Sec. 24. (a) As used in this section, "contractor" includes a subcontractor of a contractor.
(b) IC 4-13-18, regarding drug testing of employees of public works contractors, applies to a public works contract:
(1) if the estimated cost of the public works contract is at least one hundred fifty thousand dollars ($150,000); and
(2) that is awarded under this chapter after June 30, 2016.
(c) An employee drug testing program submitted to the board under this section must have been effective and applied at the time of the solicitation for bids.
(d) A contractor who has previously filed a copy of the contractor's employee drug testing program with the board in the current calendar year or within the previous two (2) calendar years satisfies the requirement for submitting an employee drug testing program, unless the employee drug testing program has been revised.
As added by P.L.252-2015, SEC.44. Amended by P.L.213-2015, SEC.264; P.L.72-2018, SEC.17.
Structure Indiana Code
Chapter 12. Public Work Projects
36-1-12-0.1. Application of Certain Amendments to Chapter
36-1-12-1. Application of Chapter; Alternatives to Chapter
36-1-12-3. Public Work Projects
36-1-12-4. Bidding Procedures for Projects Costing More Than Certain Amounts
36-1-12-4.5. Bond or Certified Check; Filing by Bidders
36-1-12-4.7. Procedures for Inviting Quotes; Applicable Dollar Amounts
36-1-12-4.9. Alternate Procedures for Projects Costing Less Than $150,000
36-1-12-5. Procedures for Inviting Quotes; Applicable Dollar Amount
36-1-12-7. Public Buildings; Approval of Plans and Specifications by Licensed Architect or Engineer
36-1-12-9. Emergencies; Contracts by Invitation
36-1-12-10. Plans and Specifications; Approval by Various Agencies
36-1-12-11. Completion of Project; Procedure
36-1-12-12. Final Payment; Requirements; Claims by Subcontractors, Laborers, or Suppliers; Disputes
36-1-12-13. Contract Provision for Payment of Subcontractors, Laborers, or Suppliers
36-1-12-15. Contractor Requirements; Antidiscrimination Provisions
36-1-12-16. Necessity of Compliance With Chapter
36-1-12-18. Change or Alteration of Specifications; Change Orders
36-1-12-20. Trench Safety Systems; Cost Recovery
36-1-12-21. Plumbing Installations; Proof of Licensure
36-1-12-23. Application of Ic 5-22-16.5 to Award of Contracts Under Article