Maryland Statutes
Subtitle 2 - Electric Generation Facility Planning
Section 7-205 - Electric Companies -- Modification of Power Plant

(a)    (1)    In this section, “modification” means a physical alteration of, replacement of, or other change to the facilities at a power plant, or a change in the fuel used by the plant, that could result in a change of the air emissions from the plant or from a generating unit of the plant.
        (2)    “Modification” does not include:
            (i)    routine maintenance or repairs of the facilities of a power plant; or
            (ii)    a change that the Commission determines will not result in an increase in air emissions from the plant or from a generating unit of the plant.
    (b)    Subject to subsections (c) through (e) of this section, a person may not commence a modification without the prior approval of the Commission under this title.
    (c)    (1)    Unless the Commission orders otherwise, an application for a modification to a power plant shall be filed with the Commission at least 180 days before the date on which the modification is to commence.
        (2)    The applicant for the modification shall submit to the Commission and to the Department of the Environment all information relating to the modification, including:
            (i)    detailed plans and specifications; and
            (ii)    the impact of the modification on air quality.
    (d)    The Commission shall render its decision within 150 days after the day the application is filed.
    (e)    Notwithstanding the provisions of this section, a modification to a power plant that involves the short-term inability to obtain the type of fuel normally used by the plant is subject to Title 2, Subtitle 5 of the Environment Article.

Structure Maryland Statutes

Maryland Statutes

Public Utilities

Division I - Public Services and Utilities

Title 7 - Gas, Electric, and Water Companies

Subtitle 2 - Electric Generation Facility Planning

Section 7-201 - Electric Companies -- Long-Range Plans

Section 7-202 - Electric Companies -- Power Plant Sites

Section 7-203 - Electric Companies -- Environmental Surcharge

Section 7-204 - Electric Companies -- Lines and Transmission Devices

Section 7-205 - Electric Companies -- Modification of Power Plant

Section 7-206 - Electric Companies -- Clean Air Act Modifications

Section 7-207 - Generating Stations or Transmission Lines -- General Certification Procedure

Section 7-207.1 - Generating Stations or Transmission Lines -- On-Site Generated Electricity; Approval Process

Section 7-207.2 - Solar Voltaic Systems

Section 7-208 - Generating Stations or Transmission Lines -- Joint Construction of Station and Associated Lines

Section 7-209 - Alternatives to Construction of Transmission Lines

Section 7-210 - Municipal Electric Plants

Section 7-211 - Energy Efficiency Programs

Section 7-212 - Regulations Governing Purchase of Liquid-Immersed Distribution Transformers; Life-Cycle Cost Methodology for Transformers Used for Installation Outside State

Section 7-213 - Service Quality and Reliability

Section 7-213.1 - Service Restoration -- Special Medical Needs Facilities

Section 7-214 - Contact Voltage Risk Zones -- Surveys and Mitigation

Section 7-215 - Sale or Transfer of Solar Electric Generating Facility

Section 7-216 - Energy Storage Pilot Program