Section 15. The contract which the director shall make with the designer appointed under the preceding section shall provide, among other appropriate terms, that the designer shall, in consultation with the using agency and subject to that agency's approval, prepare plans and specifications for the building project for submission to said director for his approval and shall use standard contract documents and specifications which said director shall have prepared with the approval of the commissioner and made available within the office.
No obligation shall be incurred or payment made for preparation of any plans or specifications for any building project without the prior approval of the commissioner; and in the case of a building project undertaken on behalf of the commonwealth, no plans or specifications shall be prepared until a special appropriation shall have been made therefor or for the project or until federal funds or assistance shall have been made available therefor. No other obligation shall be incurred or payment made in connection with any building project until such obligation or payment shall have been approved in accordance with sections 1 to 40, inclusive, and section 60 and section 11 of chapter 35.
Schematic, preliminary and working plans and specifications for each building project shall, following initial submission to the using agency for comment, be submitted by the designer to the director for his approval. In reviewing such plans and specifications, the duty of the director shall be to see that they are clear and complete and permit execution of the building project (a) within the appropriation or authorization for the project or within project cost limits specified by the appropriation or authorization and (b) in accordance with (i) any study or program prepared in accordance with section 59 or (ii) any other pre-design document which must be prepared in accordance with any other statute, appropriation or authorization or administrative directive consistent therewith. When a phased construction technique is approved by the legislature, the director shall approve working plans and specifications at appropriate stages of the project.
Following final approval of such plans and specifications, the director shall advertise in the central register published by the secretary of state pursuant to section 20 of chapter 9 and in such other publications as the commissioner shall direct, for applications to bid on or proposals for the performance of the work on the project; except that the commissioner may direct that the purchase of any materials, original equipment or original furnishings for the project shall be made under sections 22 to 26, inclusive, of chapter 7. Subject to the prior approval of the commissioner and the applicable provisions of sections 44A to 44M, inclusive, of chapter 149 the director shall award the contract or contracts for such work to the lowest responsible and eligible bidder; but no such contract on behalf of the commonwealth shall be awarded by him for a sum in excess of the amount which the comptroller shall certify to be available therefor. If the director shall knowingly award a contract in violation of this section, the director may be removed from office by the governor.
The director shall be responsible for accepting or rejecting each project upon its completion and for directing final payment for work done thereon; provided, however, that if upon inspection of any project for acceptance the director shall find that the plans, specifications, contracts or change orders for the project shall not have been fully complied with, the director shall, until such compliance has been effected or adjustment satisfactory to him has been made, refuse to accept the project and direct such payment.
Upon acceptance of the project, the director shall release the same to the using agency, unless the using agency objects to said release, in which case the director shall work with the using agency to remove the causes of the objection. The director shall not refuse to accept the project from the contractor and shall not refuse to direct final payment to the contractor because of the using agency's objections if the director has determined that the contractor has completed the project in accordance with contract.
Structure Massachusetts General Laws
Part I - Administration of the Government
Title II - Executive and Administrative Officers of the Commonwealth
Chapter 7c - Capital Asset Management and Maintenance
Section 1 - Definitions Applicable to This Chapter and Chapter 29
Section 3 - Coordination of Capital Facility Project Plans and Programs
Section 7 - Court Facilities Acquisition, Control, Disposition, etc.; Director of Court Facilities
Section 10 - Advisory Council on Capital Asset Management and Maintenance
Section 11 - Office of Programming; Director of Programming
Section 12 - Duties and Responsibilities of Director of Programming
Section 13 - Office of Project Management; Director of Project Management
Section 14 - Duties and Responsibilities of Director of Project Management
Section 17 - Change Orders or Other Contract Modifications
Section 18 - Request for Change Order; Approval or Disapproval; Appeal
Section 21 - General Principles Applicable to Equitable Adjustments
Section 22 - Resident Engineers
Section 23 - Acceptance of Federal Funds or Assistance
Section 25 - Control of Supervision of Projects by the Director of Facilities Management
Section 28 - Duties and Responsibilities of Director of Facilities Management
Section 30 - Evaluation of Energy Consumption of Buildings and Their Major Energy Using Systems
Section 34 - Procedure for the Disposition of Real Property by Sale, Rental or Otherwise
Section 35a - Termination of Lease for Nonappropriation or Nonallotment; Renegotiation of Lease
Section 40 - Rules and Regulations for the Acquisition, Utilization and Disposition of Real Property
Section 42 - Reporting of Lease or Any Agreement for Tenancy at Will or Other Rental of Space
Section 45 - Designer Selection Board
Section 46 - Jurisdiction of Designer Selection Board; Exemptions From Jurisdiction
Section 47 - Public Notice Requirements for Contracts for Design Services
Section 52 - Appointment of Designer or Interior Designer for Continued or Extended Services
Section 53 - Expedited Selection Procedures Upon Declaration of Emergency Situation
Section 54 - Adoption of Written Selection Procedure Prior to Award of Contract for Design Services
Section 57 - Adoption of Procedures and Regulations to Implement Secs. 44 to 58
Section 59 - Study or Program Required Prior to Contracting for Design or Construction Services
Section 62 - Contingency Funds or Accounts
Section 63 - Capital Facility Planning Fund
Section 64 - Long-Range Capital Facilities Development Plans
Section 65 - Required Content of Long-Range Capital Facilities Development Plans
Section 69 - Design and Construction Contingency Reserve Account
Section 70 - Emergency Repair Reserve Account
Section 72 - Annual Reporting by Commissioner to Governor and General Court