In inviting bids, the awarding authority shall reserve the right to reject any or all such general bids, if (1) the awarding authority determines that the general bidder or bidders involved are not competent to perform the work as specified, based on objective criteria established for making such determinations, including past performance and financial responsibility, (2) the low bid price exceeds the amount of money available for the project, (3) the awarding authority determines that the project shall not go forward or (4) the awarding authority finds cause to reject such bids. If the awarding authority rejects any or all bids pursuant to this section, it shall notify each affected bidder, in writing, of the reasons for such rejection.
(P.A. 73-528, S. 4, 12; P.A. 74-246, S. 4, 11; P.A. 82-447, S. 4; P.A. 87-254.)
History: P.A. 74-246 clarified circumstances under which bids may be rejected; P.A. 82-447 amended section to include past performance and financial responsibility among objective criteria and to eliminate references to sub-bids; P.A. 87-254 divided section into Subdivs. and added Subdiv. (4), re a finding of cause to reject bids, and the provision re notice to affected bidders of reasons for rejection; Sec. 4-137d transferred to Sec. 4b-94 in 1989.
Annotation to former section 4-137d:
Cited. 191 C. 497.
Structure Connecticut General Statutes
Title 4b - State Real Property
Chapter 60 - Construction and Alterations of State Buildings
Section 4b-51a. - Recycled content requirements for construction materials.
Section 4b-58. (Formerly Sec. 4-134d). - Contracting for consultant services.
Section 4b-59. (Formerly Sec. 4-134e). - Commissioner to adopt regulations.
Section 4b-60. - State Commission on Capitol Preservation and Restoration.
Section 4b-61. (Formerly Sec. 4-24m). - Contracting for design professional services.
Section 4b-62. (Formerly Sec. 4-135). - Trusts for erecting and maintaining memorials.
Section 4b-63. (Formerly Sec. 4-36b). - Demolition of state buildings. Notice to municipalities.
Section 4b-65. - Buildings adjacent to Capitol.
Section 4b-66a. - Connecticut Capitol Center Commission: Membership, duties.
Section 4b-68. (Formerly Sec. 4-24e). - Amendment of master plan.
Section 4b-73. (Formerly Sec. 4-24j). - Relocation of displaced persons.
Section 4b-75. - Status report on emergency correctional facility projects.
Section 4b-76. - Public or special act authorizations for acquisition of real property.
Section 4b-93. (Formerly Sec. 4-137c). - Contract specifications; subtrades, subcontracts.
Section 4b-94. (Formerly Sec. 4-137d). - Rejection of bids.
Section 4b-95a. - Listing of general bidder as a subcontractor on bid form.
Section 4b-97. (Formerly Sec. 4-126c). - Arbitration of public works contracts.
Section 4b-100. - Regulations.
Section 4b-103. - Construction manager at-risk project delivery contracts.