Section 62. The governor and the commissioner of capital asset management and maintenance in their long range capital facilities development plans and capital budget requests and the secretaries of the various executive offices in their review and recommendations with regard to such plans and requests may include among them plans and requests for 1 or more contingency, or other lump-sum or reserve accounts, including but not limited to planning, design and construction contingency, preventive maintenance, emergency repair, energy conservation, life-safety, and architectural barrier funds or accounts. Each shall include in their plans and request recommendations as to the purpose of such funds or accounts and the priorities and procedures for allocating the monies kept therein.
The commissioner of capital asset management and maintenance shall forthwith establish priorities and procedures for allocating such funds in conformity with the terms of the appropriation authorizing them and legislative intent in regard to long range capital facilities development plans. The commissioner shall forthwith submit copies of the priorities and procedures so established to the secretary of administration and finance and to the house and senate committees on ways and means.
Unless otherwise provided for in the appropriation authorizing such funds or accounts or other applicable law and in conformity therewith and the priorities and procedures established by the commissioner of capital asset management and maintenance, the monies kept therein shall not be allocated unless and until:
(a) the using agency, whether or not it is the agency requesting the funds for the proposed project, certifies in writing to the commissioner of capital asset management and maintenance that the project corresponds to the current needs of the using agency, including its current long range capital facilities development plan;
(b) the commissioner requests that 1 or more of the directors of the office of programming, office of project management, or the office of facilities management review the project proposal, and the director or directors certify in writing to the commissioner of capital asset management and maintenance that the project proposal reflects the agency's needs as stated, that it provides an accurate estimate of the project requirements, cost and schedule, and that the project can be accomplished within the limits of the funds requested;
(c) The commissioner of capital asset management and maintenance certifies in writing to the secretary of administration and finance and to the house and senate committees on ways and means that the project proposal has been evaluated in conformity with the terms of the appropriation or authorization of the fund or account and the priorities and procedures promulgated by him pursuant thereto and approves the allocation.
The commissioner of capital asset management and maintenance shall, upon his certification, file copies of the project proposal and other supporting documents, his certification and those of the director or directors whose review is requested and the agency requesting such funds with the secretary of administration and finance and with the house and senate committees on ways and means.
If either the director or directors whose review is requested or the commissioner of capital asset management and maintenance should fail to give the aforementioned certifications or approvals, the commissioner shall forthwith send notice of his decision and the reasons therefor to the secretary of administration and finance and to the house and senate committees on ways and means.
The commissioner of capital asset management and maintenance shall by February 15 of each year prepare and submit to the secretary of administration and finance and to the general court a report containing separate sections summarizing the disposition and the status of the funds or accounts and descriptions of all projects for which monies from such fund have been allocated.
Structure Massachusetts General Laws
Part I - Administration of the Government
Title II - Executive and Administrative Officers of the Commonwealth
Chapter 7c - Capital Asset Management and Maintenance
Section 1 - Definitions Applicable to This Chapter and Chapter 29
Section 3 - Coordination of Capital Facility Project Plans and Programs
Section 7 - Court Facilities Acquisition, Control, Disposition, etc.; Director of Court Facilities
Section 10 - Advisory Council on Capital Asset Management and Maintenance
Section 11 - Office of Programming; Director of Programming
Section 12 - Duties and Responsibilities of Director of Programming
Section 13 - Office of Project Management; Director of Project Management
Section 14 - Duties and Responsibilities of Director of Project Management
Section 17 - Change Orders or Other Contract Modifications
Section 18 - Request for Change Order; Approval or Disapproval; Appeal
Section 21 - General Principles Applicable to Equitable Adjustments
Section 22 - Resident Engineers
Section 23 - Acceptance of Federal Funds or Assistance
Section 25 - Control of Supervision of Projects by the Director of Facilities Management
Section 28 - Duties and Responsibilities of Director of Facilities Management
Section 30 - Evaluation of Energy Consumption of Buildings and Their Major Energy Using Systems
Section 34 - Procedure for the Disposition of Real Property by Sale, Rental or Otherwise
Section 35a - Termination of Lease for Nonappropriation or Nonallotment; Renegotiation of Lease
Section 40 - Rules and Regulations for the Acquisition, Utilization and Disposition of Real Property
Section 42 - Reporting of Lease or Any Agreement for Tenancy at Will or Other Rental of Space
Section 45 - Designer Selection Board
Section 46 - Jurisdiction of Designer Selection Board; Exemptions From Jurisdiction
Section 47 - Public Notice Requirements for Contracts for Design Services
Section 52 - Appointment of Designer or Interior Designer for Continued or Extended Services
Section 53 - Expedited Selection Procedures Upon Declaration of Emergency Situation
Section 54 - Adoption of Written Selection Procedure Prior to Award of Contract for Design Services
Section 57 - Adoption of Procedures and Regulations to Implement Secs. 44 to 58
Section 59 - Study or Program Required Prior to Contracting for Design or Construction Services
Section 62 - Contingency Funds or Accounts
Section 63 - Capital Facility Planning Fund
Section 64 - Long-Range Capital Facilities Development Plans
Section 65 - Required Content of Long-Range Capital Facilities Development Plans
Section 69 - Design and Construction Contingency Reserve Account
Section 70 - Emergency Repair Reserve Account
Section 72 - Annual Reporting by Commissioner to Governor and General Court