Montana Code Annotated
Part 2. Certification Proceedings
75-20-204. Facilities subject to federal energy regulatory commission jurisdiction

75-20-204. Facilities subject to federal energy regulatory commission jurisdiction. (1) For a facility that is subject to the jurisdiction of the federal energy regulatory commission, the department shall file a state recommendation with the commission.
(2) A person making application to the federal energy regulatory commission shall file with the department notice of and a copy of the federal application regarding any facility subject to subsection (1). The state recommendation must be based on its study of the federal application and other material gained through intervention in the federal proceeding.
(3) A person subject to the provisions of subsection (2) shall pay a fee to the department at the time that an application is filed with the federal energy regulatory commission. The fee must be used by the department to carry out its responsibilities to develop a state recommendation and participate as a party in any necessary federal proceeding to assert the state recommendation. The fee may not exceed one-half the amount that could be assessed under 75-20-215. A fee prescribed by 75-20-215 may not be assessed against a person paying a fee under this section.
(4) A person who fails to file a timely notice of and a copy of the federal application with the department, preventing the department from timely compliance with this section and with the rules, statutes, or procedures governing the proceedings before the federal energy regulatory commission, is subject to the provisions of 75-20-408.
History: En. Sec. 2, Ch. 591, L. 1985; amd. Sec. 2, Ch. 273, L. 1997.

Structure Montana Code Annotated

Montana Code Annotated

Title 75. Environmental Protection

Chapter 20. Major Facility Siting

Part 2. Certification Proceedings

75-20-201. Certificate required -- operation in conformance -- certificate for nuclear facility -- applicability to federal facilities

75-20-202. Repealed

75-20-203. Certificate transferable

75-20-204. Facilities subject to federal energy regulatory commission jurisdiction

75-20-205. Repealed

75-20-206. reserved

75-20-207. Notice requirement for certain electric transmission lines

75-20-208. Certain electric transmission lines -- verification of requirements

75-20-209. and 75-20-210 reserved

75-20-211. Application -- filing and contents -- proof of service and notice

75-20-212. Cure for failure of service

75-20-213. Supplemental material -- amendments

75-20-214. Repealed

75-20-215. Filing fee -- accountability -- refund -- use

75-20-216. Study, evaluation, and report on proposed facility -- assistance by other agencies

75-20-217. Voiding an application

75-20-218. Repealed

75-20-219. Amendments to certificate

75-20-220. Repealed

75-20-221. Repealed

75-20-222. Repealed

75-20-223. Board review of department decisions

75-20-224. reserved

75-20-225. Repealed

75-20-226. Repealed

75-20-227. Repealed

75-20-228. Electric generating facility fuel source change -- notice requirements

75-20-229. and 75-20-230 reserved

75-20-231. Expedited review

75-20-232. Criteria for identifying proposed facilities that qualify for expedited review