021.
Structure Montana Code Annotated
Title 75. Environmental Protection
Chapter 20. Major Facility Siting
Part 2. Certification Proceedings
75-20-203. Certificate transferable
75-20-204. Facilities subject to federal energy regulatory commission jurisdiction
75-20-207. Notice requirement for certain electric transmission lines
75-20-208. Certain electric transmission lines -- verification of requirements
75-20-209. and 75-20-210 reserved
75-20-211. Application -- filing and contents -- proof of service and notice
75-20-212. Cure for failure of service
75-20-213. Supplemental material -- amendments
75-20-215. Filing fee -- accountability -- refund -- use
75-20-216. Study, evaluation, and report on proposed facility -- assistance by other agencies
75-20-217. Voiding an application
75-20-219. Amendments to certificate
75-20-223. Board review of department decisions
75-20-228. Electric generating facility fuel source change -- notice requirements
75-20-229. and 75-20-230 reserved
75-20-232. Criteria for identifying proposed facilities that qualify for expedited review