Sec. 18. (a) If, in the course of the construction, reconstruction, or repair of a public work project, it becomes necessary to change or alter the original specifications, a change order may be issued to add, delete, or change an item or items in the original contract. The change order becomes an addendum to the contract and must be approved and signed by the board and the contractor.
(b) If a licensed architect or engineer is assigned to the public work project, the change order must be prepared by that person.
(c) A change order may not be issued before commencement of the actual construction, reconstruction, or repairs except in the case of an emergency. In that case, the board must make a declaration, and the board's minutes must show the nature of the emergency.
(d) The total of all change orders issued that increase the scope of the project may not exceed twenty percent (20%) of the amount of the original contract. A change order issued as a result of circumstances that could not have been reasonably foreseen does not increase the scope of the project.
(e) All change orders must be directly related to the original public work project.
(f) If additional units of materials included in the original contract are needed, the cost of these units in the change order must be the same as those shown in the original contract.
As added by P.L.329-1985, SEC.24.
Structure Indiana Code
Chapter 12. Public Work Projects
36-1-12-0.1. Application of Certain Amendments to Chapter
36-1-12-1. Application of Chapter; Alternatives to Chapter
36-1-12-3. Public Work Projects
36-1-12-4. Bidding Procedures for Projects Costing More Than Certain Amounts
36-1-12-4.5. Bond or Certified Check; Filing by Bidders
36-1-12-4.7. Procedures for Inviting Quotes; Applicable Dollar Amounts
36-1-12-4.9. Alternate Procedures for Projects Costing Less Than $150,000
36-1-12-5. Procedures for Inviting Quotes; Applicable Dollar Amount
36-1-12-7. Public Buildings; Approval of Plans and Specifications by Licensed Architect or Engineer
36-1-12-9. Emergencies; Contracts by Invitation
36-1-12-10. Plans and Specifications; Approval by Various Agencies
36-1-12-11. Completion of Project; Procedure
36-1-12-12. Final Payment; Requirements; Claims by Subcontractors, Laborers, or Suppliers; Disputes
36-1-12-13. Contract Provision for Payment of Subcontractors, Laborers, or Suppliers
36-1-12-15. Contractor Requirements; Antidiscrimination Provisions
36-1-12-16. Necessity of Compliance With Chapter
36-1-12-18. Change or Alteration of Specifications; Change Orders
36-1-12-20. Trench Safety Systems; Cost Recovery
36-1-12-21. Plumbing Installations; Proof of Licensure
36-1-12-23. Application of Ic 5-22-16.5 to Award of Contracts Under Article