Minnesota Statutes
Chapter 103E — Drainage
Section 103E.511 — Contract Not Awarded; Excessive Bids Or Costs.

Subdivision 1. Applicability. The procedure in this section may be used if, after a drainage system is established:
(1) the only bids received are for more than 30 percent in excess of the engineer's estimated cost, or in excess of the benefits, less damages and other costs; or
(2) a contract is awarded, but due to unavoidable delays not caused by the contractor, the contract cannot be completed for an amount equal to or less than the benefits, less damages and other costs.
Subd. 2. Petition after cost estimate error or change to lower cost. A person interested in the drainage project may petition the drainage authority if the person determines that the engineer made an error in the estimate of the drainage project cost or that the plans and specifications could be changed in a manner materially affecting the cost of the drainage system without interfering with efficiency. The petition must state the person's determinations and request that the detailed survey report and viewers' report be referred back to the engineer and to the viewers for additional consideration.
Subd. 3. Petition after excessive cost due to inflation. (a) A person interested in the drainage project may petition the drainage authority for an order to reconsider the detailed survey report and viewers' report if the person determines:
(1) that bids were received only for a price more than 30 percent in excess of the detailed survey report estimate because inflation increased the construction cost between the time of the detailed survey cost estimate and the time of awarding the contract; or
(2) that after the contract was awarded there was unavoidable delay not caused by the contractor, and between the time of awarding the contract and completion of construction inflation increased construction costs resulting in the contract not being completed for an amount equal to or less than the assessed benefits.
(b) The person may request in the petition that the drainage authority reconsider the original cost estimate in the detailed survey report and viewers' report and adjust the cost estimate consistent with the increased construction cost.
Subd. 4. Hearing. After receiving a petition, the drainage authority shall order a hearing. The order must designate the time and place of the hearing and direct the auditor to give notice by publication.
Subd. 5. Orders and actions after hearing. (a) At the hearing the drainage authority shall consider the petition and hear all interested parties.
(b) The drainage authority may, by order, authorize the engineer to amend the detailed survey report, if the drainage authority determines that:
(1) the detailed survey report cost estimate was erroneous and should be corrected;
(2) the plans and specifications could be changed in a manner materially affecting the cost of the drainage project without interfering with efficiency; and
(3) with the correction or modification a contract could be awarded within the 30 percent limitation and equal to or less than benefits.
(c) If the drainage authority determines that the amended changes affect the amount of benefits or damages to any property or that the benefits should be reexamined because of inflated land values or inflated construction costs, it shall refer the viewers' report to the viewers to reexamine the benefits and damages.
(d) The drainage authority may, by order, direct the engineer and viewers to amend their detailed survey report and viewers' report to consider the inflationary cost increases if the drainage authority determines that:
(1) bids were not received; or
(2) because of inflationary construction cost increases, construction under the awarded contract cannot be completed for 30 percent or less over the detailed survey cost estimate or in excess of the benefits, less damages and other costs.
(e) The drainage authority may continue the hearing to give the engineer or viewers additional time to amend the reports. The jurisdiction of the drainage authority continues at the adjourned hearing.
(f) The drainage authority has full authority to consider the amended reports and make findings and orders. A party may appeal to the district court under section 103E.091, subdivision 1.
1990 c 391 art 5 s 65

Structure Minnesota Statutes

Minnesota Statutes

Chapters 103A - 114B — Water

Chapter 103E — Drainage

Section 103E.005 — Definitions.

Section 103E.011 — Drainage Authority Powers.

Section 103E.015 — Considerations Before Drainage Work Is Done.

Section 103E.021 — Planting Ditches With Perennial Vegetation.

Section 103E.025 — Procedure For Drainage Project That Affects State Land Or Water Area Used For Conservation.

Section 103E.031 — Connection With Drains In Adjoining States.

Section 103E.035 — Defective Notice.

Section 103E.041 — Personal Service In Lieu Of Other Methods Of Notice.

Section 103E.043 — Informal Meetings.

Section 103E.045 — Failure To Attend Hearings; Drainage Authority.

Section 103E.051 — Defective Proceedings.

Section 103E.055 — Reimbursing Cost Of Former Surveys When Used Later.

Section 103E.061 — Right Of Entry.

Section 103E.065 — Drainage Inspectors.

Section 103E.067 — Ditch Buffer Strip; Annual Reporting.

Section 103E.071 — County Attorney.

Section 103E.075 — Obstructing Drainage System.

Section 103E.081 — Crimes Related To Drainage Systems; Penalties.

Section 103E.085 — Enforcement.

Section 103E.091 — Appeals.

Section 103E.095 — Appeal From Orders Dismissing Or Establishing Drainage Systems.

Section 103E.097 — Attorney Fees On Appeal.

Section 103E.101 — Drainage Proceeding And Construction Records.

Section 103E.105 — Advice About Drainage Questions.

Section 103E.111 — Field Surveys And Investigations By Director.

