Iowa Code
Chapter 572 - MECHANIC’S LIEN
Section 572.33 - Requirement of notification for commercial construction.

572.33 Requirement of notification for commercial construction.
1. The notification requirements in this section apply only to commercial construction.
2. A person furnishing labor or materials to a subcontractor shall not be entitled to a lien under this chapter unless the person furnishing labor or materials does all of the following:
a. Notifies the general contractor or owner-builder in writing with a one-time notice containing the name, mailing address, and telephone number of the person furnishing the labor or materials, and the name of the subcontractor to whom the labor or materials were furnished, within thirty days of first furnishing labor or materials for which a lien claim may be made. Additional labor or materials furnished by the same person to the same subcontractor for use in the same construction project shall be covered by this notice.
b. Supports the lien claim with a certified statement that the general contractor or owner-builder was notified in writing with a one-time notice containing the name, mailing address, and telephone number of the person furnishing the labor or materials, and the name of the subcontractor to whom the labor or materials were furnished, within thirty days after the labor or materials were first furnished, pursuant to paragraph “a”.
3. Notwithstanding other provisions of this chapter, a general contractor or owner-builder shall not be prohibited from requesting information from a subcontractor or a person furnishing labor or materials to a subcontractor regarding payments made or payments to be made to a person furnishing labor or materials to a subcontractor.
84 Acts, ch 1248, §1; 98 Acts, ch 1142, §4; 99 Acts, ch 104, §1; 2007 Acts, ch 83, §18; 2012 Acts, ch 1105, §23, 27, 28

Structure Iowa Code

Iowa Code

Title XIV - PROPERTY

Chapter 572 - MECHANIC’S LIEN

Section 572.1 - Definitions and rules of construction.

Section 572.2 - Persons entitled to lien.

Section 572.3 - Collateral security before completion of work.

Section 572.4 - Security after completion of work.

Section 572.5 - Extent of lien.

Section 572.6 - In case of leasehold interest.

Section 572.7 - In case of internal improvement.

Section 572.8 - Perfection of lien.

Section 572.9 - Time of lien posting.

Section 572.10 - Perfecting lien after lapse of ninety days.

Section 572.11 - Extent of lien posted after ninety days.

Section 572.12 - Time of filing against railway.

Section 572.13 - General contractor — owner notice — residential construction.

Section 572.13A - Notice of commencement of work — general contractor — owner-builder.

Section 572.13B - Preliminary notice — subcontractor — residential construction.

Section 572.14 - Liability to subcontractor after payment to general contractor or owner-builder.

Section 572.15 - Discharge of mechanic’s lien — bond.

Section 572.16 - Rule of construction.

Section 572.17 - Priority of mechanics’ liens between mechanics.

Section 572.18 - Priority over other liens.

Section 572.19 - Priority over garnishments of the owner.

Section 572.20 - Priority as to buildings over prior liens upon land.

Section 572.21 - Foreclosure of mechanic’s lien when lien on land.

Section 572.22 - Record of claim.

Section 572.23 - Acknowledgment of satisfaction of claim.

Section 572.24 - Time of bringing action — court.

Section 572.25 - Place of bringing action.

Section 572.26 - Kinds of action — amendment.

Section 572.27 - Limitation on action.

Section 572.28 - Demand for bringing suit.

Section 572.29 - Assignment of lien.

Section 572.30 - Action by subcontractor or owner against general contractor or owner-builder.

Section 572.31 - Cooperative and condominium housing.

Section 572.32 - Attorney fees — remedies.

Section 572.33 - Requirement of notification for commercial construction.

Section 572.33A - Liability of owner to general contractor — commercial construction.

Section 572.34 - Mechanics’ notice and lien registry.