(a) This section applies to the installation of pollution control equipment or a change in the method of operation at a generating station that a person performs in order to comply with Phase II pollution control requirements of the federal Clean Air Act.
(b) Any person that performs an installation or change in operation under subsection (a) of this section shall obtain prior review and approval of the Commission in accordance with:
(1) §§ 7-203, 7-207, and 7-208 of this subtitle; and
(2) the procedures set forth in § 7-205 of this subtitle and § 2-405 of the Environment Article.
(c) In order to meet compliance dates established under Title 2, Subtitle 10 of the Environment Article or the federal Clean Air Act, a Commission review and approval, or processing of an application for a certificate of public convenience and necessity under § 7-207 of this subtitle, shall be expedited and take precedence over other review and approval by the Commission if the review and approval or certificate of public convenience and necessity is required:
(1) for pollution control equipment or a change in the method of operation at a generating station; and
(2) for compliance with:
(i) Title 2, Subtitle 10 of the Environment Article;
(ii) regulations adopted by the Department of the Environment under Title 2, Subtitle 10 of the Environment Article; or
(iii) the federal Clean Air Act.
Structure Maryland Statutes
Division I - Public Services and Utilities
Title 7 - Gas, Electric, and Water Companies
Subtitle 2 - Electric Generation Facility Planning
Section 7-201 - Electric Companies -- Long-Range Plans
Section 7-202 - Electric Companies -- Power Plant Sites
Section 7-203 - Electric Companies -- Environmental Surcharge
Section 7-204 - Electric Companies -- Lines and Transmission Devices
Section 7-205 - Electric Companies -- Modification of Power Plant
Section 7-206 - Electric Companies -- Clean Air Act Modifications
Section 7-207 - Generating Stations or Transmission Lines -- General Certification Procedure
Section 7-207.2 - Solar Voltaic Systems
Section 7-209 - Alternatives to Construction of Transmission Lines
Section 7-210 - Municipal Electric Plants
Section 7-211 - Energy Efficiency Programs
Section 7-213 - Service Quality and Reliability
Section 7-213.1 - Service Restoration -- Special Medical Needs Facilities
Section 7-214 - Contact Voltage Risk Zones -- Surveys and Mitigation
Section 7-215 - Sale or Transfer of Solar Electric Generating Facility