Section 4b-92. (Formerly Sec. 4-137b). - “Lowest responsible and qualified bidder” defined. Bid bonds, certified checks, when forfeited.

As used in this chapter and except as otherwise provided, “lowest responsible and qualified bidder” means the bidder who is prequalified pursuant to section 4a-100, and whose bid is the lowest of those bidders possessing the skill, ability and integrity necessary to faithful performance of the work based on objective criteria considering past performance and information contained in the update statement submitted pursuant to section 4b-91. Essential information in regard to such qualifications shall be submitted with the bid in such form as the awarding authority may require by specification in the bid documents and on the bid form. Every general bid shall be accompanied by a bid bond or a certified check in an amount which shall be ten per cent of the bid, provided no such bid bond or certified check shall be required in relation to any general bid in which the total estimated cost of labor and materials under the contract with respect to which such general bid is submitted is less than fifty thousand dollars. Failure to execute a contract awarded as specified and bid shall result in the forfeiture of such bid bond or certified check. In considering past performance the awarding authority shall evaluate the skill, ability and integrity of bidders in terms of the bidders' fulfillment of contract obligations and of the bidders' experience or lack of experience with projects of the nature and scope of the project for which the bids are submitted.

(P.A. 73-528, S. 2, 12; P.A. 74-246, S. 2, 11; P.A. 79-490; P.A. 82-358, S. 8, 10; 82-447, S. 2; P.A. 99-75, S. 9; P.A. 03-215, S. 2; P.A. 07-202, S. 8; P.A. 14-122, S. 68; P.A. 21-198, S. 4.)
History: P.A. 74-246 deleted provision that bidder certify labor to be employed can work harmoniously with others, required objective criteria for judging bidders' qualifications and raised bid bond from 5% to 10% of bid; P.A. 79-490 exempted sub-bidders bidding less than $10,000 in labor and materials costs from bid bond requirement; P.A. 82-358 provided that bid bond or certified check is not required for general bids with estimated cost of labor and materials of less than $10,000 and raised estimated cost relative to sub-bids from $10,000 to $20,000; P.A. 82-447 amended section to eliminate all reference to sub-bidding process and to specify factors for evaluation in considering a contractor's past performance; Sec. 4-137b transferred to Sec. 4b-92 in 1989; P.A. 99-75 substituted $50,000 for $10,000; P.A. 03-215 redefined “lowest responsible and qualified bidder” and substituted “nature and scope” for “size” re projects, effective October 1, 2004; P.A. 07-202 made a technical change, effective July 10, 2007; P.A. 14-122 made technical changes; P.A. 21-198 replaced “update bid statement” with “update statement”, effective July 1, 2021.
Annotation to former section 4-137b:
Cited. 191 C. 497.

Structure Connecticut General Statutes

Connecticut General Statutes

Title 4b - State Real Property

Chapter 60 - Construction and Alterations of State Buildings

Section 4b-51. (Formerly Sec. 4-131). - Alterations, repairs or additions to real assets. Selection of consultants for certain projects.

Section 4b-51a. - Recycled content requirements for construction materials.

Section 4b-52. (Formerly Sec. 4-132). - Repairs or changes to state premises. Exception for emergency conditions. Renegotiation of leases.

Section 4b-53. (Formerly Sec. 4-131a). - Allocation of bond proceeds for art work in construction or remodeling of state buildings. State building works of art account. Maintenance account. Regulations.

Section 4b-54. (Formerly Sec. 4-134). - Designs of public structures to be submitted to Commissioner of Administrative Services. Work of art for Capitol to be submitted to Legislative Management Committee.

Section 4b-55. (Formerly Sec. 4-134a). - State Construction Services Selection Panel; Connecticut Health and Education Facilities Authority Construction Services Panel. Definitions.

Section 4b-55a. - Contracting for environmental evaluations for priority higher education facility projects.

Section 4b-56. (Formerly Sec. 4-134b). - State construction services selection panels, and Connecticut Health and Education Facilities Authority construction services panels, established. Membership.

