Montana Code Annotated
Part 2. Certification Proceedings
75-20-208. Certain electric transmission lines -- verification of requirements

75-20-208. Certain electric transmission lines -- verification of requirements. (1) Prior to constructing a transmission line under 75-20-104(10)(a)(ii), the person planning to construct the line shall provide to the department within 36 months of the date of the public notice provided under 75-20-207, unless extended by the department for good cause:
(a) copies of the right-of-way agreements or options for a right-of-way containing sufficient information to establish landowner consent to construct the line; and
(b) sufficient information for the department to verify that the requirements of 75-20-104(10)(a)(ii) are satisfied.
(2) The provisions of 75-20-104(10)(a)(ii) do not apply to any facility for which public notice under 75-20-207 has been given but for which the requirements of subsection (1) of this section have not been complied with.
History: En. Sec. 3, Ch. 597, L. 1987; amd. Sec. 216, Ch. 418, L. 1995; amd. Sec. 537, Ch. 546, L. 1995; amd. Sec. 8, Ch. 329, L. 1997; amd. Sec. 4, Ch. 293, L. 2001; amd. Sec. 4, Ch. 447, L. 2019; amd. Sec. 8, Ch. 13, L. 2021.

Structure Montana Code Annotated

Montana Code Annotated

Title 75. Environmental Protection

Chapter 20. Major Facility Siting

Part 2. Certification Proceedings

75-20-201. Certificate required -- operation in conformance -- certificate for nuclear facility -- applicability to federal facilities

75-20-202. Repealed

75-20-203. Certificate transferable

75-20-204. Facilities subject to federal energy regulatory commission jurisdiction

75-20-205. Repealed

75-20-206. reserved

75-20-207. Notice requirement for certain electric transmission lines

75-20-208. Certain electric transmission lines -- verification of requirements

75-20-209. and 75-20-210 reserved

75-20-211. Application -- filing and contents -- proof of service and notice

75-20-212. Cure for failure of service

75-20-213. Supplemental material -- amendments

75-20-214. Repealed

75-20-215. Filing fee -- accountability -- refund -- use

75-20-216. Study, evaluation, and report on proposed facility -- assistance by other agencies

75-20-217. Voiding an application

75-20-218. Repealed

75-20-219. Amendments to certificate

75-20-220. Repealed

75-20-221. Repealed

75-20-222. Repealed

75-20-223. Board review of department decisions

75-20-224. reserved

75-20-225. Repealed

75-20-226. Repealed

75-20-227. Repealed

75-20-228. Electric generating facility fuel source change -- notice requirements

75-20-229. and 75-20-230 reserved

75-20-231. Expedited review

75-20-232. Criteria for identifying proposed facilities that qualify for expedited review