75-20-207. Notice requirement for certain electric transmission lines

75-20-207. Notice requirement for certain electric transmission lines. Whenever a person plans to construct an electric transmission line or associated facilities under the provisions of 75-20-104(10)(a)(ii), it must provide public notice to persons residing in the area in which any portion of the electric transmission facility may be located and to the department. This notice must be made no less than 60 days prior to the commencement of acquisition of right-of-way as defined in 75-20-104 by publication of a summary describing the transmission facility and the proposed location of the facility in those newspapers that will substantially inform those persons of the construction and by mailing a summary to the department. The notice must inform the property owners of their rights under this chapter concerning the location of the facility and that more information concerning their rights may be obtained from the department.
History: En. Sec. 2, Ch. 597, L. 1987; amd. Sec. 7, Ch. 329, L. 1997; amd. Sec. 3, Ch. 293, L. 2001; amd. Sec. 3, Ch. 447, L. 2019; amd. Sec. 7, Ch. 13, L. 2021.

Structure Montana Code Annotated

Montana Code Annotated

Title 75. Environmental Protection

Chapter 20. Major Facility Siting

Part 2. Certification Proceedings

75-20-201. Certificate required -- operation in conformance -- certificate for nuclear facility -- applicability to federal facilities

75-20-202. Repealed

75-20-203. Certificate transferable

75-20-204. Facilities subject to federal energy regulatory commission jurisdiction

75-20-205. Repealed

75-20-206. reserved

75-20-207. Notice requirement for certain electric transmission lines

75-20-208. Certain electric transmission lines -- verification of requirements

75-20-209. and 75-20-210 reserved

75-20-211. Application -- filing and contents -- proof of service and notice

75-20-212. Cure for failure of service

75-20-213. Supplemental material -- amendments

75-20-214. Repealed

75-20-215. Filing fee -- accountability -- refund -- use

75-20-216. Study, evaluation, and report on proposed facility -- assistance by other agencies

75-20-217. Voiding an application

75-20-218. Repealed

75-20-219. Amendments to certificate

75-20-220. Repealed

75-20-221. Repealed

75-20-222. Repealed

75-20-223. Board review of department decisions

75-20-224. reserved

75-20-225. Repealed

75-20-226. Repealed

75-20-227. Repealed

75-20-228. Electric generating facility fuel source change -- notice requirements

75-20-229. and 75-20-230 reserved

75-20-231. Expedited review

75-20-232. Criteria for identifying proposed facilities that qualify for expedited review