Section 4b-57. (Formerly Sec. 4-134c). - Consultant services. Invitation of responses. Consideration by selection panel.

Section 4b-58. (Formerly Sec. 4-134d). - Contracting for consultant services.

Section 4b-59. (Formerly Sec. 4-134e). - Commissioner to adopt regulations.

Section 4b-60. - State Commission on Capitol Preservation and Restoration.

Section 4b-61. (Formerly Sec. 4-24m). - Contracting for design professional services.

Section 4b-62. (Formerly Sec. 4-135). - Trusts for erecting and maintaining memorials.

Section 4b-63. (Formerly Sec. 4-36b). - Demolition of state buildings. Notice to municipalities.

Section 4b-64. (Formerly Sec. 4-36c). - Notice of intent to dispose of, demolish or transfer certain structures to be given to Department of Economic and Community Development and affected municipality.

Section 4b-65. - Buildings adjacent to Capitol.

Section 4b-66. (Formerly Sec. 4-24c). - Connecticut Capitol Center. Master plan for development. Exceptions. Review of plan by Connecticut Capitol Center Commission. Reports.

Section 4b-66a. - Connecticut Capitol Center Commission: Membership, duties.

Section 4b-67. (Formerly Sec. 4-24d). - Consultation with the Joint Committee on Legislative Management and other state agencies.

Section 4b-68. (Formerly Sec. 4-24e). - Amendment of master plan.

Section 4b-69. (Formerly Sec. 4-24f). - Development of Connecticut Capitol Center except Legislative Office Building: Approval of preliminary plans.

Section 4b-70. (Formerly Sec. 4-24g). - Commissioner of Administrative Services to review construction.

Section 4b-71. (Formerly Sec. 4-24h). - Approvals prerequisite to acquisition or development of property within Capitol Center District.

Section 4b-72. (Formerly Sec. 4-24i). - Acquisition of property within district by Commissioner of Administrative Services.

Section 4b-73. (Formerly Sec. 4-24j). - Relocation of displaced persons.

Section 4b-74. (Formerly Sec. 4-24k). - Approval of building or zoning permits for property within district.

Section 4b-75. - Status report on emergency correctional facility projects.

Section 4b-76. - Public or special act authorizations for acquisition of real property.

Section 4b-77. - Installation of level two electric vehicle charging stations at state facility. Inclusion of electric vehicle charging infrastructure at certain buildings in municipalities.

Section 4b-91. (Formerly Sec. 4-137a). - Process for bidding for public works contracts. Prequalification requirements. Exceptions.

Section 4b-92. (Formerly Sec. 4-137b). - “Lowest responsible and qualified bidder” defined. Bid bonds, certified checks, when forfeited.

Section 4b-93. (Formerly Sec. 4-137c). - Contract specifications; subtrades, subcontracts.

Section 4b-94. (Formerly Sec. 4-137d). - Rejection of bids.

Section 4b-95. (Formerly Sec. 4-137e). - General bid form requirements. Selection by awarding authority. Subcontractors.

Section 4b-95a. - Listing of general bidder as a subcontractor on bid form.

Section 4b-96. (Formerly Sec. 4-137g). - Subcontract, form. Procedure on failure of subcontractor to execute subcontract. General bidder's responsibilities.

Section 4b-97. (Formerly Sec. 4-126c). - Arbitration of public works contracts.

Section 4b-98, 4b-98a and 4b-99. - Definitions. Large public building projects; bidding procedures, contracts and payrolls. Construction management services; invitation of responses and contracts for; regulations.

Section 4b-100. - Regulations.

Section 4b-100a. - Construction services award panels. Screening, interview and selection of contractors. Memoranda re selection. Regulations.

Section 4b-101. - Information re contractors and subcontractors to be provided to Commissioner of Revenue Services.

Section 4b-101a. - Awarding authorities to prepare report on status of certain projects and property management contracts. When.

Section 4b-102. - Bidding for certain construction contracts for the Connecticut State University System.

Section 4b-103. - Construction manager at-risk project delivery contracts.