Section 103E.115 — Hydrological And Drainage Information.

Section 103E.121 — Drain Tile; Manufacturing Studies.

Section 103E.202 — Petitions.

Section 103E.212 — New Drainage System Projects.

Section 103E.215 — Improving Drainage Systems.

Section 103E.221 — Improving Outlets.

Section 103E.225 — Laterals.

Section 103E.227 — Impounding, Rerouting, And Diverting Drainage System Waters.

Section 103E.231 — Dismissing Or Delaying Proceedings; Petitioners.

Section 103E.235 — Drainage System In Two Or More Counties.

Section 103E.238 — County Attorney Review Of Petition And Bond.

Section 103E.241 — Engineer.

Section 103E.245 — Preliminary Survey And Preliminary Survey Report.

Section 103E.251 — Filing Preliminary Survey Report.

Section 103E.255 — Commissioner's Preliminary Advisory Report.

Section 103E.261 — Preliminary Hearing.

Section 103E.265 — Order For Detailed Survey And Survey Report.

Section 103E.271 — Detailed Survey.

Section 103E.275 — Engineer's Variance From Drainage Authority Order.

Section 103E.281 — Soil Survey.

Section 103E.285 — Detailed Survey Report.

Section 103E.291 — Filing Detailed Survey Report.

Section 103E.295 — Revising Engineer's Detailed Survey Report After Acceptance.

Section 103E.301 — Commissioner's Final Advisory Report.

Section 103E.305 — Viewers' Appointment And Qualification.

Section 103E.311 — Viewer Duties.

Section 103E.315 — Assessing Drainage Benefits And Damages.

Section 103E.321 — Viewers' Report.

Section 103E.323 — Property Owners' Report.

Section 103E.325 — Final Hearing Notice.

Section 103E.331 — Jurisdiction Of Property By Drainage Authority.

Section 103E.335 — Proceedings At Final Hearing.

Section 103E.341 — Drainage Authority Final Order.

Section 103E.345 — Apportioning Cost For Joint County Drainage Systems.

Section 103E.351 — Redetermining Benefits And Damages.

Section 103E.401 — Use Of Drainage System As Outlet.

Section 103E.405 — Outlets In Adjoining States.

Section 103E.411 — Drainage System As Outlet For Municipality.

Section 103E.501 — Contract And Bond.

Section 103E.505 — Awarding Construction Contract.

Section 103E.511 — Contract Not Awarded; Excessive Bids Or Costs.

Section 103E.515 — Damages; Payment.

Section 103E.521 — Construction Supervision.

Section 103E.525 — Constructing And Maintaining Bridges And Culverts.

Section 103E.526 — Constructing Road Instead Of Bridge Or Culvert.

Section 103E.53 — Rules To Standardize Forms.

Section 103E.531 — Inspecting Drainage Construction; Partial Payments.

Section 103E.535 — Partial Payment Of Retained Contract Amounts.

Section 103E.541 — Extending Time On Contracts.

Section 103E.545 — Reducing Contractor's Bond.

Section 103E.551 — Contractor Default.

Section 103E.555 — Accepting Contract.

Section 103E.601 — Drainage Lien Statement.

Section 103E.605 — Effect Of Filed Drainage Lien.

Section 103E.611 — Paying Drainage Liens And Interest.

Section 103E.615 — Enforcing Assessments.

Section 103E.621 — Satisfying Liens.

Section 103E.625 — Subdivision By Platting; Liens Apportioned.

Section 103E.631 — Apportioning Liens.

Section 103E.635 — Drainage Bond Issues.

Section 103E.641 — Drainage Funding Bonds.

Section 103E.645 — Allowance And Payment Of Fees And Expenses.

Section 103E.651 — Drainage System Account.

Section 103E.655 — Paying Drainage System Costs.

Section 103E.661 — Examining And Establishing Drainage System Accounts; State Auditor.

Section 103E.701 — Repairs.

Section 103E.705 — Repair Procedure.

Section 103E.711 — Cost Apportionment For Joint County Drainage Systems.

Section 103E.715 — Repair By Petition.

Section 103E.721 — Replacement And Hydraulic Capacity Of Bridges And Culverts.

Section 103E.725 — Cost Of Repair.

Section 103E.728 — Apportioning Repair Costs.

Section 103E.729 — Apportioning Repair Costs; Alternative Option.

Section 103E.731 — Assessment; Bonds.

Section 103E.735 — Drainage Systems; Repair Fund.

Section 103E.741 — Property Not Assessed Benefits; Hearing.

Section 103E.745 — Cost Of Repair Exceeding Benefits In Anoka County.

Section 103E.801 — Consolidating Or Dividing Drainage Systems.

Section 103E.805 — Removing Property From Drainage System.

Section 103E.806 — Partial Abandonment Of Drainage System.

Section 103E.811 — Abandoning Drainage System.

Section 103E.812 — Transfer Of All Or Part Of Drainage System.