Subdivision 1. Report and information required. The engineer shall prepare a detailed survey report that includes the data and information in this section.
Subd. 2. Map. A complete map of the proposed drainage project and drainage system must be drawn to scale, showing:
(1) the terminus and course of each drain and whether it is ditch or tile, and the location of other proposed drainage works;
(2) the location and situation of the outlet;
(3) the watershed of the proposed drainage project and the subwatershed of main branches, if any, with the location of existing highway bridges and culverts;
(4) all property affected, with the names of the known owners;
(5) public roads and railways affected;
(6) the outline of any lake basin, wetland, or public water body affected;
(7) other physical characteristics of the watershed necessary to understand the proposed drainage project and the affected drainage system; and
(8) the area to be acquired to maintain a grass strip under section 103E.021.
Subd. 3. Profile of drainage lines. A profile of all proposed drainage lines must be presented showing, graphically, the elevation of the ground and gradient at each 100-foot station, and the station number at each section line and at each property line. The profile must show information necessary to understand it, including, in the case of an open ditch, the bottom width and side slope and, in the case of a tiled ditch, the size of tile.
Subd. 4. Bridge and culvert plans. Plans for private bridges and culverts to be constructed by and as a part of the proposed drainage project and plans for other works to be constructed for the proposed drainage project must be presented. A list must be made that shows the required minimum hydraulic capacity of bridges and culverts at railways and highways that cross ditches, and at other prospective ditch crossings where bridges and culverts are not specified to be constructed as part of the proposed drainage project. Plans and estimates of the cost of highway bridges and culverts must be prepared for the viewers to determine benefits and damages.
Subd. 5. Tabular statement of excavation, construction, and cost. A tabular statement must be prepared showing:
(1) the number of cubic yards of excavation, linear feet of tile, and average depth on each tile line;
(2) the bridges, culverts, and works to be constructed under the plans for the drainage project; and
(3) the estimated unit cost of each item, a summary of the total cost, and an estimate of the total cost of completing the proposed drainage project that includes supervision and other costs.
Subd. 6. Right-of-way acreage. The acreage must be shown that will be taken for ditch right-of-way on each government lot, 40-acre tract, or fraction of a lot or tract under separate ownership. The ditch right-of-way must include the area to be taken to maintain a grass strip under section 103E.021.
Subd. 7. Drain tile; specifications. Specifications for drain tile must be given that comply with the requirements of the American Society for Testing Materials standard specifications for drain tile, except where the engineer requires tile of a special, higher quality for certain tile depths or soil conditions.
Subd. 8. Soil survey report. If required under section 103E.281, the report on the soil survey must be included in the detailed survey report or submitted and filed separately before the final hearing.
Subd. 9. Recommendation to divide work. If construction of the proposed drainage project would be more economical, the engineer may recommend:
(1) that the work be divided into sections and contracted separately;
(2) that the ditch and tile work or tile and labor on the project be contracted separately; or
(3) the time and manner for the work to be completed.
Subd. 10. Other information on practicability and necessity of drainage project. Other data and information to inform the drainage authority of the practicability and necessity of the proposed drainage project must be made available including a comprehensive examination and the recommendation by the engineer regarding the environmental, land use, and multipurpose water management criteria in section 103E.015, subdivision 1.
Subd. 11. Outlet in another state. If an outlet is only practical in an adjoining state, the engineer shall describe the right-of-way needed and the cost of obtaining the right-of-way and constructing the outlet.
Subd. 12. Completion. The engineer shall prepare the detailed survey and complete the detailed survey report, in duplicate, as specified in this section.
1990 c 391 art 5 s 45; 2014 c 164 s 11
Structure Minnesota Statutes
Section 103E.005 — Definitions.
Section 103E.011 — Drainage Authority Powers.
Section 103E.015 — Considerations Before Drainage Work Is Done.
Section 103E.021 — Planting Ditches With Perennial Vegetation.
Section 103E.031 — Connection With Drains In Adjoining States.
Section 103E.035 — Defective Notice.
Section 103E.041 — Personal Service In Lieu Of Other Methods Of Notice.
Section 103E.043 — Informal Meetings.
Section 103E.045 — Failure To Attend Hearings; Drainage Authority.
Section 103E.051 — Defective Proceedings.
Section 103E.055 — Reimbursing Cost Of Former Surveys When Used Later.
Section 103E.061 — Right Of Entry.
Section 103E.065 — Drainage Inspectors.
Section 103E.067 — Ditch Buffer Strip; Annual Reporting.
Section 103E.071 — County Attorney.
Section 103E.075 — Obstructing Drainage System.
Section 103E.081 — Crimes Related To Drainage Systems; Penalties.
Section 103E.085 — Enforcement.
Section 103E.095 — Appeal From Orders Dismissing Or Establishing Drainage Systems.
Section 103E.097 — Attorney Fees On Appeal.
Section 103E.101 — Drainage Proceeding And Construction Records.
Section 103E.105 — Advice About Drainage Questions.
Section 103E.111 — Field Surveys And Investigations By Director.
Section 103E.115 — Hydrological And Drainage Information.
Section 103E.121 — Drain Tile; Manufacturing Studies.
Section 103E.212 — New Drainage System Projects.
Section 103E.215 — Improving Drainage Systems.
Section 103E.221 — Improving Outlets.
Section 103E.227 — Impounding, Rerouting, And Diverting Drainage System Waters.
Section 103E.231 — Dismissing Or Delaying Proceedings; Petitioners.
Section 103E.235 — Drainage System In Two Or More Counties.
Section 103E.238 — County Attorney Review Of Petition And Bond.
Section 103E.245 — Preliminary Survey And Preliminary Survey Report.
Section 103E.251 — Filing Preliminary Survey Report.
Section 103E.255 — Commissioner's Preliminary Advisory Report.
Section 103E.261 — Preliminary Hearing.
Section 103E.265 — Order For Detailed Survey And Survey Report.
Section 103E.271 — Detailed Survey.
Section 103E.275 — Engineer's Variance From Drainage Authority Order.
Section 103E.281 — Soil Survey.
Section 103E.285 — Detailed Survey Report.
Section 103E.291 — Filing Detailed Survey Report.
Section 103E.295 — Revising Engineer's Detailed Survey Report After Acceptance.
Section 103E.301 — Commissioner's Final Advisory Report.
Section 103E.305 — Viewers' Appointment And Qualification.
Section 103E.311 — Viewer Duties.
Section 103E.315 — Assessing Drainage Benefits And Damages.
Section 103E.321 — Viewers' Report.
Section 103E.323 — Property Owners' Report.
Section 103E.325 — Final Hearing Notice.
Section 103E.331 — Jurisdiction Of Property By Drainage Authority.
Section 103E.335 — Proceedings At Final Hearing.
Section 103E.341 — Drainage Authority Final Order.
Section 103E.345 — Apportioning Cost For Joint County Drainage Systems.
Section 103E.351 — Redetermining Benefits And Damages.
Section 103E.401 — Use Of Drainage System As Outlet.
Section 103E.405 — Outlets In Adjoining States.
Section 103E.411 — Drainage System As Outlet For Municipality.
Section 103E.501 — Contract And Bond.
Section 103E.505 — Awarding Construction Contract.
Section 103E.511 — Contract Not Awarded; Excessive Bids Or Costs.
Section 103E.515 — Damages; Payment.
Section 103E.521 — Construction Supervision.
Section 103E.525 — Constructing And Maintaining Bridges And Culverts.
Section 103E.526 — Constructing Road Instead Of Bridge Or Culvert.
Section 103E.53 — Rules To Standardize Forms.
Section 103E.531 — Inspecting Drainage Construction; Partial Payments.
Section 103E.535 — Partial Payment Of Retained Contract Amounts.
Section 103E.541 — Extending Time On Contracts.
Section 103E.545 — Reducing Contractor's Bond.
Section 103E.551 — Contractor Default.
Section 103E.555 — Accepting Contract.
Section 103E.601 — Drainage Lien Statement.
Section 103E.605 — Effect Of Filed Drainage Lien.
Section 103E.611 — Paying Drainage Liens And Interest.
Section 103E.615 — Enforcing Assessments.
Section 103E.621 — Satisfying Liens.
Section 103E.625 — Subdivision By Platting; Liens Apportioned.
Section 103E.631 — Apportioning Liens.
Section 103E.635 — Drainage Bond Issues.
Section 103E.641 — Drainage Funding Bonds.
Section 103E.645 — Allowance And Payment Of Fees And Expenses.
Section 103E.651 — Drainage System Account.
Section 103E.655 — Paying Drainage System Costs.
Section 103E.661 — Examining And Establishing Drainage System Accounts; State Auditor.
Section 103E.705 — Repair Procedure.
Section 103E.711 — Cost Apportionment For Joint County Drainage Systems.
Section 103E.715 — Repair By Petition.
Section 103E.721 — Replacement And Hydraulic Capacity Of Bridges And Culverts.
Section 103E.725 — Cost Of Repair.
Section 103E.728 — Apportioning Repair Costs.
Section 103E.729 — Apportioning Repair Costs; Alternative Option.
Section 103E.731 — Assessment; Bonds.
Section 103E.735 — Drainage Systems; Repair Fund.
Section 103E.741 — Property Not Assessed Benefits; Hearing.
Section 103E.745 — Cost Of Repair Exceeding Benefits In Anoka County.
Section 103E.801 — Consolidating Or Dividing Drainage Systems.
Section 103E.805 — Removing Property From Drainage System.
Section 103E.806 — Partial Abandonment Of Drainage System.
Section 103E.811 — Abandoning Drainage System.
Section 103E.812 — Transfer Of All Or Part Of Drainage System.